Azerbaijan Wind IPP is a wind farm under development in Chayli, Absheron District, Absheron Economic Region, Azerbaijan.
Project Details
Table 1: Phase-level project details for Azerbaijan Wind IPP
Phase name | Status | Nameplate capacity | Mount type | Owner | Operator |
---|---|---|---|---|---|
Chayli | Development[1] | 120 MW[1] | Onshore | ACWA Power Azerbaijan Renewable Energy LLC[1] | NOMAC[1] |
Sitalchay | Development[1] | 120 MW[1] | Onshore | ACWA Power Azerbaijan Renewable Energy LLC[1] | NOMAC[1] |
Location
Table 2: Phase-level location details for Azerbaijan Wind IPP
Phase name | Location | Coordinates (WGS 84) |
---|---|---|
Chayli | Chayli, Absheron District, Absheron Economic Region, Azerbaijan[2][1] | 40.2258, 48.9107 (approximate)[1] |
Sitalchay | Sitalchay, Khizi District, Absheron Economic Region, Azerbaijan[3][4][1] | 40.7917, 49.427 (approximate)[1] |
The map below shows the approximate locations of the wind farm phases:
Background
Articles and Resources
Additional data
To access additional data, including an interactive map of global wind farms, a downloadable dataset, and summary data, please visit the Global Wind Power Tracker on the Global Energy Monitor website.
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 "ACWA POWER". ACWA Power. Archived from the original on June 18, 2021. Retrieved June 22, 2021.
- ↑ "Absheron District". Wikipedia. March 15, 2022. Archived from the original on March 22, 2022. Retrieved April 13, 2022.
- ↑ "Azerbaijan Wind IPP". ACWA Power. Archived from the original on April 6, 2022. Retrieved April 13, 2022.
- ↑ "Khizi District". Wikipedia. May 27, 2021. Archived from the original on March 19, 2022. Retrieved April 13, 2022.