Çalışkan Ceyhan power station (Ceyhan Termik Santrali) is a cancelled power station in Sarımazı, Ceyhan, Adana, Türkiye.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Çalışkan Ceyhan power station Sarımazı, Ceyhan, Adana, Türkiye 36.93815, 35.99446 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 36.93815, 35.99446

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 cancelled coal - unknown 660 supercritical
Unit 2 cancelled coal - unknown 660 supercritical

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Çalışkan Enerji [100.0%]
Unit 2 Çalışkan Enerji [100.0%]

Project-level coal details

  • Coal source(s): imported

Background

In September 2014, Çalışkan Enerji applied for environmental permits to build a two-unit coal-fired power plant with a total planned capacity of 1,320 MW in Adana Province. The project would cost about 2 billion lira, or about $760 million. The company hopes to begin construction in 2017, and complete the plant in 2021.[1][2] Public hearings on the Çalışkan Ceyhan EIA were held in January 2015.[3]

As of June 2019, with no further progress in over four years, the project appears to be cancelled.

Protests

In January 2015, local residents held a forum to organize protests against the proposed plant.[4]

Articles and Resources

References

  1. CEYHAN İTHAL KÖMÜRE DAYALI TERMİK SANTRALİ VE KÜL DEPOLAMA ALANI PROJESİ: ÇEVRESEL ETKI DEĞERLENDIRMESI BASVURU DOSYASI (Environmental Impact Assessment Application File), ARMADA Eğitim ve Belgelendirme Danışmanlık Mühendislik Enerji Denizcilik, 29 Sept. 2014.
  2. Ceyhan Termik ÇED raporu halkın görüşüne açıldı, Enerji Günlügü, 10 Dec. 2014.
  3. Ceyhan'da Termik Santraller İçin ÇED Toplantısı, Milliyet, 14 Jan. 2015.
  4. Çalışkan Enerji Ceyhan’da protesto edildi, Yumurtalık Haber, 27 Jan. 2015.

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.