Jilin Steel Group Taihua Metal Equipment Manufacture Co Ltd
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Jilin Steel Group Taihua Metal Equipment Manufacture Co., Ltd. (吉林吉钢钢铁集团泰华冶金设备制造有限公司), also known as Jilin Jigang Huaying Heavy Industry Technology Development Co., Ltd., is a 500 thousand tonnes per annum (TTPA) electric arc furnace (EAF) steel plant operating in Changchun, Jilin, China.
Location
The map below shows the location of the steel plant in Changchun, Jilin, China.
- Location: Zone B, Industrial Concentration Zone, Jiutai City, Changchun City, Jilin Province[1]
- Coordinates (WGS 84): 44.138826, 125.914941 (exact)
Background
According to the announcement of the production capacity replacement plan, the company plans to build a 70-ton Consti electric furnace, which is planned to be put into operation in 2024 and eliminate the existing 70-ton electric furnace.[2]
Plant Details
Table 1: General Plant Details
Plant status | Start date | Closed date |
---|---|---|
operating[1] | 2008[1] | 2024[3] |
Table 2: Ownership and Parent Company Information
Parent company | Parent company PermID | Owner | Owner company PermID |
---|---|---|---|
Jilin Jigang Steel Group Co., Ltd. [98.8%]; Other [1.2%][1] | GEM0000343 [98.8%]; GEM0000000 [1.2%] | Jilin Steel Group Taihua Metal Equipment Manufacture Co., Ltd.[1] | GEM0000127 |
Table 3: Process and Products
Steel product category | Steel products | Main production equipment | Detailed production equipment |
---|---|---|---|
finished rolled[1] | rebar[1] | electric arc furnace (EAF)[3] | 1 EAF (1x70-tonne)[3] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum):
Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|
500 TTPA[3] | 500 TTPA |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 https://web.archive.org/web/20220318081008/https://www.qcc.com/firm/49a882c6f3f28a6717263d6f60f04780.html. Archived from the original on 2022-03-18.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 吉林吉钢钢铁集团泰华冶金设备制造有限公司原厂区升级改造产能置换方案公告,吉林省工业和信息化厅,2022-1-21
- ↑ 3.0 3.1 3.2 3.3 https://web.archive.org/web/20220319191644/http://gxt.jl.gov.cn/xxgk/jwwj/202112/t20211223_8340764.html. Archived from the original on 2022-03-19.
{{cite web}}
: Missing or empty|title=
(help)