Yangguang power station (神华阳光神木发电厂) is a retired power station in Dianta Town, Shenmu, Yulin, Shaanxi, China. It is also known as Shenhua Yangguang power station.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Yangguang power station | Dianta Town, Shenmu, Yulin, Shaanxi, China | 38.979897, 110.448794 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 38.979897, 110.448794
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Unit 1 | retired | coal - unknown | 135 | subcritical | 2006 | 2018 |
Unit 2 | retired | coal - unknown | 135 | subcritical | 2006 | 2018 |
Table 3: Unit-level ownership and operator details
Unit name | Owner |
---|---|
Unit 1 | Shaanxi Shenmu Power Generation Co Ltd of National Energy Group [100.0%] |
Unit 2 | Shaanxi Shenmu Power Generation Co Ltd of National Energy Group [100.0%] |
Background
The Yangguang power station was commissioned in 2006, with construction beginning in 2004.[1] Ash storage for the facility was added in 2007,[2] and in 2011 the operating managers opened a domestic public bid to transform the 110kV transmission line of the 2×135MW power plant.[3] In 2019, the Shenmu Environmental Protection Bureau, in their response to the power plant's annual environmental impact report, mandated that the plant strengthen the environmental management work during construction periods, take effective measures to control the dust, waste water, noise pollution, standard disposal of solid waste generated during construction, after the completion of construction, and restore vegetation on temporarily occupied land. It also asked for the boiler flue gas to be desulfurized and to add a high-efficiency filter after treatment, among other things.[4]
The power station was ordered to shutdown in 2018.[5] Based on Planet satellite imagery, it may have continued to operate until around mid-2019.
Articles and Resources
References
- ↑ "神华阳光神木发电有限责任公司-钉钉企业". DingTalk. Retrieved 2021-06-01.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "神华阳光神木发电2×135MW煤矸石发电厂二期贮灰场工程招标_其它_招标信息_交互式水专项成果公共服务信息平台". E20 Environmental Platform. May 31, 2010. Retrieved 2021-06-01.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "神华阳光神木发电公司2×135MW电厂110kV送出线路改造工程-北极星输配电网". shupeidian.bjx.com.cn. June 22, 2011. Retrieved 2021-06-01.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 神木市环境保护局 (2019). "环境影响报告表的批复" (PDF). SXSM. Retrieved May 31, 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 关于印发陕西省2018年度主要污染物总量减排实施方案的通知, shaanxi.gov, 2018
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.