Al-Khairat-2 power station (محطة كهرباء الخيرات البخارية) is a power station under construction in Khairat, Kerbala, Iraq.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Al-Khairat-2 power station Khairat, Kerbala, Iraq 32.65097, 43.98164 (approximate)[1]

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Retired year
Unit 1-1 construction[2][3][4] fuel oil[2][3][5] 350[2][3][6][7] steam turbine[5] not found not found
Unit 1-2 construction[2][3][4] fuel oil[2][3][5] 350[2][3][7] steam turbine[5] not found not found
Unit 1-3 construction[2][3][6][4] fuel oil[2][3][5] 350[2][3][7] steam turbine[5] not found not found
Unit 1-4 construction[2][3][4] fuel oil[2][3][5] 350[2][3][7] steam turbine[5] not found not found
Unit 2-1 construction[2][3][4] fuel oil[2][3][5] 350[2][3][7] steam turbine[5] not found not found
Unit 2-2 construction[2][3][4] fuel oil[2][3][5] 350[2][3][7] steam turbine[5] not found not found
Unit 2-3 construction[2][3][4] fuel oil[2][3][5] 350[2][3][7] steam turbine[5] not found not found
Unit 2-4 construction[2][3][4] fuel oil[2][3][5] 350[2][3][7] steam turbine[5] not found not found

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1-1 Iraq Ministry of Electricity[2] Iraq Ministry of Electricity [100.0%]
Unit 1-2 Iraq Ministry of Electricity[2] Iraq Ministry of Electricity [100.0%]
Unit 1-3 Iraq Ministry of Electricity[2] Iraq Ministry of Electricity [100.0%]
Unit 1-4 Iraq Ministry of Electricity[2] Iraq Ministry of Electricity [100.0%]
Unit 2-1 Iraq Ministry of Electricity[7] Iraq Ministry of Electricity [100.0%]
Unit 2-2 Iraq Ministry of Electricity[7] Iraq Ministry of Electricity [100.0%]
Unit 2-3 Iraq Ministry of Electricity[7] Iraq Ministry of Electricity [100.0%]
Unit 2-4 Iraq Ministry of Electricity[7] Iraq Ministry of Electricity [100.0%]

Project-level captive use details

  • Captive industry use (heat or power): power[8]
  • Captive industry: Oil & Refining[8]

Background

In 2020 Hyundai was chosen to build the second Al-Khairat power plant.[9] In 2021, that decision appeared to change when the Iraq Council of Ministers approved the decision to give the contract to Harlow International Corporation.[10]

Articles and Resources

References

  1. https://web.archive.org/web/20220819210839/https://ashourland.net/2021/02/23/%D8%A7%D9%84%D9%86%D8%A7%D8%A6%D8%A8-%D8%AC%D9%85%D8%A7%D9%84-%D8%A7%D9%84%D9%85%D8%AD%D9%85%D8%AF%D8%A7%D9%88%D9%8A-%D8%A7%D8%AD%D8%A7%D9%84%D8%A9-%D9%85%D8%AD%D8%B7%D8%A9-%D9%83%D9%87%D8%B1%D8%A8/. Archived from the original on 19 August 2022. {{cite web}}: Missing or empty |title= (help)
  2. 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 2.19 2.20 2.21 2.22 2.23 2.24 2.25 2.26 2.27 https://web.archive.org/web/20220709091250/https://www.mubasher.info/news/3893980/%D8%AD%D9%83%D9%88%D9%85%D8%A9-%D8%A7%D9%84%D8%B9%D8%B1%D8%A7%D9%82-%D8%AA-%D9%82%D8%B1-%D8%AA%D9%88%D8%B5%D9%8A%D8%A9-%D9%88%D8%A5%D8%AC%D8%B1%D8%A7%D8%A1%D8%A7%D8%AA-%D8%AC%D8%AF%D9%8A%D8%AF%D8%A9-%D8%A8%D8%B4%D8%A3%D9%86-%D9%85%D8%B4%D8%B1%D9%88%D8%B9-%D9%85%D8%AD%D8%B7%D8%A9-%D9%83%D9%87%D8%B1%D8%A8%D8%A7%D8%A1-%D8%A7%D9%84%D8%AE%D9%8A%D8%B1%D8%A7%D8%AA-%D8%A7%D9%84%D8%A8%D8%AE%D8%A7%D8%B1%D9%8A%D8%A9/. Archived from the original on 09 July 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  3. 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 3.12 3.13 3.14 3.15 3.16 3.17 3.18 3.19 3.20 3.21 3.22 3.23 https://web.archive.org/web/20221006090624/https://www.iraq-businessnews.com/2021/11/01/citic-construction-wins-3-7bn-iraq-power-deal/. Archived from the original on 06 October 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 https://www.alsumaria.tv/news/localnews/437168/%D9%85%D8%B1%D8%A7%D9%82%D8%A8%D9%88%D9%86-%D9%8A%D8%B7%D8%A7%D9%84%D8%A8%D9%88%D9%86-%D8%B1%D8%A6%D9%8A%D8%B3-%D8%A7%D9%84%D9%86%D8%B2%D8%A7%D9%87%D8%A9-%D8%A7%D9%84%D8%AC%D8%AF%D9%8A%D8%AF-%D8%A8%D8%A7%D9%84%D8%AA%D8%AD%D9%82%D9%8A%D9%82-%D9%81%D9%8A-%D9%85%D8%B4 https://www.bncnetwork.net/project/MOE-Al-Khairat-Power-Plant/MTg1NDQ4/، https://www.alsumaria.tv/news/localnews/437168/%D9%85%D8%B1%D8%A7%D9%82%D8%A8%D9%88%D9%86-%D9%8A%D8%B7%D8%A7%D9%84%D8%A8%D9%88%D9%86-%D8%B1%D8%A6%D9%8A%D8%B3-%D8%A7%D9%84%D9%86%D8%B2%D8%A7%D9%87%D8%A9-%D8%A7%D9%84%D8%AC%D8%AF%D9%8A%D8%AF-%D8%A8%D8%A7%D9%84%D8%AA%D8%AD%D9%82%D9%8A%D9%82-%D9%81%D9%8A-%D9%85%D8%B4. {{cite web}}: Check |url= value (help); Missing or empty |title= (help)
  5. 5.00 5.01 5.02 5.03 5.04 5.05 5.06 5.07 5.08 5.09 5.10 5.11 5.12 5.13 5.14 5.15 https://web.archive.org/web/20230116064734/https://www.enerdata.net/publications/daily-energy-news/chinas-citic-group-will-build-and-operate-32-gw-oil-fired-project-iraq.html. Archived from the original on 16 January 2023. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 https://www.bncnetwork.net/project/MOE-Al-Khairat-Power-Plant/MTg1NDQ4/. {{cite web}}: Missing or empty |title= (help)
  7. 7.00 7.01 7.02 7.03 7.04 7.05 7.06 7.07 7.08 7.09 7.10 7.11 https://www.alsumaria.tv/news/localnews/437168/%D9%85%D8%B1%D8%A7%D9%82%D8%A8%D9%88%D9%86-%D9%8A%D8%B7%D8%A7%D9%84%D8%A8%D9%88%D9%86-%D8%B1%D8%A6%D9%8A%D8%B3-%D8%A7%D9%84%D9%86%D8%B2%D8%A7%D9%87%D8%A9-%D8%A7%D9%84%D8%AC%D8%AF%D9%8A%D8%AF-%D8%A8%D8%A7%D9%84%D8%AA%D8%AD%D9%82%D9%8A%D9%82-%D9%81%D9%8A-%D9%85%D8%B4. {{cite web}}: Missing or empty |title= (help)
  8. 8.0 8.1 https://web.archive.org/web/20221207123548/https://www.iraq-businessnews.com/2020/07/30/hyundai-to-build-al-khairat-power-station/. Archived from the original on 07 December 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  9. Hyundai to Build Al-Khairat Power Station, Iraq Business News, Jul 30, 2020
  10. A consortium led by Iraqi-owned Harlow International is expected to implement the project, Power Technology, Feb 26, 2021

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.