Asam-Asam power station
This article is part of the CoalSwarm coverage of Indonesia and coal |
Sub-articles: |
Related articles: |
Asam-Asam power station, also known as Banjarmasin or Kalselteng-2, is a 260-megawatt (MW) coal-fired power plant in South Kalimantan Province, Indonesia. A 200 MW expansion has been proposed.
Location
The map below shows the Asam-Asam power station, in Jorong District, Tanah Laut Regency, South Kalimantan Province.[1]
Background on Plant
The Asam-Asam power station consists of four units: the two-unit, 130-MW Banjarmasin Asam-Asam-A plant, built in 2000; and the two-unit, 130-MW Kalsel Asam-Asam plant, built in 2013.[2] All four existing units are owned by PLN.
Damage to Plant
In June 2016 the plant suffered damage to its control system that led to blackouts in some areas of South and Central Kalimantan. The problems were blamed on postponement of maintenance due to Ramadan. A team of experts from Japan was working to fix the damage.[3]
Proposed Expansion
PLN is currently planning to add two more 100-MW units, known as the Banjarmasin Asam-Asam-B power station; the two additional units are described in the media at Units 5 & 6 of the Asam-Asam plant or Units 5&6 of Kalselteng-2. The original plan was apparently to build three additional units; this plan was scrapped due to various problems, including investors withdrawing from the project. In May 2013, though, the project was reborn, but now as two rather than three units.[4]
According to an October 2013 report, development of the project "is still waiting for a letter of feasibility of PT PLN (Persero) from the government." The report continued: "Garibaldi Thohir, President Director of Adaro Energy, said the government’s guarantee is needed because even as Independent Power Producer (IPP), South Kalimantan coal power plant is including on Public Private Partnership (PPP) project scheme."[5]
As of January 2015, South Kalimantan government officials were urging PLN to accelerate the expansion project, in order to help prevent blackouts in the area.[6]
In November 2015, it was reported that two units of 100 MW each had been pre-qualified for tender.[7]
In February 2016, the project entered the auction process. The process was considered likely to finish in 2016, but PLN officials stressed that success was not a certainty.[3]
Construction began in July 2017. Commercial operation of Units 5 and 6 is planned for July and October 2020.[8] In February 2020 it was reported that hundreds of construction workers who had been building the expansion had been laid off and that construction was stalled.[9]
Financing
On July 31, 2017, ITOCHU Corporation announced that it had concluded an EPC (Engineering, Procurement, and Construction) agreement for the Kalselteng-2 Units 5 & 6 project.[10] The Japan Bank for International Cooperation (JBIC) and MUFG Bank agreed to cofinance the project with approximately US$241 million in loans. JBIC is providing JPY10.1 billion and US$53 million in loans (for a total of approximately US$144 million), and MUFG is providing JPY6.8 billion and US$36 million in loans (for a total of approximately US$97 million). MUFG's portion of the financing is insured by Nippon Export and Investment Insurance.[11][12]
In October 2020 MUFG announced that it was planning to halve its overseas coal investments by 2030 and eliminate them by 2040.[13]
Project Details for Banjarmasin Asam-Asam-B Expansion
- Sponsor: Banjarmasin-B Project[5]
- Parent company: PLN[5]
- Location: Jorong District, Tanah Laut Regency, South Kalimantan Province, Indonesia
- Coordinates: -3.9271088, 115.1068497 (exact)
- Status: Construction
- Gross Capacity: 200 MW (Units 5 & 6: 100 MW)
- Type:
- Start date: 2022[14]
- Coal Type:
- Coal Source:
- Source of financing: US$241 million in debt from Japan Bank for International Cooperation and MUFG Bank[11][12]
Articles and resources
References
- ↑ PLTU Asam Asam, Wikimapia, accessed February 2013
- ↑ PLN Siapkan 2 PLTU Baru, Banjarmasin Post, 26 Oct. 2013.
- ↑ 3.0 3.1 "PLN Invites Japanese Experts to Fix Asam-asam Steam Power Plant," Media Indonesia, 20 June 2016
- ↑ PLTU Unit Lima Dan Enam Siap Dibangun, Kalimantan News, 27 May 2013.
- ↑ 5.0 5.1 5.2 Wilda Asmarini, "Adaro-Korea Power Plant Project Awaits Government's Guarantee," Indonesia Finance Today, October 25, 2013
- ↑ Ayo Percepat Pembangunan PLTU Baru, Banua Online, 16 Jan. 2015.
- ↑ "Tender Info: PLN Prequalifies EPC of Sulsul Barr-2 Kalselteng-2 Coal-Fired Steam Power Plants," RambuEnergy, November 15, 2015
- ↑ "Kalselteng-2 Coal-Fired Power Plant Project," Energy Central, August 7, 2017
- ↑ Ratusan Pekerja Proyek PLTU Asam-Asam Unit 5-6 Dirumahkan, kalsel.prokal.co, Feb. 15, 2020
- ↑ "ITOCHU Announces EPC Agreement for Coal Fired Power Plant in Indonesia," ITOCHU press release, July 31, 2017
- ↑ 11.0 11.1 Buyer's Credit for National Power Company of Indonesia, Japan Bank for International Cooperation, June 21, 2017
- ↑ 12.0 12.1 Republic of Indonesia / Loan Insurance for Kalselteng 2 Coal-fired Power Plant Project, Nippon Export and Investment Insurance, June 21, 2017
- ↑ MUFG to Join Rivals in Phasing Out Coal Power Financing, Bloomberg Law, Oct. 15, 2020
- ↑ Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2021-2030, PT PLN Persero