Caculo Cabaca hydroelectric plant is a hydroelectric power plant under construction in São Pedro da Quilemba, Cuanza Norte, Angola.

Project Details

Table 1: Project details for Caculo Cabaca hydroelectric plant

Status Commissioning year Nameplate capacity Turbines Technology type Owner
Construction[1] 2026 (planned)[1] 2040 MW[2] 5[3] Run-of-river[3] China Gezhouba Group CO LTD[4]

Location

Table 2: Location details for Caculo Cabaca hydroelectric plant

Location River Coordinates (WGS 84)
São Pedro da Quilemba, São Pedro da Quilemba, Cuanza Norte, Cuanza Norte, Angola[3] Kwanza River[5] -9.7296, 14.8163 (approximate)[3]

The map below shows the approximate location of the hydroelectric power plant:

Loading map...

Articles and Resources

Additional data

To access additional data, including an interactive map of global nuclear power plants, a downloadable dataset, and summary data, please visit the Global Hydropower Tracker on the Global Energy Monitor website.

References

  1. 1.0 1.1 https://web.archive.org/web/20230605123046/https://www.afrik21.africa/en/angola-chinas-cggc-launches-work-on-the-caculo-cabaca-dam-2-gw/. Archived from the original on 05 June 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  2. (PDF) https://web.archive.org/web/20220914174943/http://www.ppa.pt/wp-content/uploads/2018/03/3.-COBAgroup_DAMS_EN_pen_APS.pdf. Archived from the original (PDF) on 14 September 2022. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 https://web.archive.org/web/20220914175332/https://www.nsenergybusiness.com/projects/caculo-cabaca-hydropower-project/. Archived from the original on 14 September 2022. {{cite web}}: Missing or empty |title= (help)
  4. https://web.archive.org/web/20211020093430/https://www.hydroreview.com/world-regions/angolan-officials-break-ground-on-2-170-mw-caculo-cabaca-hydropower-plan-generation-begins-at-2-070-mw-lauca/. Archived from the original on 20 October 2021. {{cite web}}: Missing or empty |title= (help)