Xinyang power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Xinyang power station (信阳发电厂) is an operating power station of at least 1940-megawatts (MW) in Pingqiao, Xinyang, Henan, China with multiple units, some of which are not currently operating. It is also known as 陕煤信电2×1000MW高效超超临界机组工程, 信阳发电公司 (Phase I Unit 1 & 2), 陕煤信阳2×1000MW高效超超临界机组项目 (Unit 1 & 2), 华豫发电公司 (Phase II Unit 3 & 4).
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Xinyang power station | Pingqiao, Xinyang, Henan, China | 32.109018, 114.140877 (exact)[1] |
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4, Unit 1, Unit 2: 32.109018, 114.140877
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Phase I Unit 1 | Operating | coal: bituminous[2] | 300 | subcritical | yes | 2001 | False |
| Phase I Unit 2 | Operating | coal: bituminous[2] | 320 | subcritical | yes | 2001 | False |
| Phase II Unit 3 | Operating | coal: bituminous[2] | 660 | ultra-supercritical | – | 2009 | False |
| Phase II Unit 4 | Operating | coal: bituminous[2] | 660 | ultra-supercritical | – | 2009 | False |
| Unit 1 | Construction[3][1] | coal: bituminous[2][1] | 1000[1] | ultra-supercritical[1] | – | 2025 (planned) | False |
| Unit 2 | Construction[3][1] | coal: bituminous[2][1] | 1000[1] | ultra-supercritical[1] | – | 2026 (planned) | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase I Unit 1 | Shaanxi Coal Power Xinyang Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [51.2%]; China Datang Corp Ltd [48.2%]; unknown [0.6%] |
| Phase I Unit 2 | Shaanxi Coal Power Xinyang Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [51.2%]; China Datang Corp Ltd [48.2%]; unknown [0.6%] |
| Phase II Unit 3 | Datang Xinyang Huayu Power Generation Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [51.3%]; China Datang Corp Ltd [48.3%]; unknown [0.4%] |
| Phase II Unit 4 | Datang Xinyang Huayu Power Generation Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [51.3%]; China Datang Corp Ltd [48.3%]; unknown [0.4%] |
| Unit 1 | Shaanxi Coal Power Xinyang Co Ltd [100%][1] | Shaanxi Coal and Chemical Industry Co Ltd [51.2%]; China Datang Corp Ltd [48.2%]; unknown [0.6%] |
| Unit 2 | Shaanxi Coal Power Xinyang Co Ltd [100%][1] | Shaanxi Coal and Chemical Industry Co Ltd [51.2%]; China Datang Corp Ltd [48.2%]; unknown [0.6%] |
Project-level coal details
- Coal source(s): domestic
- Permit(s): 豫发改审批【2022】598[1]
Background
Xinyang power station is a four-unit coal-fired power plant with a total capacity of 1,920 MW. The plant was completed between 2001 and 2009, and is owned by China Datang (51%), Shaanxi Coal and Chemical Industry Group (48%), and Henan Investment Group (1%).[4]
2022: New proposal
In August 2022, a related 2 x 1,000 MW project was identified as a key project in Henan Province to "accelerate" the infrastructure construction and "stabilize" the economy (河南省全面加快基础设施建设稳住经济大盘重点项目).[5] Datang Xinyang Power Generation Co., Ltd. owns these two new units.
The Environmental Impact Assessment (EIA) was up for public review in October 2022.[6]
In 2023, a construction ceremony was held and the first concrete was poured, though the project appeared stalled.[7]
Throughout 2024 and 2025, the project progressed through tendering for major equipment and construction contracts.[8][9] The first steel for Unit 1 was hoisted in March 2025, and the chimney structure was topped out in September 2025.[10][11]
In 2026, the generator stator and rotor were installed, and the turbine was assembled.[12][13]
Articles and Resources
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 "信阳清洁高效电源点项目获省发改委批复". Xingyang.gov.cn. 2022-11-14. Archived from the original on 2024-01-25. Retrieved 2023-10-31.
- ↑ 2.0 2.1 2.2 2.3 2.4 2.5 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 "陕煤信电2×1000MW高效超超临界机组工程开工-北极星火力发电网". news.bjx.com.cn. 2023-12-28. Archived from the original on 2024-02-07. Retrieved 2024-01-03.
- ↑ Datang Xinyang Powerplant, Enipedia, accessed Sept. 2015.
- ↑ "83个电力能源项目!河南省全面加快基础设施建设稳住经济大盘重点项目清单发布【附名单】," BJX, 2022-08-10
- ↑ "关于信阳清洁高效电源点项目工程环境影响评价第一次公示," cjddsb, 2022-09-27
- ↑ "陕煤信电2×1000MW高效超超临界机组工程浇筑第一罐混凝土仪式顺利举行". BeiJiXing (BJX) News. 2023-12-28. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中国能建西北院中标陕煤信阳2×1000MW高效超超临界机组工程项目监理服务". BeiJiXing (BJX) News. 2024-05-17. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "陕煤信阳2×1000MW高效超超临界机组项目主体工程施工预中标公示". BeiJiXing (BJX) News. 2024-09-06. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "陕煤信阳2×1000兆瓦高效超超临界机组工程1号机组首根钢架顺利吊装". WeChat. 2025-03-18. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "陕煤信电公司2×1000MW高效超超临界机组工程烟囱主体结构顺利封顶". WeChat. 2025-09-17. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "陕煤信电百万机组1号发电机定子顺利吊装". WeChat. 2026-04-06. Retrieved 2026-06-02.
{{cite web}}: CS1 maint: url-status (link) - ↑ "陕煤信电2×1000MW项目1号机组汽轮机扣盖顺利完成". WeChat. 2026-07-16. Retrieved 2026-07-23.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.