Shengli Dongying power station is an operating power station of at least 1700-megawatts (MW) in 1502 Nan'er Road Wanquan Village, Dongying District, Dongying, Shandong, China with multiple units, some of which are not currently operating. It is also known as 中石化国电胜利东营热电 (Phase III Unit 5, Phase III Unit 6), 中石化胜利油田自备电厂 (Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Shengli Dongying power station | 1502 Nan'er Road Wanquan Village, Dongying District, Dongying, Shandong, China | 37.400318, 118.5242522 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase II Unit 4, Phase II Unit 3, Phase I Unit 2, Phase III Unit 5, Phase I Unit 1, Phase III Unit 6: 37.400318, 118.5242522
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Phase II Unit 4 | operating | coal - bituminous | 300 | subcritical | 2001 | – |
Phase II Unit 3 | operating | coal - bituminous | 300 | subcritical | 2000 | – |
Phase I Unit 2 | operating | coal - bituminous | 220 | subcritical | 1993 | – |
Phase III Unit 5 | operating | coal - bituminous | 660 | supercritical | 2015 | – |
Phase I Unit 1 | operating | coal - bituminous | 220 | subcritical | 1992 | – |
Phase III Unit 6 | cancelled | coal - bituminous | 660 | supercritical | – | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner |
---|---|
Phase II Unit 4 | China Sinopec Shengli Petroleum Administration Bureau [100.0%] |
Phase II Unit 3 | China Sinopec Shengli Petroleum Administration Bureau [100.0%] |
Phase I Unit 2 | China Sinopec Shengli Petroleum Administration Bureau [100.0%] |
Phase III Unit 5 | Shengli Guodian (Dongying) Thermalpower Co Ltd [100.0%] |
Phase I Unit 1 | China Sinopec Shengli Petroleum Administration Bureau [100.0%] |
Phase III Unit 6 | Shengli Guodian (Dongying) Thermalpower Co Ltd [100.0%] |
Project-level captive use details
- Captive industry use (heat or power): oil & refining
- Captive industry: Both
Project-level coal details
- Permit(s): May 28, 2012, March 22, 2016
Background
The four existing coal-fired units of Shengli Dongying power station, totaling 1,040 MW (Phase I and II), were brought online between 1992 and 2001. The plant is owned by Sinopec.[1]
Description of Expansion
Phase III of the Shengli Power Plant – two 660 MW supercritical thermal power units - was approved by the National Development and Reform Commission (NDRC) for construction in 2012. Unit 5 began construction in 2013, and was planned for completion around the middle of 2015.[1] Commissioning of unit 5 began in September 2015.[2]
Carbon capture
The space for a one million tonnes per annum CO2 capture plant was reserved at the site of the No. 5 Unit. The CO2 capture facilities were expected to begin operation in 2017. The CO2 would be used for enhanced oil recovery at the Shengli oil field, the second largest oil field in China, located in the Yellow River delta near the Bohai sea shore.[1]
Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity
In January 2017 China's National Energy Administration suspended over 100 planned and under-construction coal power projects in 13 provinces, including unit 6 of Shengli Dongying. It was unclear when or if the projects would be revived.[3]
For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.
Presumed cancelled
The phase III Unit 5 went operation in 2015, and although Unit 6 was mentioned for some time after its completion, it did not appear to be moving forward and was presumed cancelled after four years of slow to no development.
Ownership
On August 28, 2017, China's State-owned Assets Supervision and Administration Commission of the State Council (SASAC) announced that China Guodian Corporation and Shenhua Group will be jointly restructured. Shenhua Group will become China National Energy Investment Group and will absorb China Guodian Corporation. It will be the largest power company in the world by installed capacity, as well as the world's largest coal producer.[4][5] The merger was completed on November 28, 2017.[6]
Articles and Resources
References
- ↑ 1.0 1.1 1.2 "Sinopec Shengli Power Plant CCS Project (formerly Sinopec Shengli Oil Field EOR Project (Phase 2))," Global CCS, updated July 2014
- ↑ "胜利油田电厂三期首台机组点火成功," Sinopec, 2015/9/8
- ↑ "能源局下发13省市新建火电机组停建清单(附文件)," Polaris, Jan 16, 2017
- ↑ "Factbox: Shenhua and Guodian - China's latest state marriage". Reuters. 29 August 2017. Retrieved 30 August 2017.
- ↑ "China Is Creating the World's Largest Power Company". Bloomberg News. 28 August 2017. Retrieved 29 August 2017.
- ↑ "China’s Newly-Established National Energy Investment Group Sets World Records in Its Sector, With Assets of Over CNY1.8 Trillion," Yicai Global, 11-28-2017
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.