El Oued-Taleb El Arbi Gas Pipeline is a cancelled natural gas pipeline in Algeria.[1] As of October 2021, there had been no evidence for progress since 2019, and the project is considered shelved.

Location

The pipeline runs from El Oued through Hassi Khelifa to Taleb Larbi in Algeria.[2]

Loading map...

Project details

  • Operator: Société Algérienne de Gestion du Réseau de Transport du Gaz (GRTG)[1]
  • Owner:
  • Capacity:
  • Length: 110 kilometers[1]
  • Diameter: 16 inches[1]
  • Status: cancelled
  • Start year:
  • Cost:
  • Financing:
  • Associated infrastructure:

Background

The project was listed in the 2017-2020 Ten Year Development Plan of La Société Algérienne de Gestion du Réseau de Transport (GRTG), with construction intended to begin in 2020.

The 2019 GRTG Gas Transport Network Map listed the project as in development as of January 2018,[2] with an expectation that 43.8 kilometers would be built in 2020, 43.8 kilometers in 2021, and 21.9 kilometers in 2022. However, as of October 2021, there was no evidence for further development or construction of the project, and it is therefore considered shelved.

Articles and resources

References

  1. 1.0 1.1 1.2 1.3 Société Algérienne de Gestion du Réseau de Transport du Gaz (2017). "Plan de développement du Réseau de Transport du Gaz 2017-2027" (PDF). grtg.dz. Retrieved September 22, 2020.{{cite web}}: CS1 maint: url-status (link)
  2. 2.0 2.1 "GRTG || Société Algérienne de Gestion du Réseau de Transport du Gaz". www.grtg.dz. Retrieved 2020-09-23.

Related GEM.wiki articles

External resources

External articles