Jiangling power station (江陵发电厂) is an operating power station of at least 1980-megawatts (MW) in Majiazhai Town, Jiangling, Jingzhou, Hubei, China with multiple units, some of which are not currently operating. It is also known as 湖北能源江陵发电厂 (Phase II Unit 3 & 4), 湖北能源江陵电厂二期扩建(2×660MW)工程项目, 华电江陵发电厂 (Phase I Unit 1 & 2).
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Jiangling power station | Majiazhai Town, Jiangling, Jingzhou, Hubei, China | 30.091187, 112.310588 (exact)[1] |
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 30.091187, 112.310588
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Phase I Unit 1 | Operating | coal: unknown[2] | 660 | ultra-supercritical | – | 2017 | False |
| Phase I Unit 2 | Operating | coal: unknown[2] | 660 | ultra-supercritical | – | 2018 | False |
| Phase II Unit 3 | Operating[3][1] | coal: unknown[2][1] | 660[1] | ultra-supercritical[1] | yes[4] | 2026[3] | False |
| Phase II Unit 4 | Construction[1] | coal: unknown[2][1] | 660[1] | ultra-supercritical[1] | yes[4] | – | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase I Unit 1 | Hubei Huadian Jiangling Power Generation Co Ltd [100%] | Huadian Power International Co Ltd [82.6%]; unknown [17.4%] |
| Phase I Unit 2 | Hubei Huadian Jiangling Power Generation Co Ltd [100%] | Huadian Power International Co Ltd [82.6%]; unknown [17.4%] |
| Phase II Unit 3 | Hubei Energy Group Jiangling Power Generation Co Ltd [100%][1] | Hubei Energy Group Co Ltd [100.0%] |
| Phase II Unit 4 | Hubei Energy Group Jiangling Power Generation Co Ltd [100%][1] | Hubei Energy Group Co Ltd [100.0%] |
Project-level coal details
- Coal source(s): domestic/imported
- Permit(s): 鄂发改审批服务〔2022〕393号[5]
Background on Project
In 2013, China Huadian said it was planning to build a four-unit coal-fired power plant with a total planned capacity of 3,320 MW in Hubei Province.[6]
Units 1 & 2
The first two 660 MW units of the plant were initially scheduled to begin construction in 2014.[7][8]
The two units were permitted for construction in June 2015,[9] and began construction in September 2015. They are planned for completion in 2017.[10]
Unit 1 was commissioned on December 31, 2017.[11]
July 2017: Unit 2 postponed by government
In July 2017, the NEA released the "Guideline of Supply-Side Reform of the Coal Power Bubble". The Guideline included a draft list which slowed down or halted 185 coal-burning units across 21 provinces, totaling 107 GW. 114 coal units (65 GW) are ordered to slow down the construction progress during 2017 to 2020, and are not allowed to connect to the grid in 2017. In addition, 71 coal units (42 GW) were halted indefinitely for regulation violations. The list partly overlapped with the projects listed in the January NEA letter to 13 provinces.[12]
Jiangling power station Unit 2 is among the postponed coal-burning units,[12] and also appeared on an updated list of postponed projects released in September 2017.[13]
August 2018: Unit 2 commissioned
Unit 2 was commissioned in August 2018.[14]
Units 3 & 4
2016: Shelved by Nationwide Restrictions
Due to new restrictions announced during 2016 by the National Energy Administration and the National Development and Reform Commission, further capacity expansions at this location appear to be on hold or cancelled.
For more information, see China's 2016/2017 Restrictions on Development of Coal-Fired Power Capacity.
2022: Revived
On November 2, 2022, two units known as the Hubei Energy Jiangling Power Plant Phase II Expansion (2×660MW) Project were permitted.[15] Units 3 & 4 are owned by Hubei Energy Group Co., Ltd.
In March 2025, Phase II Unit 3 cooling tower topped out and Unit 4 turbine hall completed roofing[16]. Transformer installation occurred in April 2025[17]. Boiler hydrostatic test passed in July 2025[18]. Generator stator placement completed in August 2025[19]. Unit 3 generator rotor placement occurred in September 2025[20]. Unit 3 synchronized to grid in December 2025[21].
In February 2026, Unit 3 completed 168-hour trial run[22]. Heating engineering bidding was announced in March 2026, with contract awarded in April 2026[23][24].
Boiler steel frame placement for Phase II Unit 4 occurred in August 2024, and beam placement in February 2025[25][26]. Generator stator hoisting completed in October 2025[27]. Unit 4 synchronization to grid occurred in May 2026[28]. Commercial operation achieved in July 2026 after 168-hour trial run[29].
Articles and Resources
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 "开工!湖北省最先进的600MW级绿色节能型火力发电厂项目-北极星火力发电网". news.bjx.com.cn. 2024-04-18. Archived from the original on 2024-04-20. Retrieved 2024-04-18.
- ↑ 2.0 2.1 2.2 2.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 https://news.bjx.com.cn/html/20260210/1483597.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 https://news.bjx.com.cn/html/20260409/1491237.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ https://news.bjx.com.cn/html/20221103/1265933.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ "湖北省委常委、常务副省长王晓东到江陵发电厂项目现场调研", 中国华电集团公司, 2013-12-16
- ↑ "湖北华电江陵发电厂一期工程可行性研究报告通过审查", 荆州新闻网, 2013-12-15
- ↑ "国家节能中心评审湖北华电江陵发电厂一期工程", 西部节能网, 2014-05-15
- ↑ "华电江陵一期2台66万千瓦高效环保火电获核准," 中电新闻网, 2015年6月20日
- ↑ "华电江陵电厂一期工程开工," 2015-9-29
- ↑ "总投资47.59亿元 湖北华电江陵电厂一期工程1号机组投产," 湖北日报, 2018/1/2
- ↑ 12.0 12.1 "16部委联合发文防范化解煤电产能过剩风险," Sohu.com, 2017-08-03
- ↑ "2017年分省煤电停建和缓建项目名单," Sohu, 2017-10-12
- ↑ "高标准!江陵发电厂一期工程全面投产," CEEC, 2018-08-23
- ↑ "湖北能源江陵电厂二期扩建(2×660MW)工程获得核准," BJX News, 2022-11-03
- ↑ "湖北能源江陵电厂二期扩建(2×660兆瓦)工程项目1号冷却塔筒身顺利到顶、2号汽机房顺利完成屋面断水". 微信公众平台. 2025-03-09. Retrieved 2025-03-24.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵电厂二期扩建(2×660兆瓦)工程项目1号主变压器顺利就位". 北极星电力网. 2025-04-05. Retrieved 2025-04-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵电厂二期扩建(2×660兆瓦)工程项目1号机组锅炉水压试验一次成功". 微信公众平台. 2025-07-20. Retrieved 2025-07-31.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵电厂二期扩建2×660兆瓦工程项目1号机组定子吊装就位". 北极星电力网. 2025-08-08. Retrieved 2025-08-14.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵电厂二期扩建(2×660兆瓦)工程项目1号机组发电机转子穿装一次成功". 微信公众平台. 2025-09-11. Retrieved 2025-11-05.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵火电(2×660兆瓦)项目1号机组成功并入电网". 北极星电力网. 2025-12-24. Retrieved 2025-12-25.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵火电项目1号机组顺利完成168小时满负荷试运行". 微信公众平台. 2026-02-09. Retrieved 2026-03-04.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵电厂二期扩建2×660MW工程项目供热工程招标". 北极星电力网. 2026-03-04. Retrieved 2026-03-04.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵电厂二期扩建(2×660MW)工程项目供热工程中标公示". 北极星电力网. 2026-04-09. Retrieved 2026-04-09.
{{cite web}}: CS1 maint: url-status (link) - ↑ "建设公司江陵电厂二期2号机组锅炉首根钢架顺利吊装就位". 微信公众平台. 2024-08-15. Retrieved 2024-11-01.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵电厂二期扩建(2X660兆瓦)工程项目2号机组锅炉大板梁顺利吊装". 微信公众平台. 2025-02-16. Retrieved 2025-03-24.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵电厂二期扩建(2×660兆瓦)工程项目2号机组发电机定子顺利吊装就位". 微信公众平台. 2025-10-11. Retrieved 2025-11-05.
{{cite web}}: CS1 maint: url-status (link) - ↑ "湖北能源江陵火电项目2号机组首次并网成功,进入带负荷试运行阶段". 微信公众平台. 2026-05-28. Retrieved 2026-06-03.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江陵电厂二期扩建(2×660MW)项目2号机组顺利通过168小时满负荷试运行,正式投入商业运营". 北极星电力网. 2026-07-27. Retrieved 2026-07-27.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.