Nanxiong power station (华电韶关南雄上大压小热电联产) is an operating power station of at least 700-megawatts (MW) in Quan'an Town, Nanxiong, Shaoguan, Guangdong, China. It is also known as Huadian Nanxiong power station.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Nanxiong power station | Quan'an Town, Nanxiong, Shaoguan, Guangdong, China | 25.146159, 114.290634 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 25.146159, 114.290634
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Unit 1 | operating | coal - unknown | 350 | supercritical | 2018 | – |
Unit 2 | operating | coal - unknown | 350 | supercritical | 2019 | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner |
---|---|
Unit 1 | Guangdong Huadian Shaoguan Thermal Power Co Ltd [100.0%] |
Unit 2 | Guangdong Huadian Shaoguan Thermal Power Co Ltd [100.0%] |
Project-level coal details
- Permit(s): May 28, 2015
Background on Project
China Huadian has proposed the 700 MW power station. Environmental clearance was obtained in 2015. Commissioning is planned for 2017. The estimated cost is 3.562 billion yuan.[1][2]
Construction began in 2016.[3]
Project suspended by central government
In January 2017 China's National Energy Board directed the Guangdong Province to suspend or postpone nine coal projects in the province, including Nanxiong power station, due to excess coal capacity.[4]
For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.
Construction ongoing
Satellite imagery from Planet, February 2017 to March 2018 shows construction clearly ongoing at the plant.
The units appear on a July 2018 central government list of units allowed to come online in 2018.[5]
Unit 1 was commissioned in December 2018.[6]
Unit 2 was commissioned in July 2019.[7]
Articles and Resources
References
- ↑ "Huadian Power International Corporation Limited project approval announcement," Like News, June 1, 2015
- ↑ "华电韶关南雄热电项目(2×350MW)获核准," 韶关热电公司, 2015-05-29
- ↑ "广东华电南雄“上大压小”热电联产工程(2×35万千瓦)第二批辅机自主招标公告," 中国物资采购网, 2016-04-11
- ↑ "9个项目遭遇“禁令” 广东煤电投资刹车" 财新网北极星电力网, 2017-01-13
- ↑ "名单来了|涉及11省共34台机组已移出停缓建名单!2018年分省煤电项目汇总表公布," 微能网, July 6, 2018
- ↑ "华电南雄“上大压小”热电联产工程(2×350MW)#1机组顺利投产," 北极星电力网新闻中心, 2018/12/19
- ↑ "中国能建承建韶关南雄“上大压," 小”热电联产工程全面投产, 2019-07-05
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.