Huxian power station

From Global Energy Monitor
(Redirected from Huxian-2 power station)
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Huxian power station (大唐户县热电厂) is an operating power station of at least 600-megawatts (MW) in Yuxia Town, Hu County, Xi'an, Shaanxi, China with multiple units, some of which are not currently operating. It is also known as 大唐户县第二热电厂; 大唐西安鄠邑热电公司 (Phase II Unit 1, Phase II Unit 2).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Huxian power station Yuxia Town, Hu County, Xi'an, Shaanxi, China 34.07419, 108.61852 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase I Unit 3, Phase I Unit 4, Phase I Unit 5, Phase II Unit 1, Phase II Unit 2: 34.07419, 108.61852

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Phase I Unit 3 retired coal - bituminous 50 subcritical 1977 2008
Phase I Unit 4 retired coal - bituminous 50 subcritical 1978 2008
Phase I Unit 5 retired coal - bituminous 50 subcritical 1978 2008
Phase II Unit 1 operating coal - bituminous 300 subcritical 2005
Phase II Unit 2 operating coal - bituminous 300 subcritical 2005

Table 3: Unit-level ownership and operator details

Unit name Owner
Phase I Unit 3 Datang Shaanxi Power Generation Co Ltd Huxian Thermal Power Plant [100.0%]
Phase I Unit 4 Datang Shaanxi Power Generation Co Ltd Huxian Thermal Power Plant [100.0%]
Phase I Unit 5 Datang Shaanxi Power Generation Co Ltd Huxian Thermal Power Plant [100.0%]
Phase II Unit 1 Datang Shaanxi Power Generation Co Ltd Xi'an Thermal Power Plant [100.0%]
Phase II Unit 2 Datang Shaanxi Power Generation Co Ltd Xi'an Thermal Power Plant [100.0%]

Background

Huxian power station began operating in 1957 in Hu County, Shaanxi Province. After 3 expansions, the total capacity reached 200 MW with 5 units. In the end of 2002, China Datang became its parent company, and continued working on its 4th expansion, known as Huxian-2 power station (大唐户县第二热电厂). The two new units with capacity of 300 MW each were brought online in 2005,[1] and had registered a new operating company as Datang Xi'an Huyi Thermal Power Company. (大唐西安鄠邑热电公司). The 5 older units were gradually retired till 2008. [2]

According to Platts, two more units totaling 600 MW, were completed in 2010. However, those units were not shown in photographs nor in web descriptions.[3][4]

Articles and Resources

References

  1. "全国投运燃煤机组脱硫设施清单," MEE, 2011
  2. 大唐户县热电厂 Baidu Baike
  3. "World Electric Power Plants Database,", Platts, June 2014. The database is not available online but can be purchased from Platts.
  4. "Huxian Datang Second Power Plant," Xi'an Continental Electric Power Design & Engineering Co., accessed December 2014

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.