Jieyang LNG Terminal (PipeChina)
| Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Jieyang LNG Terminal (PipeChina), also known as 国家管网粤东LNG接收站 and 国家管网揭阳LNG接收站, is an LNG import terminal in China with units that are proposed and operating.
Location
Table 1: Location details
| Name | Location | Coordinates (WGS 84) |
|---|---|---|
| Phase 1 | Jieyang, Guangdong, China[1] | 22.934479, 116.371427 (exact) |
| Phase 2 | Jieyang, Guangdong, China[1] | 22.934479, 116.371427 (exact) |
The map below shows the exact location of the terminal:
Project Details
Table 2: Infrastructure details
| Name | Facility type | Status | Capacity | Total terminal capacity | Offshore | Associated infrastructure |
|---|---|---|---|---|---|---|
| Phase 1 | import[1] | operating[2] | 5.04 mtpa[1][3][4] | 10.04 mtpa | False | – |
| Phase 2 | import | proposed[5] | 5 mtpa[5] | 10.04 mtpa | False | – |
Table 3: Cost
| Name | Facility type | Cost | Total known terminal costs |
|---|---|---|---|
| Phase 1 | import[1] | US$1,632,000,000 (10,200,000,000 RMB)[6] | US$1,632,000,000 |
| Phase 2 | import | – | US$1,632,000,000 |
Financing
No financing data available.
Table 4: Project timeline
| Name | Facility type | Status | Proposal year | FID year | Construction year | Operating year | Inactive year |
|---|---|---|---|---|---|---|---|
| Phase 1 | import[1] | operating[2] | – | – | 2013[6][7] | 2017[2] | – |
| Phase 2 | import | proposed[5] | 2025[5] | – | – | – | – |
Ownership
Table 5: Ownership
| Name | Facility type | Status | Owners | Parent companies | Operator |
|---|---|---|---|---|---|
| Phase 1 | import[1] | operating[2] | Pipechina Yuedong LNG Co Ltd [100%][8] | National Petroleum and Natural Gas Pipeline Network Group Co Ltd [100.0%] | – |
| Phase 2 | import | proposed[5] | Pipechina Yuedong LNG Co Ltd [100%][8] | National Petroleum and Natural Gas Pipeline Network Group Co Ltd [100.0%] | – |
Background
Jieyang LNG Terminal (PipeChina) is an operating LNG terminal in Guangdong, China.[9]
Phase 1
The Jieyang LNG Terminal project was approved in 2013 and was completed in 2015. However, a lack in demand postponed commissioning of the project.[10][11] The terminal has three tanks and a receiving capacity of 2 mtpa.[12]
The first cargo delivery was received in 2017 by Qatargas.[13][14]
Phase 2
On February 18, 2013, the project was approved by the National Development and Reform Commission.[15]
On July 24, 2025, the Guangdong Development and Reform Commission approved the project. [16]
On December 30, 2025, construction officially commenced.[17]
Ownership change
In February 9, 2019, the National Petroleum and Natural Gas Pipeline Group Co., Ltd. (PipeChina) was established with a major focus on the investment and construction of the long-distance oil and gas pipeline network and storage & peaking facilities, offering fair and open oil and gas pipeline transmission services.[18] 10 existing and under-construction LNG terminals were reportedly transferred or are going to transfer their ownerships to PipeChina.[19] Jieyang LNG terminal is one of them.
Articles and Resources
Additional data
To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 https://www.pipechina.com.cn/gywm/jtjj.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 2.3 https://finance.sina.com.cn/money/future/nyzx/2017-05-27/doc-ifyfqvmh9215194.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ http://www.huilai.gov.cn/hjbh/sthjxxgk/content/post_445136.html.
{{cite web}}: Missing or empty|title=(help) - ↑ (PDF) http://www.huilai.gov.cn/attachment/0/75/75089/445136.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 5.2 5.3 5.4 https://bendi.news.163.com/guangdong/25/0407/12/JSHT4JL404179HUU.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.0 6.1 http://cpc.people.com.cn/n/2013/0210/c87228-20476018.html.
{{cite web}}: Missing or empty|title=(help) - ↑ http://www.sasac.gov.cn/n2588025/n2588124/c4052116/content.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 8.0 8.1 https://www.qcc.com/weblogin?back=%2Ffirm%2Fea4e0967ec4ddfbf88aba47796331ffe.html.
{{cite web}}: Missing or empty|title=(help) - ↑ Jieyang LNG Terminal, A Barrel Full, accessed April 2017
- ↑ CNOOC to commission LNG terminal in S. China's Jieyang in Nov., Evie Feng, Shanxi Fenwei Energy Information Services Co., Ltd., February 9, 2017
- ↑ Chinese LNG demand falls for the first time on record, Stephen Letts, Australia Broadcasting Corporation, February 4, 2016
- ↑ Yuedong (Jieyang) LNG Terminal China, GEO, accessed June, 2017
- ↑ Qatargas delivers commissioning cargo to Yuedong LNG terminal LNG World News, May 3, 2017
- ↑ "中海油粤东LNG接收站5月26日正式投产"新华网 2017-5-27
- ↑ "揭阳大南海石化工业园项目暨中海油项目简介". 2013-03-10. Retrieved 2026-03-23.
{{cite web}}: CS1 maint: url-status (link) - ↑ "关于粤东LNG接收站储气工程项目核准的批复". 2025-07-28. Retrieved 2026-04-09.
{{cite web}}: CS1 maint: url-status (link) - ↑ "粤东LNG接收站储气工程开工". 2025-12-31. Retrieved 2026-04-09.
{{cite web}}: CS1 maint: url-status (link) - ↑ "集团简介--国家管网公司". www.pipechina.com.cn. Retrieved 2021-04-16.