Jubail (SWCC) power station

From Global Energy Monitor
(Redirected from Jubail (SWCC) Power Station)
Part of the
Global Oil and Gas Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related categories:

Jubail (SWCC) power station (محطة الجبيل المتكاملة لتحلية المياه وتوليد الكهرباء) is an operating power station of at least 1570-megawatts (MW) in Al-Jubail, Ash Sharqiyah, Saudi Arabia with multiple units, some of which are not currently operating. It is also known as Jubail Plant, Jubail Phase 3 power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Jubail (SWCC) power station Al-Jubail, Ash Sharqiyah, Saudi Arabia 26.89657, 49.77687 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1-1, Unit 1-2, Unit 1-3, Unit 1-4, Unit 1-5, Unit 1-6, Unit 2-1, Unit 2-10, Unit 2-2, Unit 2-3, Unit 2-4, Unit 2-5, Unit 2-6, Unit 2-7, Unit 2-8, Unit 2-9, Unit CC1: 26.89657, 49.77687

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Retired year
Unit 1-1 operating[2][3] gas[4][5] 60[4] steam turbine[2] not found 1980[4] 2024 (planned)
Unit 1-2 operating[2][3] gas[4][5] 60[4] steam turbine[2] not found 1980[4] 2024 (planned)
Unit 1-3 operating[2][3] gas[4][5] 60[4] steam turbine[2] not found 1980[4] 2024 (planned)
Unit 1-4 operating[2][3] gas[4][5] 60[4] steam turbine[2] not found 1980[4] 2024 (planned)
Unit 1-5 operating[2][3] gas[4][5] 60[4] steam turbine[2] not found 1980[4] 2024 (planned)
Unit 1-6 operating[2][3] gas[4][5] 60[4] steam turbine[2] not found 1980[4] 2024 (planned)
Unit 2-1 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-10 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-2 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-3 operating[2][3] gas[4] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-4 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-5 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-6 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-7 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-8 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit 2-9 operating[2][3] gas[4][5] 121[4] steam turbine[2] not found 1982[4] 2024 (planned)
Unit CC1 cancelled[6] gas[7] 3000[8] combined cycle[8] not found

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1-1 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 1-2 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 1-3 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 1-4 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 1-5 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 1-6 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-1 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-10 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-2 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-3 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-4 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-5 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-6 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-7 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-8 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit 2-9 Saline Water Conversion Corporation (SWCC)[4] Saline Water Conversion Corporation (SWCC) [100.0%]
Unit CC1 Saline Water Conversion Corporation (SWCC)[9] Saline Water Conversion Corporation (SWCC) [100.0%]

Project-level captive use details

  • Captive industry use (heat or power): both[10][11]
  • Captive industry: Chemicals[10][11]

Background

A combined cycle unit of the Jubail (SWCC) Power Station was announced in 2018[12] In August 2019, Saudi Water Partnership Company announced ten qualified bidders for the project, which had been revised from "an integrated water desalination and power plant of 1,170,000 m3/day of potable water capacity and 3,000 MW of power" to "two IWPs of 600,000 m3/day potable water capacity for Jubail-3A and 570,000 m3/day potable water capacity for Jubail-3B"[13] that will also "produce 3,000 MW of electricity with their related facilities".[14] However, Saudi Water Partnership decided to drop the power generation component of the project.[15]

Articles and Resources

References

  1. https://www.google.com/maps/place/%D8%A5%D8%AF%D8%A7%D8%B1%D8%A9+%D9%85%D8%AD%D8%B7%D8%A7%D8%AA+%D8%AA%D8%AD%D9%84%D9%8A%D8%A9+%D8%A7%D9%84%D9%85%D9%8A%D8%A7%D9%87+%D8%A7%D9%84%D9%85%D8%A7%D9%84%D8%AD%D8%A9+%D8%A8%D8%A7%D9%84%D8%AC%D8%A8%D9%8A%D9%84%E2%80%AD/@26.896585849.77391332017m/data=!3m1!1e3!4m13!1m7!3m6!1s0x0:0x0!2zMjbCsDU0JzM2LjAiTiA0OcKwNDYnMDguNCJF!3b1!8m2!3d26.91!4d49.769!3m4!1s0x3e3590b5c89b744d:0x7cc94cb1387081cb!8m2!3d26.8962924!4d49.7769392. {{cite web}}: Missing or empty |title= (help)
  2. 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 2.19 2.20 2.21 2.22 2.23 2.24 2.25 2.26 2.27 2.28 2.29 2.30 2.31 https://web.archive.org/web/20220123152836/https://datasource.kapsarc.org/explore/dataset/electricity-generation-by-station-capacities-in-saudi-arabia/export/. Archived from the original on 23 January 2022. {{cite web}}: Missing or empty |title= (help)
  3. 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 3.12 3.13 3.14 3.15 (PDF) https://web.archive.org/web/20221021182841/https://www.swcc.gov.sa/uploads/SustainabilityReport2021(English).pdf. Archived from the original (PDF) on 21 October 2022. {{cite web}}: Missing or empty |title= (help)
  4. 4.00 4.01 4.02 4.03 4.04 4.05 4.06 4.07 4.08 4.09 4.10 4.11 4.12 4.13 4.14 4.15 4.16 4.17 4.18 4.19 4.20 4.21 4.22 4.23 4.24 4.25 4.26 4.27 4.28 4.29 4.30 4.31 4.32 4.33 4.34 4.35 4.36 4.37 4.38 4.39 4.40 4.41 4.42 4.43 4.44 4.45 4.46 4.47 4.48 4.49 4.50 4.51 4.52 4.53 4.54 4.55 4.56 4.57 4.58 4.59 4.60 4.61 4.62 4.63 https://web.archive.org/web/20210624171139/https://github.com/wri/global-power-plant-database/blob/13b6a3baaca73e84b1a549d14c274981abec775b/raw_source_files/WRI/Saudi%20Arabia.csv. Archived from the original on 24 June 2021. {{cite web}}: Missing or empty |title= (help)
  5. 5.00 5.01 5.02 5.03 5.04 5.05 5.06 5.07 5.08 5.09 5.10 5.11 5.12 5.13 5.14 https://web.archive.org/web/20221126080827/https://www.abunayyanholding.com/en/casestudy/what-we-do/case-studies/jubail-independent-water-power-project.html?sector=6. Archived from the original on 26 November 2022. {{cite web}}: Missing or empty |title= (help)
  6. https://energy-utilities.com/saudi-arabia-evaluates-proposals-for-two-major-news084969.html. {{cite web}}: Missing or empty |title= (help)
  7. https://web.archive.org/web/20220706201739/https://www.marafiq.com.sa/en/89-jubail-water-and-power-company-jwap/1/51. Archived from the original on 06 July 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  8. 8.0 8.1 https://www.globaldata.com/store/report/swcc-wec-jubail-power-and-desalination-plant-phase-iii-eastern-province/. {{cite web}}: Missing or empty |title= (help)
  9. https://web.archive.org/web/20211206004257/https://www.zawya.com/mena/en/project/120713103953/jubail-phase-3-independent-water-power-project/. Archived from the original on 06 December 2021. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  10. 10.0 10.1 https://web.archive.org/web/20220711154010/https://archive.aawsat.com/details.asp?article=180942&issueno=8990. Archived from the original on 11 July 2022. {{cite web}}: Missing or empty |title= (help)
  11. 11.0 11.1 https://web.archive.org/web/20220119165912/http://www.tradearabia.com/news/OGN_337861.html. Archived from the original on 19 January 2022. {{cite web}}: Missing or empty |title= (help)
  12. Developers invited for Jubail Phase 3 IWPP, Trade Arabia, Mar 13, 2018
  13. Cristina Novo , Qualified bidders for Jubail-3 IWPs announced, Smart Water Magazine, Aug 13, 2019
  14. SWCC - Jubail Desalination Plant Phase 3, ZAWYA, Apr 17 2019
  15. "Saudi Arabia evaluates proposals for two major desalination plants". Energy & Utilities. Retrieved 2022-06-01.

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.