Karamay–Ürümqi New Gas Pipeline 克乌新输气管线 (克拉玛依-乌鲁木齐), also known as the Kewu New Gas Pipeine, is a gas pipeline operating in China.[1]

Location

The pipeline runs from Karamay, Xinjiang, China to Ürümqi, Xinjiang, China.[1]

Loading map...

Project details

  • Parent company: PipeChina
  • Capacity: 1 billion cubic meters per year[1]
  • Length: 285 kilometers[1]
  • Status: Operating[1]
  • Start year: 2006[1]
  • Cost: 600 million yuan

Background

Construction started in 2005, and the pipeline became operational in June 2006.