Lanzhou New District cogen power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Lanzhou New District cogen power station (甘肃能化兰州新区热电联产项目) is a power station under construction in Xicha Town, Gaolan, Lanzhou, Gansu, China. It is also known as 国家电投黄河上游水电开发公司兰州新区热电厂一期 (Unit 1), 华能兰州新区热电厂.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Lanzhou New District cogen power station | Xicha Town, Gaolan, Lanzhou, Gansu, China | 36.619982, 103.756325 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 36.619982, 103.756325
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Unit 1 | construction | coal - unknown | 350 | supercritical | – | – |
Unit 2 | construction[1] | coal - unknown | 350 | supercritical | – | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner |
---|---|
Unit 1 | Gansu ENERGY Chemical Co Ltd [100.0%] |
Unit 2 | Gansu ENERGY Chemical Co Ltd [100.0%] |
Project-level coal details
- Permit(s): December 2015
Background
In May 2023, a signing ceremony between Lanzhou New District and Gansu ENERGY Chemical Co., Ltd. took place to initiate plans for a new cogeneration power project of two 350 MW units in New District, Lanzhou, Gansu Province, China.[2] Gansu ENERGY Chemical Co., Ltd. plans to invest 4.2 billion in Lanzhou New District cogeneration project.[3] The proposed supercritical project was expected to begin construction in September 2023 and operation was estimated to begin in October 2025.[2]
In June 2023, it was reported that the project was preparing its feasibility study report.[4]
A bidding announcement for the compilation of the power project's Environmental Impact Report was posted by the owner in June 2023.[5] In July 2023, additional bidding announcements were published for project design reports and further feasibility studies.[6] Biddings for steam turbine, generator and boiler were also called.[7]
Articles and Resources
References
- ↑ https://web.archive.org/web/20240125153925/https://gansu.gansudaily.com.cn/system/2023/12/12/030921985.shtml. Archived from the original on 25 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 兰州新区与甘肃能化新建2×350兆瓦热电联产项目签约, BJX news, May 30, 2023
- ↑ "甘肃能化拟41.86亿投建兰州新区2×350MW热电联产项目". 北极星电力网. 2023-08-25. Retrieved 2023-9-5.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ 新区与甘肃能化热电联产项目签约, BJX news, June 2, 2023
- ↑ 甘肃能化兰州新区2×350MW热电项目环境影响报告(含地下水环境影响评价)编制招标公告, 甘肃煤炭交易中心有限公司, June 9, 2023
- ↑ 甘肃能化兰州新区2×350MW热电项目 接入系统设计(一次、二次)报告等五项报告编制 第一包、第三包、第四包第二次竞争性磋商公告, GSEI, July 3, 2023
- ↑ "甘肃兰州2×350MW热电项目三大主机采购". 电力项目圈. 2023-07-23. Retrieved 2023-9-5.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.