SLNG 2 LNG Terminal is a proposed LNG import terminal in Singapore.

Location

Table 1: Location details

Name Location Coordinates (WGS 84)
SLNG 2 LNG Terminal Offshore Singapore, Singapore[1] 1.200281, 103.672847 (approximate)

The map below shows the approximate location of the terminal:

Loading map...

Project Details

Table 2: Infrastructure details

mtpa = million tonnes per year
Name Facility type Status Capacity Total terminal capacity Offshore Associated infrastructure
SLNG 2 LNG Terminal import[1] proposed[1] 5 mtpa[1] 5.0 mtpa True –

Table 3: Cost

Name Facility type Cost Total known terminal costs
SLNG 2 LNG Terminal import[1] – –

Financing

No financing data available.

Table 4: Project timeline

FID = Final Investment Decision, used by some developers to indicate a project will move forward
Name Facility type Status Proposal year FID year Construction year Operating year Inactive year
SLNG 2 LNG Terminal import[1] proposed[1] 2021[2] – – –[1][1] –

Ownership

Table 5: Ownership

Name Facility type Status Owners Parent companies Operator
SLNG 2 LNG Terminal import[1] proposed[1] Singapore LNG Corp [100%][1] Singapore LNG Corp [100.0%] –

Background

As of July 2021, Singapore had announced plans to construct the country's second liquefied natural gas (LNG) terminal in the eastern part of the island-state to enhance energy security and grow the local LNG industry.The proposed second LNG terminal will support new industrial sites and power plants in the area and give Singapore a strategic buffer, as well as support the development of ancillary services like LNG trading, bunkering and vessel cool-down services.[3]

In October 2023, a new version of this proposal emerged. SLNG proposed to own and operate Singapore's second LNG terminal, which would have a capacity of 5 mtpa and be located offshore using a floating storage and regasification unit (FSRU). SLNG plans for the project to be operational by the end of the decade.[4]

In October 2024, SLNG signed an agreement with MOL to charter an FSRU with a capacity of 5 mtpa for the project.[5]

MOL will own, manage and operate the FSRU under a long-term time charter once delivered, while SLNG operates the terminal facility itself. As of March 2026, the FSRU (204,000 cbm storage, 5 mtpa regasification capacity, built to run up to 25 years without drydocking) was under construction at Hanwha Ocean's Geoje shipyard in South Korea for about US$413 million, with the keel laid 26 May 2026 and delivery expected by October 2027. SLNG awarded the onshore connecting-infrastructure EPC contract (main process area, FSRU jetty, pipelines to the national gas grid) to China Communications Construction Company (Singapore) in November 2025, with groundbreaking in late March 2026. The FSRU is planned to be moored at Jurong Port and connected to Singapore's gas network by 2030, taking SLNG's combined throughput capacity (with the existing Jurong Island terminal) to up to 15 mtpa.[6][7][8][9]

Articles and Resources

Additional data

To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.

References

  1. ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 https://www.slng.com.sg/node/317. {{cite web}}: Missing or empty |title= (help)
  2. ↑ https://www.dmsprojects.net/singapore/projects/slng-jurong-island-second-lng-terminal/PRJ00020666. {{cite web}}: Missing or empty |title= (help)
  3. ↑ Jurong Island Second LNG Terminal, DMS Projects, accessed April 19, 2021
  4. ↑ "SLNG To Develop, Own And Operate Second LNG Terminal In Singapore As It Marks 10 Years Of Commercial Operations | SLNG". www.slng.com.sg. Retrieved 2024-07-15.
  5. ↑ https://cdn.prod.website-files.com/67bdb9fc993751711c5f54fd/685278fda1e68e3b4324e2cf_0432365c1c5b8fb129ae8055cca8cb9b_%23GIIGNL%20-%20Livre%202025-20250610-Simple.pdf
  6. ↑ "MOL Signs Long-Term Time Charter Contract for Singapore's 1st FSRU". Mitsui O.S.K. Lines. Retrieved 2026-07-27.
  7. ↑ "Hanwha Ocean lays keel for 204,000-cbm MOL FSRU for Singapore LNG terminal". PortNews. Retrieved 2026-07-27.
  8. ↑ "Singapore starts onshore infrastructure work for second LNG terminal". GIIGNL news digest (orig. LNG Prime). Retrieved 2026-07-27.