Tianjin LNG Terminal (Sinopec)

From Global Energy Monitor
(Redirected from Tianjin LNG Terminal (CNPC))
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Tianjin LNG Terminal (Sinopec) (中石化天津LNG接收站) is an operating LNG terminal in Tianjin, China.

Location

Loading map...

The undated satellite image shows the exact location of Tianjin LNG Terminal (Sinopec) with first and second phases on the right of the site and the third phase on the left.

Project details

  • Owner: Sinopec Tianjin LNG Co., Ltd. 中石化天津液化天然气有限责任公司 [1]
  • Parent company: China Petroleum and Chemical Corporation Limited 98%, Tianjin Economic and Technological Development Area State-owned Assets Management Co., Ltd 2%
中国石化天然气有限责任公司 98%
天津经济技术开发区南港发展集团有限公司 2%
  • Location: Tianjin, China
  • Coordinates: 38.749154, 117.714895 (exact)
  • Capacity: 6 mtpa [2]
  • Status: Operating[3]
  • Type: Import
  • Start year: 2018

Background

Tianjin LNG Terminal (Sinopec) is an LNG terminal under development in Tianjin, China.[4]

Tianjin LNG Terminal (Sinopec) started construction in 2013 and was originally set to be running by 2016. In July 2015, it was announced by China’s National Audit Office that the project was delayed until 2017. The terminal will supply LNG to Beijing, Tianjin, and the Hebei region.[5] The 3 mtpa facility is awaiting final regulatory approvals for completion.[6]

The terminal began commercial operations in February 2018, and completed construction of all of its storage tanks in September 2018.[7]

The receiving capacity increased from 3 mtpa to 6 mtpa in 2021 following the completion of the second receiving berth[3].

Expansion projects

Phase II

In September 2018 Sinopec announced that Phase II of the project had been approved by the Tianjin Development and Reform Commission. Phase II would construct five LNG storage tanks, each with a capacity of 220,000 cubic meters.[8] Construction of the expansion began in April 2020.[9][10] Operations are set to start in October 2023.[11]

The main structure completed construction in August 2022.[12]

In September 2023, phase two with 5 storage tanks has completed construction and is preparing for the full operation when the winter heating season arrives. [13]

Tianjin LNG terminal (Sinopec) storage tanks for phase I & II
  • Owner: Sinopec Tianjin LNG Co., Ltd. 中石化天津液化天然气有限责任公司 [1]
  • Parent company: China Petroleum and Chemical Corporation Limited 98%, Tianjin Economic and Technological Development Area State-owned Assets Management Co., Ltd 2%
  • Location: Tianjin, China
  • Coordinates: 38.749154, 117.714895 (exact)
  • Capacity: 4.8 mpta, 0.70 bcfd[14][15]
  • Status: operating
  • Type: Import
  • Start year: 2023[16]

Phase III

In December 2021, Phase III (Stage one and two ) of the LNG terminal was approved by Tianjin government. It was considered a necessary step toward the final permit by NDRC.[17] According to the approval document, Phase III (Stage one and two ) plans to add 5 more storage tanks with 270,000 cubic meters each to the LNG terminal, as well as light hydrocarbon separation devices, cold and heat exchange stations, uploading stations and supporting auxiliary facilities. The total receiving capacity of Tianjin LNG terminal will be increased to 11.65 million tons per year after the Phase III is completed.[17]

By the end of 2022, no further news could be heard on Phase III.

The local authority said in December 2023 that the construction of the foundation of the third phase had completed. It is next to the first and second phase on the left side.[18]

Tianjin LNG terminal (Sinopec) phase III construction site--December 2023
  • Owner: Sinopec Tianjin LNG Co., Ltd. 中石化天津液化天然气有限责任公司 [1]
  • Parent company: China Petroleum and Chemical Corporation Limited 98%, Tianjin Economic and Technological Development Area State-owned Assets Management Co., Ltd 2%
  • Location: Tianjin, China
  • Coordinates: 38.749154, 117.714895 (exact)
  • Capacity: 0.85 mpta[17]
  • Status: Proposed
  • Type: Import
  • Start year:

Articles and resources

References

  1. 1.0 1.1 1.2 "中石化天津液化天然气有限责任公司 - 企查查". www.qcc.com. Retrieved 2021-04-19.{{cite web}}: CS1 maint: url-status (link)
  2. "中国石化天然气分公司天津LNG接收站二期工程主体结构全面完工----来源:中国新闻网". chinanews.com.cn. 2022-08-09.{{cite web}}: CS1 maint: url-status (link)
  3. 3.0 3.1 "国内首座"双泊位"LNG码头正式投用-新华网". www.xinhuanet.com. 2021-12-29.{{cite web}}: CS1 maint: url-status (link)
  4. Tianjin LNG Terminal (CNPC), Wood Mackenzie, accessed April 2017
  5. Energy Markets in Emerging Economies: Strategies for growth, Wang, Henry K.H., Routlege, London and New York, 2017, 75-76
  6. LNG & Natural Gas News, Commodity3, April 21, 2017
  7. China's Sinopec adds LNG tank at Tianjin terminal, Reuters, Sep. 25, 2018
  8. China's Sinopec says Phase 2 of Tianjin LNG terminal approved, Reuters, Oct. 31, 2018
  9. SINOPEC STARTS WORK ON TIANJIN TERMINAL PHASE 2, Natural Gas World, Mar. 29, 2019
  10. "中石化LNG二期项目开工- 来源:滨城时报". 人民网 http://tj.people.com.cn. 2020-04-15. {{cite web}}: External link in |website= (help)CS1 maint: url-status (link)
  11. 中石化天津LNG接收站二期建设全速推进 Sohu.com, 09-25-2020
  12. "天然气分公司天津LNG接收站二期项目主体结构全面完工". www.sinopecnews.com.cn (in 中文). 2022-08-10.{{cite web}}: CS1 maint: url-status (link)
  13. "9号储罐中交 中石化天津LNG接收站二期项目全面完工----天津经开区—泰达". https://www.teda.gov.cn. 2023-09-14. {{cite web}}: External link in |website= (help)CS1 maint: url-status (link)
  14. Sinopec To More Than Double LNG Capacity, Apr. 2, 2018
  15. "今冬华北保供"底气"更足了——中石化天津LNG接收站"双泊位"LNG码头投用_新华广播_新华网". www.xinhuanet.com. 2021-12-31.{{cite web}}: CS1 maint: url-status (link)
  16. "天津LNG接收站储气能力居国内首位-重庆石油天然气交易中心 来源:国际能源网". www.chinacqpgx.com. 2024-01-10.{{cite web}}: CS1 maint: url-status (link)
  17. 17.0 17.1 17.2 "中石化天津LNG项目三期工程 (一阶段、二阶段)取得核准批复-北极星能源网". news.bjx.com.cn. 2021-12-06.{{cite web}}: CS1 maint: url-status (link)
  18. "中石化天津LNG项目三期完成桩基施工". attnew.teda.gov.cn. 2023-12-04.{{cite web}}: CS1 maint: url-status (link)