Fujian Longgang New Materials Co., Ltd. (福建龙钢新型材料有限公司) is a 1210 thousand tonnes per annum (TTPA) blast furnace (BF) and basic oxygen furnace (BOF) steel plant under construction in Longyan, Fujian, China.
Location
The map below shows the location of the steel plant in Longyan, Fujian, China.
- Location: Zhangping Industrial Park, Longyan City, Fujian Province[1]
- Coordinates (WGS 84): 25.357408, 117.362096 (exact)
Background
According to the project capacity replacement plan announcement, it is planned to construct 1×1320m3 blast furnace and 1×106t basic oxygen furnace.[2]The construction is in the final sprint stage, and it is expected to start casting molten iron by the end of May or early June.[3]
Plant Details
Table 1: General Plant Details
Plant status | Proposed date | Construction date | Workforce size |
---|---|---|---|
construction[4] | 2019[5] | 2021[4] | 196[6] |
Table 2: Ownership and Parent Company Information
Parent company | Parent company PermID | Owner | Owner company PermID |
---|---|---|---|
Fujian Longgang New Materials Co., Ltd. [100%][6] | GEM0000043 [100%] | Fujian Longgang New Materials Co., Ltd.[6] | GEM0000043 |
Table 3: Process and Products
Main production equipment | Detailed production equipment |
---|---|
blast furnace (BF) and basic oxygen furnace (BOF)[7] | 1 BOF (1x106-tonne)[5][8] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum):
Basic oxygen furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|
1210 TTPA[5] | 1210 TTPA |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum):
Blast furnace capacity | Nominal iron capacity (total) |
---|---|
1203 TTPA[5] | 1203 TTPA |
Blast Furnace Details
Table 6: Blast Furnace Details:
Unit name | Status | Proposed date | Construction date | Current size | Current capacity |
---|---|---|---|---|---|
unknown | construction[1] | December 2019[5] | October 2021[5] | 1320 m³[5][8] | 1203 TTPA[5] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker and Global Blast Furnace Tracker on the Global Energy Monitor website.
- ↑ 1.0 1.1 https://web.archive.org/web/20220318135739/https://www.hangxunbao.com/a/19781742.html. Archived from the original on 2022-03-18.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "福建龙钢智能化钢铁工业4.0定制化生产示范项目". 漳平市人民政府.
- ↑ "北材难下?南材北上!". zhaogang. 2023-03-12.
- ↑ 4.0 4.1 http://qy.guikexiu.com/cms/news/186681.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.0 5.1 5.2 5.3 5.4 5.5 5.6 5.7 https://gc.mysteel.com/19/1220/10/0506528FD5E158FB.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.0 6.1 6.2 https://web.archive.org/web/20220319014347/https://www.qcc.com/weblogin?back. Archived from the original on 2022-03-19.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://gc.mysteel.com/19/1220/10/0506528FD5E158FB.html;http://bmjcloud.com/zctz/986318.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 https://web.archive.org/web/20220318233353/http://bmjcloud.com/zctz/986318. Archived from the original on 2022-03-18.
{{cite web}}
: Missing or empty|title=
(help)