Aguirre GasPort FSRU is a cancelled (confirmed) LNG import terminal in United States.

Location

Table 1: Location details

Name Location Coordinates (WGS 84)
Aguirre GasPort FSRU Guayama, Guayama, United States[1] 17.974167, -66.11 (approximate)

The map below shows the approximate location of the terminal:

Loading map...

Project Details

Table 2: Infrastructure details

mtpa = million tonnes per year
Name Facility type Status Capacity Total terminal capacity Offshore Associated infrastructure
Aguirre GasPort FSRU import[2] cancelled (confirmed)[3] 3.8 mtpa[2] 3.8 mtpa True –

Table 3: Cost

Name Facility type Cost Total known terminal costs
Aguirre GasPort FSRU import[2] – –

Financing

No financing data available.

Table 4: Project timeline

FID = Final Investment Decision, used by some developers to indicate a project will move forward
Name Facility type Status Proposal year FID year Construction year Operating year Inactive year
Aguirre GasPort FSRU import[2] cancelled (confirmed)[3] – – – – 2019 (cancelled)[4]

Ownership

Table 5: Ownership

Name Facility type Status Owners Parent companies Operator
Aguirre GasPort FSRU import[2] cancelled (confirmed)[3] Excelerate Energy LP [100%][2] Excelerate Energy Inc [24.3%]; Excelerate Energy Holdings LLC –

Background

The project is being developed by the Puerto Rico Electric Power Authority and Excelerate Energy. Excelerate Energy submitted its formal application to FERC in April 2013. On July 24, 2015, FERC issued the order authorizing the construction and operation of the project.[5]

The installation will include a floating storage and regasification unit (FSRU) and submarine lines for gas supply. The complex will provide fuel to the Central Aguirre power plant. It is planned for 2018.[6]

As a result of changed circumstances, the Aguirre Offshore GasPort project, including the liquefied natural gas (LNG) terminal conditionally authorized by the regulator, was cancelled by the company in November of 2019. Excelerate filed in a request to FERC to vacate the authorization for the construction of the facilities that would have included a floating storage and regasification unit (FSRU) with a baseload capacity of 500 mmscf/d, minimal infrastructure to moor the vessel, and a subsea pipeline to deliver the gas onshore.[7]

Articles and Resources

Additional data

To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.

References

  1. ↑ http://en.aguirreoffshoregasport.com/the-aguirre-offshore-gasport-project-overview/location-puerto-rico/. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.0 2.1 2.2 2.3 2.4 2.5 http://en.aguirreoffshoregasport.com/the-aguirre-offshore-gasport-project-overview/gasport-project-status-and-timeline/. {{cite web}}: Missing or empty |title= (help)
  3. ↑ 3.0 3.1 3.2 https://www.lngworldnews.com/ferc-ends-aguirre-offshore-lng-gasport-process/. {{cite web}}: Missing or empty |title= (help)
  4. ↑ https://www.lngworldnews.com/ferc-ends-aguirre-offshore-lng-gasport-process/ https://www.lngworldnews.com/ferc-ends-aguirre-offshore-lng-gasport-process/; https://www.lngworldnews.com/ferc-ends-aguirre-offshore-lng-gasport-process/. {{cite web}}: Check |url= value (help); Missing or empty |title= (help)
  5. ↑ "Project Status and Timeline," Aguirre Offshore Gasport, accessed July 2017
  6. ↑ "Aguirre Offshore GasPort," BN Americas, accessed July 2017
  7. ↑ FERC ends Aguirre Offshore LNG GasPort process LNG World News, February 2019