Anhui Langxi Hongtai Iron and Steel Co Ltd (安徽省郎溪县鸿泰钢铁有限公司) is an electric arc furnace (EAF) steel plant operating in Xuancheng, Anhui, China.

Location

The map below shows the exact location of the plant in Xuancheng, Anhui, China:

Loading map...
  • Location: Gaojia Village, Xinfa Town, Langxi County, Xuancheng City, Anhui Province
  • Coordinates (WGS 84): 31.246635, 119.120443 (exact)

Background

In 2018, the company announced the capacity replacement program for electric arc furnace construction project, which stated to withdraw two 70-ton electric arc furnaces and two 70-ton refining furnaces and construct one 128-ton electric arc furnace and one 128-ton refining furnace.[1]

On January 14, 2022, during the pre-commissioning assessment of the electric arc furnace project, after reviewing the information and on-site field verification, two 70-ton electric arc furnaces and two 70-ton refining furnaces have been shut down, transformers and electrodes have been removed, and the main equipment has been sealed, and the newly constructed one 128-ton electric arc furnace and one 128-ton refining furnace have their numbers, models, specifications and other information measured on-site, although they are the same as those in the drawings, but the furnace type The actual average steel output is 130 tons. In view of the new project capacity and replacement program is inconsistent, the project was ordered to rectify, rectification is not in place before the construction project shall not be put into operation.[2]

The "Electric arc furnace optimization and upgrading transformation project capacity replacement change plan" was announced on March 2022, which conversed of 128-ton electric arc and refining furnaces to 130-ton, respectively.And the new electric arc furnace(130-tonne) was put into production in March 2022[2][3]

Plant Details

Table 1: General Plant Details

Phase Plant status Start date Pre-retirement announcement date Retired date Workforce size Power source
Main plant Operating[4] 2002[5] 268[6] Langxi Power Grid[7]
Closure Retired[4] 2018[4] 2022-03[4] Langxi Power Grid[7]
Expansion Operating[4] 2022[4] Langxi Power Grid[7]

Table 2: Ownership and Parent Company Information

Phase Parent company Parent company GEM ID Owner Owner company GEM ID
Main plant Anhui Langxi County Fuhang Steel Co Ltd [100%] E100000123261 [100%] Anhui Langxi Hongtai Iron and Steel Co., Ltd.[5] E100000126133

Table 3: Process and Products

Phase Steel product category Steel products Steel sector end users ISO 14001 Main production equipment Detailed production equipment
Main plant finished rolled[6] rebar[6] building and infrastructure[6] 2023-03-28 00:00:00[8] EAF[9] 2 EAF (2x70-tonne) 2 LF(2x70-tonne)[9][4]
Closure finished rolled[6] rebar[6] EAF[9] 2 EAF (2x70-tonne) 2 LF(2x70-tonne)[9][4]
Expansion finished rolled[6] rebar[6] EAF[9] 1 EAF (1x130-tonne) 1LF (1x130-tonne)[9][4]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
Main plant operating
Closure retired 1000 TTPA[10][10] 1000 TTPA[10][10]
Expansion operating 1000 TTPA[10] 1000 TTPA[10]

Table 5: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status*
Main plant operating
Closure retired
Expansion operating

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. "安徽省郎溪县鸿泰钢铁有限公司 128 吨电弧炉建设项目产能置换方案" (PDF). 2018-4-16. {{cite news}}: Check date values in: |date= (help)
  2. 2.0 2.1 关于安徽省郎溪县鸿泰钢铁有限公司产能置换退出设备拆除验收及电弧炉建设项目投产前评估情况的公示,安徽省经济和信息化厅,January 20, 2022
  3. 关于安徽省郎溪县鸿泰钢铁电弧炉优化升级改造项目产能置换变更方案的公告,安徽省经济和信息化厅,March 8, 2022
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 https://web.archive.org/web/20220318080437/http://jx.ah.gov.cn/sy/wjgg/146419041.html. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 https://web.archive.org/web/20220320170530/https://www.qcc.com/weblogin?back. Archived from the original on 20 March 2022. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 6.2 6.3 6.4 6.5 6.6 6.7 https://web.archive.org/web/20231003145919/http://cx.cnca.cn/CertECloud/result/skipDetail?rzjgId=CNCA-R-2002-053&certNumber=05323E30293R0M&showtemp=1&etlId=&lot_number=3b72b8dd054d4d4898a8d53314c9271f&pass_token=a9efe82481ff3e8cd6855892fbb31fda25fadae4487df709fd9ea33dff12e71e&gen_time=1696345014&captcha_output=sDNe0yZW5lU3WYq1nI3vWAFiIOQTSlCydn8Nzst3GCMMFxO6o3QN16sG7xqJBTE3Qm2cHw9lKy-904V-sYBGPIE6cAc98NLuKTadIrrsEI6u9jjSAgUfe9rUT1lI2btPgRmSqQqlPz7M3X-EiOmM56H3QMqM1Uj5MvK4p4ecCcPiw0TVkxbvo4sYNRVF-7YkJco99lM2NDj-QRsWpScpYOxSxucYzmstBqXl7mRtxA61X1uJuZHVhGQOrh0LISBto56KJKL5HWA8conOlC72Jw==. Archived from the original on 03 October 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  7. 7.0 7.1 7.2 https://www.ahlx.gov.cn/OpennessContent/show/2182264.html. {{cite web}}: Missing or empty |title= (help)
  8. https://web.archive.org/web/20231003145801/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E5%AE%89%E5%BE%BD%E7%9C%81%E9%83%8E%E6%BA%AA%E5%8E%BF%E9%B8%BF%E6%B3%B0%E9%92%A2%E9%93%81%E6%9C%89%E9%99%90%E5%85%AC%E5%8F%B8&fromIndex=true. Archived from the original on 03 October 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  9. 9.0 9.1 9.2 9.3 9.4 9.5 https://web.archive.org/web/20220318090706/https://factory.mysteel.com/22/0124/09/BBD61B3CA5E78301.html. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)
  10. 10.0 10.1 10.2 10.3 10.4 10.5 https://factory.mysteel.com/22/0124/09/BBD61B3CA5E78301.html;https://factory.mysteel.com/22/0308/13/1AECF0DFE17BF60C.html. {{cite web}}: Missing or empty |title= (help)

Resources