ArcelorMittal Resende steel plant

From Global Energy Monitor
This article is part of the
Global Steel Plant Tracker, a project of Global Energy Monitor.
Download full dataset
Report an error
Sub-articles:

ArcelorMittal Resende steel plant (Usina siderúrgica ArcelorMittal Resende (Portuguese)), also known as ArcelorMittal Sul Fluminense Resende and Votorantim Resende (predecessor), is a 1000 thousand tonnes per annum (TTPA) electric arc furnace (EAF) steel plant operating in Resende, Rio de Janeiro, Brazil.

Location

The map below shows the location of the steel plant in Resende, Rio de Janeiro, Brazil.

Loading map...
  • Location: Av. Professor Darcy Ribeiro, 4330, Casa da Lua, 27523-300, Resende, Rio de Janeiro, Brazil[1]
  • Coordinates (WGS 84): -22.493597, -44.512628 (exact)

Background

Founded in 2009, the ArcelorMittal Resende plant is a mini-mill, creating steel primarily from scrap metal in an electric arc furnace.[2] The plant specializes in rebar, wire rod, and drawn steel for use in civil construction, industry, and agribusiness.[3][4]

The plant was originally owned by Brazilian steelmaker Votorantim Siderurgia. In February 2017, ArcelorMittal and Votorantim announced plans to combine their long steel operations in Brazil.[5] Under the deal, concluded in April 2018, Votorantim Siderurgia became a subsidiary of ArcelorMittal Brasil.[6]



Plant Details

Table 1: General Plant Details

Plant status Start date Workforce size
operating[7] 2009[8][9] 900[10]

Table 2: Ownership and Parent Company Information

Parent company Parent company PermID Owner Owner company PermID
ArcelorMittal SA [100%][11] 5000030092 [100%] Arcelormittal Brasil SA[12][13][14] 4295859712

Table 3: Process and Products

Steel product category Steel products Steel sector end users ISO 14001 Main production equipment Detailed production equipment
finished rolled[15] rebar, wire rod[16][7] building and infrastructure; energy; tools and machinery; transport[15] yes[17] electric arc furnace (EAF)[17][18][9] 1 EAF (2009)[9][19]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum):

Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
1000 TTPA[20][21][22][23] 1000 TTPA

Table 5: Actual Crude Steel Production by Year (thousand tonnes per annum):

Year BOF Production EAF Production OHF Production Total (all routes)
2020 737 TTPA[11][19][13] 737 TTPA[11][19][13]
2021 789 TTPA[17][24][18] 789 TTPA[17][24][18]

Articles and Resources

References

  1. (PDF) https://web.archive.org/web/20220120203349/https://acobrasil.org.br/site/wp-content/uploads/2021/07/Anuario_Completo_2021.pdf. Archived from the original (PDF) on 2022-01-20. {{cite web}}: Missing or empty |title= (help)
  2. "RELATÓRIO DE AUDITORIA AMBIENTAL DE CONTROLE |DZ-056.R-3 - ARCELORMITTAL –UNIDADE RESENDE" (PDF). Ambio Soluções Ambientais. February 27, 2019.{{cite web}}: CS1 maint: url-status (link)
  3. "Unidades | ArcelorMittal". ArcelorMittal Brasil. Retrieved 2020-08-05.{{cite web}}: CS1 maint: url-status (link)
  4. "Quem somos | ArcelorMittal". ArcelorMittal Brasil. Retrieved 2020-08-05.{{cite web}}: CS1 maint: url-status (link)
  5. "ArcelorMittal to top Brazil's long steel output after Votorantim deal: executive". Reuters. February 7, 2018.{{cite web}}: CS1 maint: url-status (link)
  6. "Arcelor Mittal assume usinas da Votorantim em Barra Mansa, Resende e Três Lagoas". Diário do Vale. April 2, 2018.{{cite web}}: CS1 maint: url-status (link)
  7. 7.0 7.1 https://web.archive.org/web/20211228114101/https://brasil.arcelormittal.com/a-arcelormittal/unidades. Archived from the original on 2021-12-28. {{cite web}}: Missing or empty |title= (help)
  8. https://web.archive.org/web/20220922024322/https://100anos.arcelormittal.com.br/unidades/. Archived from the original on 2022-09-22. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 9.2 (PDF) https://web.archive.org/web/20210713135507/http://www.inea.rj.gov.br/wp-content/uploads/2019/05/2019.02.14_Votorantim-Resende-Relat%C3%B3rio-de-Auditoria-DZ-56_rEF.-2018_Assinado.pdf. Archived from the original (PDF) on 2021-07-13. {{cite web}}: Missing or empty |title= (help)
  10. https://web.archive.org/web/20220922020554/https://diariodovale.com.br/tempo-real/votorantim-vende-siderurgicas-de-resende-e-barra-mansa/. Archived from the original on 2022-09-22. {{cite web}}: Missing or empty |title= (help)
  11. 11.0 11.1 11.2 (PDF) https://web.archive.org/web/20220318103656/https://corporate-media.arcelormittal.com/media/b2lge2bt/fact-book-2020_may-21.pdf. Archived from the original (PDF) on 2022-03-18. {{cite web}}: Missing or empty |title= (help)
  12. https://web.archive.org/web/20211228114647/https://brasil.arcelormittal.com/sustentabilidade/meio-ambiente/acos-longos/estrutura-gestao. Archived from the original on 2021-12-28. {{cite web}}: Missing or empty |title= (help)
  13. 13.0 13.1 13.2 (PDF) https://web.archive.org/web/20211231044946/https://corporate-media.arcelormittal.com/media/w0epovkr/2020-arcelormittal-annual-report.pdf. Archived from the original (PDF) on 2021-12-31. {{cite web}}: Missing or empty |title= (help)
  14. https://web.archive.org/web/20220126093218/https://brasil.arcelormittal.com/a-arcelormittal/estrutura-organizacional. Archived from the original on 2022-01-26. {{cite web}}: Missing or empty |title= (help)
  15. 15.0 15.1 https://web.archive.org/web/20211228113803/https://brasil.arcelormittal.com/a-arcelormittal/quem-somos. Archived from the original on 2021-12-28. {{cite web}}: Missing or empty |title= (help)
  16. https://web.archive.org/web/20220921201213/https://brasil.arcelormittal.com/sala-imprensa/publicacoes-relatorios/brasil/apresentacao-institucional-2021. Archived from the original on 2022-09-21. {{cite web}}: Missing or empty |title= (help)
  17. 17.0 17.1 17.2 17.3 (PDF) https://corporate.arcelormittal.com/media/3z1ozw5h/arcelor-mittal-fact-book-2021.pdf. {{cite web}}: Missing or empty |title= (help)
  18. 18.0 18.1 18.2 (PDF) https://web.archive.org/web/20220625100836/https://acobrasil.org.br/site/wp-content/uploads/2022/05/AcoBrasil_Mini_anuario_2022.pdf. Archived from the original (PDF) on 2022-06-25. {{cite web}}: Missing or empty |title= (help)
  19. 19.0 19.1 19.2 (PDF) https://web.archive.org/web/20220120225956/https://acobrasil.org.br/site/wp-content/uploads/2021/06/Mini_anuario_2021_AcoBrasil-1.pdf. Archived from the original (PDF) on 2022-01-20. {{cite web}}: Missing or empty |title= (help)
  20. (PDF) https://web.archive.org/web/20220921234716/https://www.gov.br/mcti/pt-br/acompanhe-o-mcti/cgcl/clima/arquivos/opcoes-de-mitigacao-de-emissoes-de-gee-em-setores-chave/modelagem-setorial-de-opcoes-de-baixo-carbono-para-o-setor-de-ferro-gusa-e-aco.pdf. Archived from the original (PDF) on 2022-09-21. {{cite web}}: Missing or empty |title= (help)
  21. (PDF) https://web.archive.org/web/20220121194842/https://acobrasil.org.br/site/wp-content/uploads/2019/10/LIVRO_ACO_BX.pdf. Archived from the original (PDF) on 2022-01-21. {{cite web}}: Missing or empty |title= (help)
  22. https://web.archive.org/web/20220205181043/https://cnmcut.org.br/noticias/votorantim-siderurgica-produz-18-milhao-de-toneladas-de-aco-por-ano-d011. Archived from the original on 2022-02-05. {{cite web}}: Missing or empty |title= (help)
  23. (PDF) https://web.archive.org/web/20200606111618/https://web.bndes.gov.br/bib/jspui/bitstream/1408/18340/1/PRCapLiv209331_Investimentos%20na%20siderurgia%20brasileira_Compl_P.pdf. Archived from the original (PDF) on 2020-06-06. {{cite web}}: Missing or empty |title= (help)
  24. 24.0 24.1 https://web.archive.org/web/20211023042623/https://www.steelorbis.com/steel-news/latest-news/arcelormittal-brazil-resumes-steel-output-at-barra-mansa-mill-1216169.htm. Archived from the original on 2021-10-23. {{cite web}}: Missing or empty |title= (help)

External resources



Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.