Avtozavod power station (Автозаводская ТЭЦ) is an operating power station of at least 480-megawatts (MW) in Nizhny Novgorod, Nizhny Novgorod Oblast, Russia with multiple units, some of which are not currently operating. It is also known as Gorky Motor Works CHP.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Avtozavod power station Nizhny Novgorod, Nizhny Novgorod Oblast, Russia 56.24286, 43.89231 (exact)[1][2]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 10, Unit 11, Unit 12, Unit 7, Unit 8, Unit 9, Unit CC1: 56.24286, 43.89231

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Retired year
Unit 10 operating[3][4] gas, heavy fuel oil[5] 60[6][7] steam turbine[6][7] yes[3] 1976[6][7]
Unit 11 operating[3][4] gas, heavy fuel oil[5] 60[6][7] steam turbine[6][7] yes[3] 1976[6][7]
Unit 12 operating[3][4] gas, heavy fuel oil[5] 100[6][7] steam turbine[6][7] yes[3] 1978[6][7]
Unit 7 operating[3][4] gas, heavy fuel oil[5] 100[6][7] steam turbine[6][7] yes[3] 1965[6][7]
Unit 8 operating[3][4] gas, heavy fuel oil[5] 100[6][7] steam turbine[6][7] yes[3] 1966[6][7]
Unit 9 operating[3][4] gas, heavy fuel oil[5] 60[6][7] steam turbine[6][7] yes[3] 1974[6][7]
Unit CC1 shelved[8][9][10][11][3][4] gas, heavy fuel oil[9] 440[9] combined cycle[8][9] yes[9]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 10 LLC "Avtozavodskaya CHP"[1] En+ Group [100.0%]
Unit 11 LLC "Avtozavodskaya CHP"[1] En+ Group [100.0%]
Unit 12 LLC "Avtozavodskaya CHP"[1] En+ Group [100.0%]
Unit 7 LLC "Avtozavodskaya CHP"[1] En+ Group [100.0%]
Unit 8 LLC "Avtozavodskaya CHP"[1] En+ Group [100.0%]
Unit 9 LLC "Avtozavodskaya CHP"[1] En+ Group [100.0%]
Unit CC1 LLC "Avtozavodskaya CHP"[1] En+ Group [100.0%]

Background

The project has been announced to be frozen until 2021 in 2015.[12] There have been no updates since 2021. The project was not included in the scheme and program for the development of the Unified Energy System of Russia for 2022-2028[13] or the Russian Ministry of Energy 2023-2028 energy program issued in February 2023.[14] As of November 2023, the project is considered shelved. In September 2023, En+ Group had to abandon another modernization project, which aimed to increase the installed capacity of the power station by 60 MW. The cancellation was attributed to the escalated project costs.[15]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 https://energybase.ru/power-plant/Avtozavodskaya_CHP-1. {{cite web}}: Missing or empty |title= (help)
  2. https://web.archive.org/web/20210830234108/https://www.industryabout.com/country-territories-3/2137-russia/fossil-fuels-energy/32775-avtozavodskaya-gas-power-plant. Archived from the original on 30 August 2021. {{cite web}}: Missing or empty |title= (help)
  3. 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 3.12 https://web.archive.org/web/20210830213624/https://enplusgroup.com/en/company/map/avtozavodskaya-chp/. Archived from the original on 30 August 2021. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 (PDF) https://web.archive.org/web/20230313040439/https://www.so-ups.ru/fileadmin/files/company/future_plan/public_discussion/2023/final/31_Nizhegorodskaja_oblast_fin.pdf. Archived from the original (PDF) on 13 March 2023. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 5.4 5.5 https://web.archive.org/web/20210830222414/https://old.volgaenergo.ru/o_kompanii/novosti/novosti_kompanii/detail.php?id=105. Archived from the original on 30 August 2021. {{cite web}}: Missing or empty |title= (help)
  6. 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 (PDF) https://web.archive.org/web/20211123173128/https://admgor.nnov.ru/uploads/editor/20/a7/gl1.pdf. Archived from the original (PDF) on 23 November 2021. {{cite web}}: Missing or empty |title= (help)
  7. 7.00 7.01 7.02 7.03 7.04 7.05 7.06 7.07 7.08 7.09 7.10 7.11 7.12 7.13 7.14 7.15 7.16 7.17 https://web.archive.org/web/20220605045016/https://ru.wikipedia.org/wiki/%D0%90%D0%B2%D1%82%D0%BE%D0%B7%D0%B0%D0%B2%D0%BE%D0%B4%D1%81%D0%BA%D0%B0%D1%8F_%D0%A2%D0%AD%D0%A6. Archived from the original on 05 June 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  8. 8.0 8.1 http://pravo.gov.ru/proxy/ips/?docbody=&prevDoc=102414460&backlink=1&&nd=102405847. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 9.2 9.3 9.4 https://web.archive.org/web/20210909171250/https://government-nnov.ru/?id=195507. Archived from the original on 09 September 2021. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  10. https://web.archive.org/web/20210909162220/https://www.nta-nn.ru/news/economy/2015/news_535161/. Archived from the original on 09 September 2021. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  11. https://web.archive.org/web/20220708160248/https://www.reuters.com/article/orubs-eurosibenergo-station-coal-idRUKBN0M11EJ20150305. Archived from the original on 08 July 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  12. "Слабый рубль заморозил проект ТЭЦ Евросибэнерго, поднял экспорт угля". Reuters.com. Mar 5, 2015. Retrieved Apr 25, 2022.
  13. "Приказ Министерства энергетики РФ от 28 февраля 2022 г. № 146 "Об утверждении схемы и программы развития Единой энергетической системы России на 2022 - 2028 годы"".{{cite web}}: CS1 maint: url-status (link)
  14. "СХЕМА И ПРОГРАММА РАЗВИТИЯ ЭЛЕКТРОЭНЕРГЕТИЧЕСКИХ СИСТЕМ РОССИИ НА 2023–2028 ГОДЫ НИЖЕГОРОДСКАЯ ОБЛАСТЬ" (PDF). SO UPS of Russia. February 28, 2023. Retrieved December 5, 2023.{{cite web}}: CS1 maint: url-status (link)
  15. "Минэнерго согласилось снизить штрафы за отказ от проектов КОММод на 55–65%". peretok.ru. September 24, 2023. Retrieved December 5, 2023.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.