Baotou Hexi power station (华电包头发电厂) is an operating power station of at least 1200-megawatts (MW) in Machi, Jiuyuan, Baotou, Inner Mongolia, China with multiple units, some of which are not currently operating. It is also known as 华电包头河西电厂.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Baotou Hexi power station Machi, Jiuyuan, Baotou, Inner Mongolia, China 40.5709362, 109.7951317 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase II Unit 3, Phase II Unit 4: 40.5709362, 109.7951317
  • Phase I Unit 1, Phase I Unit 2: 40.5701785, 109.7897806

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Phase I Unit 1 operating coal - bituminous 600 subcritical 2006
Phase I Unit 2 operating coal - bituminous 600 subcritical 2006
Phase II Unit 3 cancelled coal - unknown 660 unknown
Phase II Unit 4 cancelled coal - unknown 660 unknown

Table 3: Unit-level ownership and operator details

Unit name Owner
Phase I Unit 1 Baotou Power Generation Branch of Huadian Inner Mongolia Energy Co Ltd [100.0%]
Phase I Unit 2 Baotou Power Generation Branch of Huadian Inner Mongolia Energy Co Ltd [100.0%]
Phase II Unit 3 Baotou Power Generation Branch of Huadian Inner Mongolia Energy Co Ltd [100.0%]
Phase II Unit 4 Baotou Power Generation Branch of Huadian Inner Mongolia Energy Co Ltd [100.0%]

Background

The two existing coal-fired units of Baotou Hexi power station, totaling 1,200 MW, were brought online in 2006. The plant is owned by China Huadian.[1]

Description of Expansion

Huadian has proposed to build additional coal-fired units at this plant.[1][2]

In August 2015 Huadian said it would be pursuing a phase II of 2 x 660 MW at the power station.[3]

2016: Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity

Due to new restrictions announced during 2016 by the National Energy Administration and the National Development and Reform Commission, further capacity expansions at this location appear to be on hold or cancelled. For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.

Plant Details for Existing Phase I

  • Sponsor: Huadian Inner Mongolia Energy Co
  • Parent company: China Huadian
  • Location: Machi, Kundulun (Hondlon) District, Baotou Prefecture, Inner Mongolia Autonomous Region, China
  • Coordinates: 40.5701785, 109.7897806 (exact)
  • Status: Operating
  • Gross capacity: 1,200 MW (Units 1 & 2: 600 MW)
  • Type: Subcritical
  • In service: 2006
  • Coal type:
  • Coal source:
  • Source of financing:

Articles and Resources

References

  1. 1.0 1.1 "公司简介", 中国华电集团公司内蒙古公司, chd.com.cn, accessed December 2014
  2. Ailun Yang and Yiyun Cui, "Global Coal Risk Assessment: Data Analysis and Market Research," World Resources Institute working paper, November 2012
  3. "华电包头河西电厂(二期)项目签约举行," 包头日, 2015-08-06

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.