Barru power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Barru power station is an operating power station of at least 100-megawatts (MW) in Lampoko, Balusu, Barru, South Sulawesi, Indonesia with multiple units, some of which are not currently operating. It is also known as 巴鲁火电站.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Barru power station Lampoko, Balusu, Barru, South Sulawesi, Indonesia -4.29329, 119.63135 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase II Unit 1, Unit 1, Unit 2: -4.29329, 119.63135

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Phase II Unit 1 construction coal - unknown 100 subcritical 2022
Unit 1 operating coal - unknown 50 subcritical 2013
Unit 2 operating coal - unknown 50 subcritical 2013

Table 3: Unit-level ownership and operator details

Unit name Owner
Phase II Unit 1 PT PLN (Persero) [100.0%]
Unit 1 PT PLN (Persero) [100.0%]
Unit 2 PT PLN (Persero) [100.0%]

Background on Units 1 and 2

The two-unit, 100-MW Barru-1 coal-fired power plant was built by PLN and went online in 2013.[1]

Barru-2

In November 2015, it was reported that an additional 100 MW has been pre-qualified for tender.[2]

The units are listed in the Indonesia Electricity Supply Business Plan (RUPTL) 2017-2026, with a planned operation date of 2019.[3]

In November 2017 a joint venture of PT Wijaya Karya (Persero) Tbk and Mitsubishi Corporation secured the Engineering, Procurement, and Construction (EPC) contract for the project.[4] In July 2018 construction of Barru-2 began.[5] In March 2019 construction of Barru-2 was reported to be 20% complete.[6] In January 2020 construction of Barru-2 was reported to be 70% complete.[7] In March 2021 construction of Barru-2 was 78% complete, with a targeted commissioning date of 2022.[8] In September 2021 construction of Barru-2 was 90% complete.[9]

In April 2022, it was reported that the Sulsel Barru-2 power station was synchronized. The unit was targeted to operate commercially (COD) by October 2022.[10][11]

In early 2023, the expansion was listed as a 2022 achievement.[12] The unit was presumed to be fully built, but it was unclear that it had reached Commercial Operation (COD).

In June 2023, staff were pictured conducting a "Work Progress Check for Construction Supervision of PLTU Sulsel Barru Unit 3", suggesting that construction work was ongoing.[13]

Planet imagery showed minimal visible construction progress between January and November 2023.

Financing

Barru-2: In 2015, it was reported that the project will be financed by corporate loan to PLN or the minimum amount of 70% (excluding VAT) of the contract price and the remaining will be financed by PLN’s own budget. At least 50 percent of the loan portion shall be covered under Export Credit Agency and the remaining loan portion shall be covered by the lenders or any other sources without government guarantee and no collateral.[14]

Articles and Resources

References

  1. PLTU Barru Siap Beroperasi, PLN press release, July 2013.
  2. "Tender Info: PLN Prequalifies EPC of Sulsul Barr-2 Kalselteng-2 Coal-Fired Steam Power Plants," RambuEnergy, November 15, 2015
  3. Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2017-2026, PT PLN Persero, p. D-62
  4. PLN – PLTU Sulsel Barru II Coal-Fired Power Plant 100 MW – South Sulawesi - Project Profile, JSB Market Research, Apr. 10, 2018
  5. Pembangunan PLTU 2 Barru Resmi Dimulai, Rakyatku, Jul. 3, 2018
  6. Mengintip Progress PLTU 2 Barru di HUT ke-59 PT. Wika, Rakyatku, Mar. 11, 2019
  7. Pembangunan Proyek PLTU 2. Barru Bangun Fisik dan SDM Lokal, Rakyat Sulsel, Jan. 15, 2020
  8. DJPPR Virtually Monitors The Progress Of PLTU Sulsel Barru 2, DIRECTORATE GENERAL OF FINANCING AND RISK MANAGEMENT, MINISTRY OF FINANCE, Apr. 6, 2021
  9. Pembangunan PLTU Sulsel Barru-2 Rampung 90%, Makassar, Sep. 14, 2021
  10. PLN Sinkronisasi PLTU Sulsel Barru-2 100MW, Bisnis, Apr. 13, 2022
  11. PLN Sinkronisasi PLTU Sulsel Barru-2 100MW, Apr. 19, 2022
  12. "Progres Proyek Listrik 35 GW Baru 47 Persen hingga Desember 2022," VOI, Feb. 1, 2023
  13. "PLN Enjiniring Melakukan Kunjungan ke PLTU Sulsel Barru Unit 3 (1×100 MW)," PLN Enjiniring, June 17, 2023
  14. "TENDER INFO: PLN prequalifies EPC of Sulsel Barru-2, Kalselteng-2 coal fired steam power plants". rambuenergy.com. November 2015.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.