Borinquen geothermal power project (local name: Central geotérmica Borinquen) is a geothermal power plant in pre-construction in Liberia, Guanacaste, Costa Rica.


Project Details

Table 1: Unit-level project details for Borinquen geothermal power project

Unit Name Status Commissioning Year Nameplate Capacity Type Owner Operator
1 Pre-construction[1] 2027 (planned)[2] 55 MW[3] Unknown type Costa Rican Electricity Institute (ICE)[4] Costa Rican Electricity Institute (ICE)[4]
2 Pre-construction[1] 2027 (planned)[1] 55 MW[3] Unknown type Costa Rican Electricity Institute (ICE)[3] Costa Rican Electricity Institute (ICE)[3]


Location

Table 2: Unit-level location details for Borinquen geothermal power project

Unit Name Location Coordinates (WGS 84)
1 Liberia, Guanacaste, Costa Rica[5] 10.6344, -85.4397 (approximate)[5]
2 Liberia, Guanacaste, Costa Rica[3] 10.6344, -85.4397 (approximate)[3]

The map below shows the approximate location of the geothermal power plant units:

Loading map...

Background

Articles and Resources

Additional data

To access additional data, including an interactive map of global geothermal power plants, a downloadable dataset, and summary data, please visit Global Geothermal Power Tracker on the Global Energy Monitor website.

References

  1. 1.0 1.1 1.2 https://web.archive.org/web/20221206001404/https://revistasumma.com/costa-rica-proyecto-geotermico-borinquen-aumenta-conectividad-ecologica-en-liberia/. Archived from the original on 2022-12-06. {{cite web}}: Missing or empty |title= (help)
  2. "Wildlife benefits from ecological work at Borinquen geothermal project". Think Geoenergy. January 24, 2022. Archived from the original on March 7, 2022. Retrieved July 13, 2022.
  3. 3.0 3.1 3.2 3.3 3.4 3.5 "Costa Rica secures 4m funding for Borinquen geothermal project". Think Geoenergy. August 31, 2016. Archived from the original on April 18, 2022. Retrieved July 13, 2022.
  4. 4.0 4.1 "Costa Rica postpones development of Borinquen 1 geothermal project". Think Geoenergy. November 9, 2018. Archived from the original on April 18, 2022. Retrieved July 13, 2022.