Bukhara Teploenergo 3 power station

From Global Energy Monitor
Part of the
Global Oil and Gas Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related categories:

Bukhara Teploenergo 3 power station (котельная №-3 предприятия «Теплоэнерго» г.Бухары) is a power station in the pre-permit stage in Bukhara, Uzbekistan. It is also known as 3-boiler plant of the Teploenergo enterprise in Bukhara.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Bukhara Teploenergo 3 power station Bukhara, Bukhara, Bukhara, Uzbekistan 39.743978, 64.411911 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 39.743978, 64.411911

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Retired year
Unit 1 pre-permit[2][3] fossil gas - natural gas[4] 54[4] gas turbine[4] 2024[3]
Unit 2 pre-permit[2][3] fossil gas - natural gas[4] 54[4] gas turbine[4] 2024[3]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Teploenergo [100.0%]
Unit 2 Teploenergo [100.0%]

Background

In May 2023, an agreement was signed between JSC Thermal Power Stations and Siemens Energy for installation of two gas turbines, 54 MW each, at the power station.[5] The turbines were expected to be delivered and installed in 2023 and commissioned in December 2023.[6] As of March 2024, there have not been any updates about the project.

Articles and Resources

References

  1. https://www.google.com/maps/place/Kotel'naya+Rk-3/@39.743775864.409336517z/data=!4m14!1m7!3m6!1s0x3f500710b5243333:0x29f47d8229fb79f7!2sKotel'naya+Rk-3!8m2!3d39.7437717!4d64.4119114!16s%2Fg%2F11pr3_thcy!3m5!1s0x3f500710b5243333:0x29f47d8229fb79f7!8m2!3d39.7437717!4d64.4119114!16s%2Fg%2F11pr3_thcy?entry=ttu. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 https://neftegaz.ru/news/energy/778894-siemens-i-uzbekistan-zaklyuchili-soglasheniya-v-sfere-energetiki-na-72-mln-evro/. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 https://web.archive.org/web/20240404092857/https://kun.uz/en/news/2023/05/03/siemens-to-build-two-tpps-in-uzbekistan. Archived from the original on 04 April 2024. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 4.4 4.5 https://web.archive.org/web/20240120032332/http://www.uzdaily.com/en/post/80743. Archived from the original on 20 January 2024. {{cite web}}: Missing or empty |title= (help)
  5. "Siemens и Узбекистан заключили соглашения в сфере энергетики на 72 млн евро". neftegaz.ru. May 5, 2023. Retrieved March 29, 2024.{{cite web}}: CS1 maint: url-status (link)
  6. "Siemens to build two TPPs in Uzbekistan". kun.uz. May 3, 2023. Retrieved March 29, 2023.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.