CEEC Chongzuo power station (中能建崇左发电项目) is an operating power station of at least 1320-megawatts (MW) in Qvjiu Town, Fusui County, Chongzuo, Guangxi, China with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| CEEC Chongzuo power station | Qvjiu Town, Fusui County, Chongzuo, Guangxi, China | 22.494869, 107.555455 (exact)[1] |
Unit-level coordinates (WGS 84):
- Phase II Unit 3, Phase II Unit 4, Unit 1, Unit 2: 22.494869, 107.555455
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|
| Phase II Unit 3 | Shelved[2] | coal: unknown[3][2] | 660[2] | ultra-supercritical[2] | 2025 (planned)[2] | False |
| Phase II Unit 4 | Shelved[2] | coal: unknown[3][2] | 660[2] | ultra-supercritical[2] | 2025 (planned)[2] | False |
| Unit 1 | Operating[4] | coal: unknown[3][1] | 660[5] | ultra-supercritical[1] | 2025[4] | False |
| Unit 2 | Operating[6][5] | coal: unknown[3][1] | 660[5] | ultra-supercritical[1] | 2025[6] | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase II Unit 3 | China Energy Construction Chongzuo Development Investment Co Ltd [100%][1] | China Energy Engineering Corp Ltd [100.0%] |
| Phase II Unit 4 | China Energy Construction Chongzuo Development Investment Co Ltd [100%][1] | China Energy Engineering Corp Ltd [100.0%] |
| Unit 1 | China Energy Construction Chongzuo Development Investment Co Ltd [100%][1] | China Energy Engineering Corp Ltd [100.0%] |
| Unit 2 | China Energy Construction Chongzuo Development Investment Co Ltd [100%][1] | China Energy Engineering Corp Ltd [100.0%] |
Project-level coal details
- Coal source(s): domestic/imported
- Permit(s): 桂发改电力〔2022〕1325 号[2]
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background on Project
The draft EIA for the plant was released in June 2021. According to the updated project schedule, the power plant was scheduled to start construction in July 2021. Unit No. 1 was planned to be put into operation in July 2023, and Unit No. 2 in December 2023.[7]
Construction reportedly began in April 2022.[8] In August 2022, a news article reported that the project had again begun construction.[9]
However, with no known permit documents or evidence of construction, the units are presumed still under pre-permit development.
According to a 2023 list of key construction projects in Guangxi, the power project had indeed begun construction in August 2022.[10] The power station was estimated to begin operation in 2025.[10]
A second phase of the power plant (2 x 660 MW units) was reportedly announced in 2023.[10]
Unit 1 saw the boiler heating surface welded on October 18, 2023[11], the sixth layer of steel structure passed inspection on December 7[12], and the boiler beam was hoisted on December 19[13]. In 2024, the main plant steel roof truss and deaerator were hoisted in January[14][15], the main plant was enclosed and the cooling tower was topped out in March[16], the generator stator was hoisted in July[17], and the turbine was covered in November[18].
In 2025, the unit was connected to the grid on March 13[19] and passed the 168-hour trial on April 24[20].
Unit 2 saw boiler steel frame hoisting begin on August 21, 2023[21]. In 2024, the boiler beam was hoisted in February[22], the cooling tower was completed in July[23], the turbine stator and main transformer were installed in September–October[24][25], the boiler hydraulic test passed in October[26], and the plant power system received power in November[27].
In 2025, the turbine cover was completed in January[28], flushing was completed in April[29], the unit was connected to the grid in May[30], and it passed the 168-hour trial in June[31].
Phase II (units 3 and 4) received an EIA approval in August 2024 and land pre‑approval in December 2024.[32] By 2025, the project was not on the provincial key projects list. Construction had not started by late 2025 and was shelved by mid-2026[33].
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 https://news.bjx.com.cn/html/20210624/1160265.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 (PDF) http://sthjt.gxzf.gov.cn/zfxxgk/zfxxgkgl/fdzdgknr/hjjccf/xzxk/npzxm/P020240819607411855826.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 3.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 https://news.bjx.com.cn/html/20250425/1438608.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 5.2 "中能建崇左2×660MW电厂工程2号机组锅炉钢架顺利开吊-北极星火力发电网". news.bjx.com.cn. 2023-08-21. Archived from the original on 2024-01-25. Retrieved 2023-10-16.
- ↑ 6.0 6.1 https://news.bjx.com.cn/html/20250619/1447092.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ "广西崇左市拟建2台百万千瓦煤电机组," 北极星电力网新闻中心, 2021/6/24
- ↑ 2×660MW!中国能建崇左电厂项目开工, BJX, 2022-04-15
- ↑ 中能建崇左2×660MW电厂工程开工, BJX, 2022-08-19
- ↑ 10.0 10.1 10.2 广西能源基础设施建设2023年工作推进方案:加快油气及煤炭储运建设 计划完成投资44.8亿元, BJX, March 30, 2023
- ↑ "中能建崇左电厂一号机组锅炉受热面顺利开焊". 北极星电力网. 2023-10-30. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂1号机组锅炉第六层钢结构通过验收". 北极星电力网. 2023-12-11. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂一号锅炉首根大板梁顺利吊装就位". 微信公众平台. 2023-12-21. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂1号机组主厂房钢屋架开始吊装". 微信公众平台. 2024-01-24. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂一号机组除氧器吊装就位". 微信公众平台. 2024-01-24. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂1号主厂房封闭断水及1号冷却塔结顶". 微信公众平台. 2024-06-14. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂1号机组发电机定子一次吊装就位". 北极星电力网. 2024-07-15. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂1号机组汽轮机扣盖完成". 微信公众平台. 2024-11-19. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂1号机组首次并网一次成功". 北极星电力网. 2025-03-14. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂1号机组通过168小时试运行". 北极星电力网. 2025-04-25. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂2号机组锅炉钢架顺利开吊". 北极星电力网. 2023-08-21. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "崇左项目2号机组锅炉首根大板梁顺利起吊". 微信公众平台. 2024-03-22. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂2号冷却塔提前34天顺利到顶". 北极星电力网. 2024-07-26. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂2号机组汽轮机定子顺利吊装就位". 微信公众平台. 2024-10-30. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂2号机主变压器顺利就位". 微信公众平台. 2024-10-30. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "崇左电厂2号机组锅炉水压试验一次成功". 微信公众平台. 2024-11-19. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左项目2号机厂用受电一次成功". 微信公众平台. 2024-11-19. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "崇左项目2号机组汽机扣盖顺利完成". 微信公众平台. 2025-01-31. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左项目2号机锅炉点火冲管圆满完成". 北极星电力网. 2025-04-25. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左项目2号机首次并网成功". 北极星电力网. 2025-05-16. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中能建崇左电厂2号机组通过168小时试运行". 北极星电力网. 2025-06-19. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "自治区生态环境厅关于中能建崇左电厂二期工程项目环评审批公示". 广西生态环境厅. 2024-08-19. Retrieved 2026-06-12.
{{cite web}}: CS1 maint: url-status (link) - ↑ "崇左电厂二期项目搁置". 北极星电力网. 2026-05-15. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.