Central Java FSRU

From Global Energy Monitor
Part of the
Global Gas Infrastructure Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error

Central Java FSRU is a cancelled (inferred 4 y) LNG import terminal in Indonesia.

Location

Table 1: Location details

Name Location Coordinates (WGS 84)
Central Java FSRU Cilicap, Central Java, Indonesia[1] -7.733333, 109.0 (approximate)

The map below shows the approximate location of the terminal:

Loading map...

Project Details

Table 2: Infrastructure details

mtpa = million tonnes per year
Name Facility type Status Capacity Total terminal capacity Offshore Associated infrastructure
Central Java FSRU import[2] cancelled (inferred 4 y) 1.4 mtpa[2] 1.4 mtpa True –

Table 3: Cost

Name Facility type Cost Total known terminal costs
Central Java FSRU import[2] – –

Financing

No financing data available.

Table 4: Project timeline

FID = Final Investment Decision, used by some developers to indicate a project will move forward
Name Facility type Status Proposal year FID year Construction year Operating year Inactive year
Central Java FSRU import[2] cancelled (inferred 4 y) 2016[3] – – – 2024 (cancelled)

Ownership

Table 5: Ownership

Name Facility type Status Owners Parent companies Operator
Central Java FSRU import[2] cancelled (inferred 4 y) PT Pertamina (Persero) [100%][3] PT Pertamina (Persero) [100.0%] –

Background

PT Pertamina has opened tenders for a third FSRU-based terminal in Indonesia to import up to 1.6 mtpa via Cilacap in Central Java, Central Java FSRU. The Central Java FSRU will be a 25-year build, own, operate, transfer (BOOT) contract. Pertamina is asking bidders to explain where and how they would source the LNG and to supply the vessel for the project.[4] In August 2019 Pertamina stated that the FSRU's capacity would be 200 million cubic feet per day or approximately 1.4 million tonnes per annum.[5]

In May 2021, Pertamina announced plans to build a small-scale LNG import facility (Central Java Mini LNG Terminal) at its oil refinery in Cilacap, with a capacity of 0.84 mtpa.[6]

There have been no development updates in over four years, and the project is inferred to be shelved as of 2024.

Articles and Resources

Additional data

To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.

References

  1. ↑ https://www.google.com/maps/place/7%C2%B044'00.0%22S+109%C2%B000'00.0%22E/@-7.733333,108.9974197,1272m/data=!3m2!1e3!4b1!4m4!3m3!8m2!3d-7.733333!4d109?entry=ttu&g_ep=EgoyMDI1MDgxMy4wIKXMDSoASAFQAw%3D%3D. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.0 2.1 2.2 2.3 2.4 https://www.spglobal.com/platts/en/market-insights/latest-news/natural-gas/080619-analysis-indonesia-natural-gas-exports-set-to-slump-to-2-decade-low-in-2019. {{cite web}}: Missing or empty |title= (help)
  3. ↑ 3.0 3.1 http://bit.ly/2lHSige. {{cite web}}: Missing or empty |title= (help)
  4. ↑ Karen Thomas, "Small-scale LNG supplement: Indonesia - big plans for small-scale LNG," LNG World Shipping, 25 Apr 2016
  5. ↑ Indonesia natural gas exports set to slump to 2-decade low in 2019, S&P Platts Global, Aug. 6, 2019
  6. ↑ Evans, Damon (2021-05-28). "Pertamina set to build small-scale LNG regas unit - News for the Energy Sector". Energy Voice. Retrieved 2022-06-30.