Changde power station (华电常德发电厂) is an operating power station of at least 1320-megawatts (MW) in Deshan Town Fengshugang Villege, Wuling District, Changde, Hunan, China.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Changde power station | Deshan Town Fengshugang Villege, Wuling District, Changde, Hunan, China | 29.031, 111.7 (exact) |
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 29.031, 111.7
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Unit 1 | Operating | coal: unknown[1] | 660 | ultra-supercritical | yes | 2015 | False |
| Unit 2 | Operating | coal: unknown[1] | 660 | ultra-supercritical | yes | 2015 | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Hunan Huadian Changde Power Generation Co Ltd [100%] | Huadian Power International Co Ltd [49.0%]; Shaanxi Coal and Chemical Industry Co Ltd [49.0%]; unknown [2.0%] |
| Unit 2 | Hunan Huadian Changde Power Generation Co Ltd [100%] | Huadian Power International Co Ltd [49.0%]; Shaanxi Coal and Chemical Industry Co Ltd [49.0%]; unknown [2.0%] |
Project-level coal details
- Coal source(s): domestic
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background on Project
China Huadian (49%), Shaanxi Coal and Chemical Industry Group (49%), and Changde Economic Construction Investment Group (2%) are currently planning to build a coal-fired power plant with a total planned capacity of 1,320 MW in Hunan Province.[2]
Construction began in 2013.[3] The power station is planned for operation in 2015,[4] and was commissioned in 2015.[5]
Articles and Resources
References
- ↑ 1.0 1.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "华电集团常德电厂项目获得国家能源局“路条”" accessed June 2013
- ↑ "中国能建承建华电常德电厂一期工程开工", 国务院国资委信息中心, 2013-12-27
- ↑ "华电常德电厂一期2×660MW工程开工 2015年'双投'", 北极星电力网,新闻频道,火力发电网, 2013-1227