Chifeng Zhongtang Special Steel Co Ltd (赤峰中唐特钢有限公司) is a steel plant in Ningcheng, Chifeng, Inner Mongolia, China that operates basic oxygen furnace (BOF) and blast furnace (BF) technology.
Location
The map below shows the exact location of the plant in Ningcheng, Chifeng, Inner Mongolia, China:
Location: Xizi Town Industrial Park
Coordinates (WGS 84 ): 41.834064, 119.281883 (exact)
Background
Chifeng Zhongtang Special Steel Co., Ltd. planned to build two 1580m3 blast furnaces and two 120-tonne basic oxygen furnaces in 2020.[ 1]
The construction of the project started in June 2020.[ 2]
As of November 6, 2021, the two blast furnaces have been fired in succession.[ 3]
The #1 blast furnace was put into production in April 2022.[ 4]
The #2 blast furnace was put into production in September 2022.[ 5]
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker , a project of Global Energy Monitor.
Plant Details
Table 1: General Plant Details
Construction date
Start date
2020-06[ 6]
2022[ 7]
Table 2: Ownership and Parent Company Information
Parent company
Parent company PermID
Parent GEM entity ID
Owner
Owner company PermID
Owner GEM entity ID
Tangshan Jinma Iron & Steel Group Co Ltd [83.7%]; Hainan Mingbo Investment Co Ltd [16.0%]; unknown [0.3%]
unknown [83.7%]; unknown [16.0%]; not applicable [0.3%]
E100000126512 [83.7%]; E100000128365 [16.0%]; E100000132388 [0.3%]
Chifeng Zhongtang Special Steel Co Ltd [100%][ 8]
unknown
E100000126095 [100%]
Table 3: Process and Products
Table 4: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)
1 Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status1
Basic oxygen furnace steelmaking capacity
Nominal crude steel capacity (total)
operating
2700[ 10]
2700[ 10]
Table 5: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
1 Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status1
Blast furnace capacity
Nominal iron capacity (total)
operating
2740[ 10]
2740[ 10]
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Ferronickel
Sinter
Coke
Pellets
NF
NF
NF
NF
Table 7: Actual Plant-level Crude Steel Production by Year (thousand tonnes per annum)
Year
BOF production
Other/unknown steel production
2024
unknown
unknown
Table 8: Actual Plant-level Crude Iron Production by Year (thousand tonnes per annum)
Year
BF production
Other/unknown iron production
2022
unknown
unknown
2023
unknown
unknown
2024
unknown
unknown
Unit Details
Table 9: Blast Furnace Details
Unit name
Status
Start date
Current size
Current capacity (ttpa)
Decarbonization technology
BF 1
operating[ 11]
2022[ 11]
1580.0 m3[ 10]
1370[ 10]
unknown
BF 2
operating[ 7]
2022[ 7]
1580.0 m3[ 10]
1370[ 10]
unknown
Table 10: Basic Oxygen Furnace Details
Unit name
Status
Construction date
Start date
Current capacity (ttpa)
Current size
unknown BOF (1)
operating[ 6] [ 12]
2020-09-30[ 13]
2024[ 12]
1350[ 10]
120.0 tonnes[ 10]
unknown BOF (2)
operating[ 6] [ 12]
2020-09-30[ 13]
2024[ 12]
1350[ 10]
120.0 tonnes[ 10]