Chuo Trunk Line Gas Pipeline is an operating natural gas pipeline in Japan.[1]

Location

The first phase pipeline runs from Edogawa Ward, Tokyo to Soku, Saitama. The second phase of the pipeline runs from Soku to Kawaguchi city, Japan. [1]

Loading map...

Project Details

  • Operator: Tokyo Gas
  • Parent Company: Tokyo Gas
  • Current Capacity:
  • Proposed Capacity:
  • Length: 20.38 mi / 32.8 km
    • Phase one: 14.42 mi / 23.2 km
    • Phase two: 5.97 mi / 9.6 km
  • Status: Operating
  • Start Year:
    • Phase one: October 2009
    • Phase two: October 2010

Background

The pipeline operates at a pressure of 7.0 MPa and has a diameter of 600 mm.[1]