Chuzhou power station (中煤新集能源滁州电厂2×660MW超超临界机组, 大唐滁州发电厂) is an operating power station of at least 1320-megawatts (MW) in Shahe Town, Nanqiao District, Chuzhou, Anhui, China with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Chuzhou power station Shahe Town, Nanqiao District, Chuzhou, Anhui, China 32.9337496, 117.6878713 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Phase II Unit 1, Phase II Unit 2, Unit 1, Unit 2: 32.9337496, 117.6878713

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Phase II Unit 1 Announced[2] coal: unknown[3][2] 1000[2] ultra-supercritical – False
Phase II Unit 2 Announced[2] coal: unknown[3][2] 1000[2] ultra-supercritical – False
Unit 1 Operating[4][5] coal: unknown[3][1] 660[1] ultra-supercritical[6] 2026[4][6] False
Unit 2 Operating[7][8] coal: unknown[3][1] 660[1] ultra-supercritical[7] 2026[6][8] False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase II Unit 1 Datang Fengyang Xiaogang Village Energy Co Ltd [100%][1] Datang International Power Generation Co Ltd [51.0%]; China Coal Xinji Energy Co Ltd [49.0%]
Phase II Unit 2 Datang Fengyang Xiaogang Village Energy Co Ltd [100%][1] Datang International Power Generation Co Ltd [51.0%]; China Coal Xinji Energy Co Ltd [49.0%]
Unit 1 Datang Fengyang Xiaogang Village Energy Co Ltd [100%][1] Datang International Power Generation Co Ltd [51.0%]; China Coal Xinji Energy Co Ltd [49.0%]
Unit 2 Datang Fengyang Xiaogang Village Energy Co Ltd [100%][1] Datang International Power Generation Co Ltd [51.0%]; China Coal Xinji Energy Co Ltd [49.0%]

Project-level coal details

  • Coal source(s): domestic

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Financing

  • Source of financing: Datang Anhui Power Generation Co., Ltd. and China Coal Xinji Energy Co., Ltd. (5.24 billion yuan)

Background on Project

China Datang was planning to build a two-unit coal-fired power plant with a total capacity of 2,000 MW in Anhui Province.[9][10][11][12]

The project's Environmental Impact Assessment (EIA) was published in January 2014.[13]

In 2015, the plant's EIA was rejected due to insufficient plans to reduce regional pollution; being in an environmentally-sensitive location; and having insufficient public participation. The planned capacity was listed as 2 x 660 MW.[14][15]

However, in the Anhui Province Power Development 13th 5-Year Plan published in May 2017, Chuzhou power station was listed as a start-construction project.[16]

As of July 2018, the power station was moving forward in a new location to avoid the problems with the original EIA.[17]

The plant was approved for construction in July 2020.[18]

In July 2021, it was agreed that Datang Anhui Power Generation Co., Ltd. and China Coal Xinji Energy Co., Ltd. would jointly fund the construction. The total investment of the project is about 5.24 billion yuan. Datang Anhui will invest about 802 million yuan in accordance with a 51% equity ratio.[19]

Bidding announcements for construction were reportedly released in late 2021.[20]

The plant reportedly began construction in May 2022.[21]

In December 2023, the investment agreement was finalized. In March 2024, foundation excavation for the chimney began. In April 2024, cooling tower construction started. In May 2024, chimney concrete was poured. In July 2024, the EPC contract was signed. In August 2024, boiler steel er****ion progressed. In December 2024, the first beam was hoisted, and the chimney was topped out. In March 2025, steel roof hoisting began. In March 2025, boiler heating surface hoisting began. In May 2025, the cooling tower was topped out. In September 2025, high and medium pressure cylinders were placed. In October 2025, the generator rotor was installed, and chimney painting was completed. In November 2025, the boiler hydrostatic test succeeded. In January 2026, the boiler dynamic field test was completed. In March 2026, turbine spin and grid connection succeeded. Unit 1 completed its 168-hour trial run in March 2026[22].

In September 2024, the cooling tower ring beam was poured. In April 2025, the absorber tower was topped out. In May 2025, the DCS was energized. In June 2025, the generator stator was placed. In September 2025, turbine cylinder work was completed. In December 2025, steam blowing was completed. In December 2025, grid connection succeeded. Unit 2 completed its 168-hour trial run in January 2026[23].

In December 2025, the preliminary feasibility study was awarded. In December 2025, the study was won by Anhui Design Institute.

Articles and Resources

References

  1. ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 http://news.bjx.com.cn/html/20200727/1092356.shtml. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.0 2.1 2.2 2.3 2.4 2.5 https://news.bjx.com.cn/html/20251216/1474903.shtml. {{cite web}}: Missing or empty |title= (help)
  3. ↑ 3.0 3.1 3.2 3.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  4. ↑ 4.0 4.1 https://news.bjx.com.cn/html/20260330/1489690.shtml. {{cite web}}: Missing or empty |title= (help)
  5. ↑ https://mp.weixin.qq.com/s/YbwbENM0KJ46eSGti3N_-g. {{cite web}}: Missing or empty |title= (help)
  6. ↑ 6.0 6.1 6.2 https://mp.weixin.qq.com/s/_gYJoIaaPL-A5Dq0a2H2Lg. {{cite web}}: Missing or empty |title= (help)
  7. ↑ 7.0 7.1 https://mp.weixin.qq.com/s/HPFmNze4_GCnvJ09xNdBAA. {{cite web}}: Missing or empty |title= (help)
  8. ↑ 8.0 8.1 https://caifuhao.eastmoney.com/news/1663088847. {{cite web}}: Missing or empty |title= (help)
  9. ↑ Ailun Yang and Yiyun Cui, "Global Coal Risk Assessment: Data Analysis and Market Research," World Resources Institute working paper, November 2012
  10. ↑ "大唐滁州发电厂2×1000兆瓦机组初可研报告通过审查," 中国能源信息网, 2007-03-13.
  11. ↑ Datang Chuzhou Powerplant, Enipedia, accessed 2014-11.
  12. ↑ Datang Chuzhou Power Plant's Feasibility Study Report for Two 1,000 MW Units Passes Preliminary Examination, Industrial Info Resources, 2007-05-29.
  13. ↑ 大唐滁州发电厂2×1000MW 新建工程环境影响评价公示, CPECC East China Electric Power Design Institute, 2014-01-24.
  14. ↑ "大唐安徽火电项目环评被退," 北极星电力网新闻中心来源, Dec 14, 2015
  15. ↑ "大唐电厂项目为什么会在滁州建设、它会给滁州带来哪些利弊?现在滁州网记者就项目背景," 滁州网, 2015-05-11
  16. ↑ "安徽省电力发展“十三五”规划"安徽省能源局, 2017-5
  17. ↑ "大唐滁州发电项目用地预审顺利通过省级踏勘论证," 2018-07-30
  18. ↑ "大唐滁州发电厂2×660MW机组工程获得核准," BJX, 2020/7/27
  19. ↑ "大唐发电:拟投建滁州2×660MW多能互补(煤电)项目," bjx, July 7, 2021
  20. ↑ "大唐滁州发电厂2X660MW机组工程桩基工程施工招标," December 17, 2021
  21. ↑ 稳增长!大唐集团9个火电、水电项目最新进展来了, Beijixing, May 17, 2022
  22. ↑ "滁州电厂1号机组顺利通过168小时试运行,正式投产". 微信公众平台. 2026-03-27. Retrieved 2026-04-01.{{cite web}}: CS1 maint: url-status (link)
  23. ↑ "滁州发电2×660MW超超临界二次再热机组新建工程2号机组圆满完成168小时满负荷试运行,正式投产". 微信公众平台. 2026-01-30. Retrieved 2026-03-06.{{cite web}}: CS1 maint: url-status (link)