Cuncaota Coal Mine(中国神华能源股份有限公司金烽寸草塔煤矿)is located in Ulan Mulun Town, Ejin Horo Banner, Ordos City, Inner Mongolia, China with a production capacity of 4.5 million tons per year.[1]

Location

The undated satellite photo below shows the coal mine located in Ulan Mulun Town, Ejin Horo Banner, Ordos City, Inner Mongolia, China.

Loading map...

Coal Mine Background

Cuncaota Coal Mine is operated by Shendong Coal Branch of China Shenhua Energy Co., Ltd.,[1]It was completed and put into production by Haibowan Mining Bureau in October 1990, and transferred to Baotou Mining Bureau in April 1991, with an annual output of 150,000 tons of coal. After being transferred to Wanli Coal Branch in July 2005, it carried out technological upgradings and all were completed at the end of 2008, with an approved production capacity of 2.4 million tons per year.[2]The production capacity was increased to 4.50Mt/a in January 2018.[1]

An electrical and mechanical accident occurred in Cuncaota Coal Mine on August 12, 2020, resulting in 1 death.[3]

Project Details

  • Operator:China Shenhua Energy Co., Ltd. Shendong Coal Branch[1]
  • Parent Company: National Energy Investment Group Co., Ltd.[4]
  • Location: Ulan Mulun Town, Ejin Horo Banner, Ordos City, Inner Mongolia
  • GPS Coordinates:39.442648, 110.035292(exact)
  • Status: Operating
  • Production Capacity: 4.5Mt/a
  • Minable Reserves: 175.62Mt[2]
  • Coal Type:bituminous (non-caking coal,long flame coal)[2]
  • Mine Size: 22.64k㎡[2]
  • Mine Type: Underground
  • Start Year: 1990[2]


Articles and resources

References

  1. 1.0 1.1 1.2 1.3 "中国神华能源股份有限公司金烽寸草塔煤矿安全现状评价报告"内蒙古安邦安全科技有限公司网,June 30, 2019
  2. 2.0 2.1 2.2 2.3 2.4 "神华集团各典型煤矿基本介绍",中国煤炭期刊网,2018-11-08
  3. "关于神华集团寸草塔煤矿“8·12”机电事故的通报!"搜狐网,August 29, 2020