Datang Guangdong Huizhou Boluo Gas Thermal power station (广东大唐惠州博罗燃气热电联产项目, 大唐惠州博罗燃气热电厂) is a power station under construction in Huizhou, Yuanzhou Town, Boluo County, Guangdong, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Datang Guangdong Huizhou Boluo Gas Thermal power station Huizhou, Yuanzhou Town, Boluo County, Guangdong, China 23.182965, 113.968585 (approximate)[1][2]

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Retired year
Unit 1 construction[3][4] fossil gas - natural gas[2][3][4][5] 460[2] combined cycle[3] 2025[6]
Unit 2 construction[3][4] fossil gas - natural gas[2][3][4][5] 460[2] combined cycle[3] 2025[6]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Datang Huizhou Thermal Power Co Ltd [100.0%]
Unit 2 Datang Huizhou Thermal Power Co Ltd [100.0%]

Background

In September 2021, the Guangdong Provincial Energy Bureau approved the energy-saving report for this project. [7]In September 2023, this project officially started construction.[8]

Articles and Resources

References

  1. https://web.archive.org/web/20210604165126/http://land.huizhou.gov.cn/tzgg/content/post_4116111.html. Archived from the original on 04 June 2021. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 https://web.archive.org/web/20220708082108/https://news.bjx.com.cn/html/20220708/1239757.shtml. Archived from the original on 08 July 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 https://m.bjx.com.cn/mnews/20231007/1335047.shtml. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 https://web.archive.org/web/20240417022529/https://guangfu.bjx.com.cn/news/20240401/1369231.shtml. Archived from the original on 17 April 2024. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 https://web.archive.org/web/20240508050639/https://passport.weibo.com/visitor/visitor?entry=miniblog&a=enter&url=https%253A%252F%252Fweibo.com%252F1886674350%252FNlowD4LNJ&domain=weibo.com&ua=Mozilla%252F5.0%2520%2528Windows%2520NT%252010.0%253B%2520Win64%253B%2520x64%2529%2520AppleWebKit%252F537.36%2520%2528KHTML%252C%2520like%2520Gecko%2529%2520Chrome%252F115.0.0.0%2520Safari%252F537.36&_rand=1715144798683&sudaref=. Archived from the original on 08 May 2024. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  6. 6.0 6.1 https://weibo.com/1886674350/NlowD4LNJ,http://drc.gd.gov.cn/ywtz/content/post_4137123.html. {{cite web}}: Missing or empty |title= (help)
  7. "广东省能源局关于广东大唐惠州博罗燃气热电联产项目节能报告的审查意见". 2021-09-07. Retrieved 2023-10-23.{{cite web}}: CS1 maint: url-status (link)
  8. "大唐惠州博罗燃气热电联产项目全面开工". 2023-10-07. Retrieved 2023-10-23.{{cite web}}: CS1 maint: url-status (link)