Datang Haikou Gas power station
Part of the Global Oil and Gas Plant Tracker, a Global Energy Monitor project. |
Related categories: |
Datang Haikou Gas power station (大唐海口天然气发电厂, 海口美安气电 (Units 1-1, 1-2)) is an operating power station of at least 974-megawatts (MW) in Haikou, Hainan, China with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Datang Haikou Gas power station | Haikou, Hainan, China | 19.913828, 110.151883 (approximate)[1] |
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year |
---|---|---|---|---|---|---|
1-1 | Operating[2] | fossil gas: natural gas[2] | 487[2] | combined cycle[2] | not found | 2022[2] |
1-2 | Operating[2] | fossil gas: natural gas [93%], other: hydrogen (unknown) [7%][3][2] | 487[2] | combined cycle[2] | not found | 2023[2] |
2-1 | Announced[2] | fossil gas: natural gas[2][4][5] | 487[5] | combined cycle[2] | not found | – |
2-2 | Announced[2] | fossil gas: natural gas[2][4][5] | 487[5] | combined cycle[2] | not found | – |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
1-1 | Datang Hainan Energy Development Co Ltd [100%][4] | Datang Hainan Energy Development Co Ltd [100.0%] |
1-2 | Datang Hainan Energy Development Co Ltd [100%][4] | Datang Hainan Energy Development Co Ltd [100.0%] |
2-1 | Datang Hainan Energy Development Co Ltd [100%][4] | Datang Hainan Energy Development Co Ltd [100.0%] |
2-2 | Datang Hainan Energy Development Co Ltd [100%][4] | Datang Hainan Energy Development Co Ltd [100.0%] |
Table 4: Unit-level hydrogen conversion proposal details
Unit name | H2 ready turbine (%)? | MOU for H2 supply? | Contract for H2 supply? | Financing for supply of H2? | Co-located with electrolyzer/H2 production facility? | What % of H2 blending currently? |
---|---|---|---|---|---|---|
1-1 | – | – | – | – | – | – |
1-2[3] | – | NF | NF | NF | NF | 7.0 |
2-1 | – | – | – | – | – | – |
2-2 | – | – | – | – | – | – |
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
The first phase of Datang Haikou Gas power station (大唐海口天然气发电厂) commenced construction on February 28, 2021. Unit 1-1 started operation on November 9, 2022, and Unit 1-2 commenced operation on May 30, 2023.[6]
Articles and Resources
References
- ↑ "大唐海口天然气发电项目筹建处入驻美安科技新城". news.sina.cn. 2019-06-28. Archived from the original on 2024-05-15. Retrieved 2024-05-11.
- ↑ 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.13 2.14 2.15 https://www.cpnn.com.cn/news/yq/202306/t20230601_1605917.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 3.0 3.1 https://cctvjingji.com/part-161/14774.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 4.0 4.1 4.2 4.3 4.4 4.5 https://web.archive.org/web/20210604010205/https://news.bjx.com.cn/html/20190123/958718.shtml. Archived from the original on 2021-06-04.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.0 5.1 5.2 5.3 https://web.archive.org/web/20210604204555/https://news.bjx.com.cn/html/20200303/1049988.shtml.
{{cite web}}
: Check|archive-url=
value (help); Missing or empty|title=
(help) - ↑ "大唐海口天然气发电项目2号发电机组顺利投产". 2023-06-01. Retrieved 2023-11-07.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.