Datang Xinyu power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Datang Xinyu power station (大唐国际新余发电厂) is an operating power station of at least 2000-megawatts (MW) in Liangshan Town, Yushui, Xinyu, Jiangxi, China with multiple units, some of which are not currently operating. It is also known as 大唐国际新余第二发电公司 (Phase II Unit 1&2).
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Datang Xinyu power station | Liangshan Town, Yushui, Xinyu, Jiangxi, China | 27.679755, 114.956506 (exact)[1] |
Unit-level coordinates (WGS 84):
- Phase II Unit 1, Phase II Unit 2: 27.679755, 114.956506
- Phase I Unit 1, Phase I Unit 2: 27.7770329, 114.9091471
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Phase I Unit 1 | Retired | coal: anthracite[2] | 220 | subcritical | 1995 | 2022 | False |
| Phase I Unit 2 | Retired | coal: anthracite[2] | 220 | subcritical | 1996 | 2022 | False |
| Phase II Unit 1 | Operating[3] | coal: anthracite[2][1] | 1000[1] | ultra-supercritical[1] | 2024[3] | – | False |
| Phase II Unit 2 | Operating[4] | coal: anthracite[2][1] | 1000[1] | ultra-supercritical[1] | 2024[4] | – | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase I Unit 1 | Jiangxi Datang International Xinyu Power Generation Co Ltd [100%] | Datang International Power Generation Co Ltd [100.0%] |
| Phase I Unit 2 | Jiangxi Datang International Xinyu Power Generation Co Ltd [100%] | Datang International Power Generation Co Ltd [100.0%] |
| Phase II Unit 1 | Jiangxi Datang International Xinyu No.2 Power Generation Co Ltd [100%][1] | Datang International Power Generation Co Ltd [65.0%]; Jiangxi Provincial Investment Group Corp [26.2%]; Jiangxi Provincial State-owned Enterprise Asset Management(Holding) Co Ltd [5.3%]; Jiangxi Financial Investment Group Co Ltd [3.5%] |
| Phase II Unit 2 | Jiangxi Datang International Xinyu No.2 Power Generation Co Ltd [100%][1] | Datang International Power Generation Co Ltd [65.0%]; Jiangxi Provincial Investment Group Corp [26.2%]; Jiangxi Provincial State-owned Enterprise Asset Management(Holding) Co Ltd [5.3%]; Jiangxi Financial Investment Group Co Ltd [3.5%] |
Project-level coal details
- Coal source(s): domestic
- Permit(s): Also permitted in 2020
Background
The two existing coal-fired units of Datang Xinyu-1 power station, totaling 440 MW, were brought online between 1995 and 1996. The plant is owned by China Datang.[5]
Proposed expansion
Datang is planning to build two additional coal-fired units at the site, the Datang Xinyu-2 power station, with a total planned capacity of 2,000 MW.[5]
It was permitted for construction in 2015.[6]
As of May 2018, Planet satellite photos from April 2018 show no construction.
The project appears in the Jiangxi Province Development Plan of the Railway Economic Belt (2019-2025), released in October 2019.[7]
Various news sources reported that construction began between December 2021 and April 2022, but it was unclear what the construction involved.[8]
By June 2022, construction was confirmed underway.[9]
Unit 1 achieved a number of operational milestones in 2024, including its first boiler ignition (May)[10], grid connection (August)[11], and successful completion of the 168-hour trial run (September)[12][13].
Unit 2 also progressed through its construction phases in 2024, completing milestones such as the boiler hydrostatic test (March)[14], turbine bucket (June)[15], and steam blow (September)[16]. It successfully connected to the grid in October 2024[17] and completed its 168-hour trial run, entering commercial operation later that month[18].
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 https://news.bjx.com.cn/html/20240319/1366880.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 2.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 "投运!国内首个煤电与光伏协同发展项目-北极星火力发电网". news.bjx.com.cn. 2024-09-14. Archived from the original on 2024-09-30. Retrieved 2024-09-16.
- ↑ 4.0 4.1 https://news.bjx.com.cn/html/20241025/1406939.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 "安源煤业与大唐国际签订合作协议确定大唐国际 新余发电厂异地扩建和新余简家煤矿两个项目",华夏经纬网, 2014-05-21
- ↑ "大唐新余二期扩建项目环境影响报告书拟批准公示," 11-15-2017
- ↑ "江西省人民政府关于印发江西省高铁经济带发展规划(2019-2025年)的通知," Jiangxi government, 2019-10-08
- ↑ Examples: https://news.bjx.com.cn/html/20220331/1214519.shtml, https://www.sohu.com/a/510881295_121090399, http://jx.people.com.cn/n2/2022/0425/c190181-35239420.html, http://www.smedianews.com/NewsContents_46822.html, http://www.andegcj.cn/NewsView.aspx?id=5206
- ↑ 大唐新余二期异地扩建2×100万千瓦工程正式开工, power.in-en, 2022-06-27
- ↑ "新余第二发电公司2X1000MW清洁高效煤电项目1号锅炉吹管首次点火一次成功". BJX. 2024-06-04. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "新余第二发电公司2×1000MW清洁高效煤电项目1号机组首次并网一次成功". BJX. 2024-08-06. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江西新余二期2×1000兆瓦异地扩建工程项目1号机组一次性通过168小时试运行". BJX. 2024-09-14. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江西新余二期2×1000兆瓦异地扩建工程项目1号机组一次性通过168小时试运行". WeChat. 2024-09-13. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江西大唐国际新余二期异地扩建2×1000MW工程2号锅炉水压试验一次成功". WeChat. 2024-03-12. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江西大唐国际新余二期异地扩建2×1000MW工程2号机组汽轮机扣盖顺利完成". WeChat. 2024-06-15. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江西大唐国际新余二期异地扩建2×1000MW工程2号机组锅炉点火吹管圆满完成". WeChat. 2024-09-11. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江西大唐国际新余二期异地扩建2×1000MW工程2号机组首次并网一次成功". BJX. 2024-10-12. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江西大唐国际新余二期异地扩建2×1000兆瓦工程2号机组一次性通过168小时试运,正式投入商业运营". WeChat. 2024-10-24. Retrieved 2026-07-17.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.