Diantou power station (陕煤集团黄陵矿业店头发电厂, 沮源发电2×1000MW发电项目) is an operating power station of at least 1320-megawatts (MW) in Diantou Town, Huangling, Yan'an, Shaanxi, China with multiple units, some of which are not currently operating. It is also known as 陕煤黄陵店头电厂三期2×1000MW机组扩建项目 (Phase III Unit 5 & 6), 陕煤黄陵店头电厂二期2×1000MW机组扩建项目 (Phase II Unit 3 & 4).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Diantou power station Diantou Town, Huangling, Yan'an, Shaanxi, China 35.657848, 109.050538 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4, Phase III Unit 5, Phase III Unit 6: 35.657848, 109.050538

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Phase I Unit 1 Operating coal: unknown[2] 660 ultra-supercritical 2023 False
Phase I Unit 2 Operating coal: unknown[2] 660 ultra-supercritical 2023 False
Phase II Unit 3 Construction[3] coal: unknown[2][4] 1000[4] ultra-supercritical[4] – False
Phase II Unit 4 Construction[3] coal: unknown[2][4] 1000[4] ultra-supercritical[4] – False
Phase III Unit 5 Permitted[1] coal: unknown[2][1] 1000[1] ultra-supercritical[1] – False
Phase III Unit 6 Permitted[1] coal: unknown[2][1] 1000[1] ultra-supercritical[1] – False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase I Unit 1 Shaanxi Huangling Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [31.0%]; Xi'an Jinxuan Investment Management Partnership LP [29.6%]; Jiangsu Yueda Group Co Ltd [23.6%]; Industrial and Commercial Bank of China Ltd [7.9%]; Xi'an Jingfa Holding (Group) Co Ltd [1.1%]; Shaanxi Finance Investment Management Co Ltd [1.1%]; China Construction Bank Corp [1.0%]; Shaanxi Yanchang Petroleum (Group) Co Ltd [0.9%]; unknown [0.8%]; Far East Horizon Ltd [0.8%]; Xi'an Urban Infrastructure Construction Investment Group Co Ltd [0.8%]; Yulin Investment Operation Group Co Ltd [0.8%]; Shaanxi International Trust Co Ltd [0.4%]; Chang'an Huitong Co Ltd [0.1%]
Phase I Unit 2 Shaanxi Huangling Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [31.0%]; Xi'an Jinxuan Investment Management Partnership LP [29.6%]; Jiangsu Yueda Group Co Ltd [23.6%]; Industrial and Commercial Bank of China Ltd [7.9%]; Xi'an Jingfa Holding (Group) Co Ltd [1.1%]; Shaanxi Finance Investment Management Co Ltd [1.1%]; China Construction Bank Corp [1.0%]; Shaanxi Yanchang Petroleum (Group) Co Ltd [0.9%]; unknown [0.8%]; Far East Horizon Ltd [0.8%]; Xi'an Urban Infrastructure Construction Investment Group Co Ltd [0.8%]; Yulin Investment Operation Group Co Ltd [0.8%]; Shaanxi International Trust Co Ltd [0.4%]; Chang'an Huitong Co Ltd [0.1%]
Phase II Unit 3 Shaanxi Huangling Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [31.0%]; Xi'an Jinxuan Investment Management Partnership LP [29.6%]; Jiangsu Yueda Group Co Ltd [23.6%]; Industrial and Commercial Bank of China Ltd [7.9%]; Xi'an Jingfa Holding (Group) Co Ltd [1.1%]; Shaanxi Finance Investment Management Co Ltd [1.1%]; China Construction Bank Corp [1.0%]; Shaanxi Yanchang Petroleum (Group) Co Ltd [0.9%]; unknown [0.8%]; Far East Horizon Ltd [0.8%]; Xi'an Urban Infrastructure Construction Investment Group Co Ltd [0.8%]; Yulin Investment Operation Group Co Ltd [0.8%]; Shaanxi International Trust Co Ltd [0.4%]; Chang'an Huitong Co Ltd [0.1%]
Phase II Unit 4 Shaanxi Huangling Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [31.0%]; Xi'an Jinxuan Investment Management Partnership LP [29.6%]; Jiangsu Yueda Group Co Ltd [23.6%]; Industrial and Commercial Bank of China Ltd [7.9%]; Xi'an Jingfa Holding (Group) Co Ltd [1.1%]; Shaanxi Finance Investment Management Co Ltd [1.1%]; China Construction Bank Corp [1.0%]; Shaanxi Yanchang Petroleum (Group) Co Ltd [0.9%]; unknown [0.8%]; Far East Horizon Ltd [0.8%]; Xi'an Urban Infrastructure Construction Investment Group Co Ltd [0.8%]; Yulin Investment Operation Group Co Ltd [0.8%]; Shaanxi International Trust Co Ltd [0.4%]; Chang'an Huitong Co Ltd [0.1%]
Phase III Unit 5 Shaanxi Huangling Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [31.0%]; Xi'an Jinxuan Investment Management Partnership LP [29.6%]; Jiangsu Yueda Group Co Ltd [23.6%]; Industrial and Commercial Bank of China Ltd [7.9%]; Xi'an Jingfa Holding (Group) Co Ltd [1.1%]; Shaanxi Finance Investment Management Co Ltd [1.1%]; China Construction Bank Corp [1.0%]; Shaanxi Yanchang Petroleum (Group) Co Ltd [0.9%]; unknown [0.8%]; Far East Horizon Ltd [0.8%]; Xi'an Urban Infrastructure Construction Investment Group Co Ltd [0.8%]; Yulin Investment Operation Group Co Ltd [0.8%]; Shaanxi International Trust Co Ltd [0.4%]; Chang'an Huitong Co Ltd [0.1%]
Phase III Unit 6 Shaanxi Huangling Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [31.0%]; Xi'an Jinxuan Investment Management Partnership LP [29.6%]; Jiangsu Yueda Group Co Ltd [23.6%]; Industrial and Commercial Bank of China Ltd [7.9%]; Xi'an Jingfa Holding (Group) Co Ltd [1.1%]; Shaanxi Finance Investment Management Co Ltd [1.1%]; China Construction Bank Corp [1.0%]; Shaanxi Yanchang Petroleum (Group) Co Ltd [0.9%]; unknown [0.8%]; Far East Horizon Ltd [0.8%]; Xi'an Urban Infrastructure Construction Investment Group Co Ltd [0.8%]; Yulin Investment Operation Group Co Ltd [0.8%]; Shaanxi International Trust Co Ltd [0.4%]; Chang'an Huitong Co Ltd [0.1%]

Project-level coal details

  • Coal source(s): domestic

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background on Project

Huangling Coal Mining applied for environmental clearance to build a 2 x 660 MW coal plant in Huangling.[5] The EIA of the power plant was approved by the Shaanxi provincial EPA in September 2016.[6]

There were no further developments on the project until March 2019, when sponsor Huangling Coal Mining again discussed plans for the project.[7] As of March 2020 Huangling Coal Mining had completed the pre-feasibility study and was seeking environmental clearance.[8] The project was permitted in March 2020, with operation planned for 2023.[9][10]

Construction began on unit 1 in May 2021.[11] Unit 2 also appeared to be underway.

By October 2022, a second 2 x 1,000 MW phase was permitted. The first phase was still under construction.[12]

In May 2023, it was reported that construction of the first phase was nearly complete.[13] By the end of the same month, Unit 1 had begun operation.[14] In June 2023, Unit 2 also successfully connected to the grid and began operating.[15][16][17]

Construction activities for Unit 3 progressed from early 2024 through 2026, including equipment procurement, the first concrete pour for the main plant (June 2024)[18], and various structural milestones such as cooling tower and chimney completions, and boiler header placement[19][20][21]. The boiler for Unit 1 was ignited in June 2026[22].

Construction milestones for Unit 4 included the completion of the cooling tower base (October 2024)[23], boiler steel frame placement (November 2024)[24], and boiler header placement (July 2025)[25]. The generator stator was placed in early 2026[26], and the turbine cylinder was bucked in June 2026[27].

The Phase III of the project received approval in December 2024[28][29]. Subsequent activities included tenders for feasibility and EIA reports in 2025[30] and a survey and design tender in July 2026[31][32].

Articles and Resources

References

  1. ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 "陕煤黄陵店头电厂三期2×1000MW机组项目获核准批复-北极星火力发电网". news.bjx.com.cn. 2024-12-20. Archived from the original on 2025-04-18. Retrieved 2025-01-07.
  2. ↑ 2.0 2.1 2.2 2.3 2.4 2.5 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  3. ↑ 3.0 3.1 https://news.bjx.com.cn/html/20240619/1384010.shtml. {{cite web}}: Missing or empty |title= (help)
  4. ↑ 4.0 4.1 4.2 4.3 4.4 4.5 "黄陵店头电厂二期2×1000MW机组扩建项目喜获核准批复-北极星火力发电网". news.bjx.com.cn. 2022-10-21. Archived from the original on 2024-01-25. Retrieved 2023-11-22.
  5. ↑ "关于“黄陵矿业集团有限责任公司店头电厂2×660MW工程”项目环境影响报告书全文公示信息," Huangling Coal Mining, 2016-5-23
  6. ↑ "黄陵矿业集团店头电厂2×660MW工程取得环评批复"Huangling Mining Group, 2016-09-13
  7. ↑ "黄陵矿业公司2019年基本建设工作都有哪些新要求发布时间," Huangling Coal Mining, 2019-03-29
  8. ↑ "陕北—湖北特高压通道配套煤电规划获国家能源局批复,预计配置新能源项目6GW," SolarBe, 2020-03-08
  9. ↑ "陕北至湖北特高压配套4个大型火电项目已获核准 2个项目计划今年开工," 北极星电力网新闻中心, 2020/3/13
  10. ↑ "陕煤黄陵店头电厂2×660MW工程项目预计2022年底投产," china5e, 2021-08-26
  11. ↑ "2×660MW!陕西省一大型火电项目开工," Sohu, 2021-05-18
  12. ↑ "黄陵店头电厂二期2×1000MW机组扩建项目喜获核准批复," BJX, 2022-10-21
  13. ↑ 陕煤集团:黄陵矿业2×660MW电厂项目进入冲刺阶段 , Sohu News, 2023-05-12
  14. ↑ 陕西黄陵发电公司2×660兆瓦电厂项目1号机组投产, BJX, May 29, 2023
  15. ↑ 陕西黄陵2×660MW电厂项目2号机组首次并网一次成功, BJX, 2023-06-15
  16. ↑ 黄陵矿业2×660MW电厂项目实现“双机双投”, BJX, 2023-06-28
  17. ↑ 【项目】火电|2x1000MW!浙能嘉兴四期扩建9号机组EPC总承包开标/2×660MW!陕煤黄陵矿业电厂实现“双机双投”, MP Weixin, 2023-06-29
  18. ↑ "陕煤黄陵店头电厂二期2×1000MW机组扩建项目举行主厂房第一罐混凝土浇筑仪式". BJX. 2024-06-19. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  19. ↑ "陕煤黄陵店头2×1000MW发电项目脱硫系统1号吸收塔顺利到顶". WeChat. 2025-03-24. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  20. ↑ "黄陵矿业公司店头电厂二期扩建工程烟筒顺利到顶". WeChat. 2025-05-05. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  21. ↑ "沮源发电公司2×1000MW发电项目1号机组锅炉首根大板梁吊装就位". WeChat. 2025-06-03. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  22. ↑ "黄陵矿业2×1000MW项目1号机组1号锅炉点火一次成功". BJX. 2026-06-30. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  23. ↑ "2×1000MW发电项目#2间冷塔环基最后一罐混凝土浇筑完成". WeChat. 2024-10-04. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  24. ↑ "陕煤黄陵店头电厂2×1000MW发电项目#2机组锅炉首根钢架吊装就位". WeChat. 2024-11-15. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  25. ↑ "黄陵店头电厂二期2×1000MW机组扩建项目2号锅炉大板梁顺利完成吊装". WeChat. 2025-07-23. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  26. ↑ "陕煤黄陵店头电厂二期2×1000MW机组扩建工程项目2#机组汽轮发电机定子顺利吊装就位". WeChat. 2026-12-30. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  27. ↑ "黄陵项目#2机组汽轮机扣盖作业一次成功". WeChat. 2026-06-27. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  28. ↑ "陕煤黄陵店头电厂三期2×1000MW机组项目获得核准批复". WeChat. 2024-12-17. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  29. ↑ "陕煤黄陵店头电厂三期2×1000MW机组项目获得核准批复". BJX. 2024-12-20. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  30. ↑ "陕煤黄陵店头电厂三期2×1000MW机组项目可研报告、环评报告编制服务招标". BJX. 2025-06-30. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  31. ↑ "陕煤黄陵店头电厂三期2×1000MW机组项目勘察设计招标公告". WeChat. 2026-07-14. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)
  32. ↑ "陕煤黄陵店头电厂三期2×1000MW机组项目勘察设计招标公告". BJX. 2026-07-14. Retrieved 2026-07-17.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.