Kirazlıdere power complex

From Global Energy Monitor

Kirazlıdere power complex (also known as the Filiz Kirazlidere Power Generation) is a proposed 2-unit, 1,600-megawatt (MW) (2 x 800MW) coal-fired power complex proposed for Çanakkale province, Turkey.[1]

Location

The satellite photo below shows the approximate plant's site, which is near Güreci village, Lapseki district, Çanakkale province.

Loading map...

Background on Plant

Kirazlıdere power complex is owned by Filiz Enerji which is now a subsidiary of Yıldırım Group.[2] Its permitting and company partnership process followed a similar pathway as Karaburun power station proposed for Çanakkale province by Sarıkaya Enerji. Both companies became subsidiaries of Yıldırım Group in 2013.[3] There are also some references that both Sarıkaya Energy and Filiz Energy companies used to be owned by Doğtaş, a subsidiary of Doğanlar Holding, before 2013.[4][5] Both of their environmental permission processes were started before 2013, as there used to be some references that Kirazlıdere power complex received the generation license for the 1st unit in 2010[6] and for the 2nd unit in 2012,[7] but these licenses are not currently accessible (December 2019 update). The information below is based on the latest accessible references and updated capacities.

Environmental permission processes for two units of Kirazlıdere power complex started individually in 2012; for the first unit, the EIA report was submitted on 14th September 2012,[8] and for the second unit an EIA application file (a pre-EIA report file) was submitted on 28th September 2012.[9] "EIA positive decisions" were given to the first unit (600MW) on 14th February 2013,[10] and to the second unit (660MW) on 14th June 2013.[10] A generation license was given to the first unit on 7th March 2013,[11] and a pre-generation license was given to the second unit on 3rd March 2014.[12] In 2015, EMRA combined individual generation licenses for both units and announced it as 1,260 MW (600MW + 660MW).[1] EIA positive decisions for the first unit were cancelled on December 2014 after legal cases.[13] New EIA reports for the first and the second units received positive decisions individually on 5th May 2015.[1]

At the end of 2015, after COP21 in Paris, the company decided to change the technology from ultra-critical to ultra-supercritical to meet the international finance and credit requirements of E.C.A. - Export Credit Agency that resulted in the capacity increase from 1,260 MW to 1,600 MW (2 units x 800MW).[1] As this capacity increase requires the revision of filtration systems, fill-area and cooling water, the new EIA process started in 2016.[1] The permitting process was paused for 2 months in April 2017 after the board of inspection and survey meeting as the company was requested to complete the missing parts in the air pollution modeling.[14] On 18th August 2017, another board of inspection and survey meeting was held, where many NGOs objected on health grounds and claimed that emissions from the plant would exceed new EU limits.[15] Legal cases against the new EIA report were dismissed, on 3rd October 2017 the final EIA report for unit 1 and unit 2 combined, with 1,600 MW total capacity, was accepted.[16] However, the generation license is valid for 1,260 MW.[11]

Environmental Impact

Environment and health groups claimed that emissions from the plant would exceed new EU limits[17] and called for a cumulative air pollution assessment.[18]

Coal

Coal for the plant will be provided by YIlliak A.Ş., a Yıldırım Group company, from the YCCX coal mine company in Colombia. It will be shipped with a Newcastlemax ship capable of carrying 200,000 tons of freight at Yıldırım Shipping Inc., a Yıldırım Group company.[19]

Project Details

  • Sponsor: Filiz Enerji (Filiz Kirazlıdere Enerji Üretim A.Ş.)
  • Parent company: Yıldırım Group
  • Location: Güreci village, Lapseki district, Çanakkale province, Turkey
  • Coordinates: 40.38227, 26.99455 (exact)
  • Status: Permitted
  • Detailed status:
  • Gross capacity: 1600 MW (2 x 800 MW)[1]
  • Type: Ultra-supercritical[1]
  • Projected in service: 2021
  • Coal source: Columbia[19]
  • Source of financing:

Articles and resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 Kirazlıdere 2016 EIA report, Ministry of Environment and Urbanism online EIA database, July 2016.
  2. HAKKIMIZDA, Filiz Enerji website, accessed Feb. 2018.
  3. Tarihçe, Yıldırım Holding website, accessed Dec. 2019.
  4. Doğtaş, Çanakkale'de iki ithal kömür santrali kuracak, Enerji Günlüğü, July 3, 2013.
  5. Sektör:Enerji, Çınar Mühendislik website, accessed Dec. 2019.
  6. Detaylar: Kirazlıdere Termik Santralı, EPDK website, accessed Apr. 2014.
  7. Detaylar: Kirazlıdere-2 Termik Santralı, EPDK website, accessed Apr. 2014.
  8. Çed Duyurusu, Çanakkale Provincial Directorate of Environment and Urbanism, Sep. 14, 2012.
  9. Çed Süreci Başlama Duyurusu, Çanakkale Provincial Directorate of Environment and Urbanism, Sep. 28, 2012.
  10. 10.0 10.1 Lisans ve İzinler, Filiz Enerji, accessed December.
  11. 11.0 11.1 Kirazlidere Generation Licence: EÜ/4301-5/02545, EMRA Licence website, accessed December 2019.
  12. Kirazlidere-2 Pre-Generation Licence:03.04.2014, EMRA Pre-Licence website, accessed December 2019.
  13. Kirazlıdere Termik Santrali Entegre Projesi “ÇED Olumlu Kararı” İptal Edildi Çanakkaleİçinde, Dec.1, 2014
  14. Kirazlıdere Termik Santrali durduruldu, Aydınlık, April 28, 2017.
  15. 17 sivil toplum kuruluşu itiraz etti: “Kirazlıdere Termik Santrali ölüm saçacak”, Sözcü, Aug. 18, 2017.
  16. Türkiye'de İklim Koruma Davaları-2016, Ekoloji Kollektifi, March 2017.
  17. Kirazlidere IDK Dilekçesi, Right to Clean Air Platform-Turkey, Aug. 18, 2017
  18. Yıldırım Holding'e "Çanakkale'nin Havasını Bozma" Çağrısı, Bianet, May. 24, 2017.
  19. 19.0 19.1 TEMİZ KÖMÜRLÜ SÜPER VERİMLİ VE ÇEVRECİ SANTRAL PROJESİ, Filiz Enerji website, accessed June 2018.

Related SourceWatch articles

External resources

NO2 and SO2 emissions (Turkish)