Fujian Putian Shimen'ao Cogen power station (福建莆田市石门澳产业园热电) is an operating power station of at least 160-megawatts (MW) in Shimen'ao, Xiuyu, Putian, Fujian, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Fujian Putian Shimen'ao Cogen power station Shimen'ao, Xiuyu, Putian, Fujian, China 25.224679, 119.024749 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Phase II Unit 3, Phase II Unit 4: 25.224679, 119.024749

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Emergency/Backup
Phase II Unit 3 Operating[2] coal: unknown[3][1] 80[1] subcritical[1] yes[1] 2023[2] False
Phase II Unit 4 Operating[2] coal: unknown[3][1] 80[1] subcritical[1] yes[1] 2024[2] False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase II Unit 3 Fujian EVERSUN Technology Co Ltd [100%][1] Putian City state-owned Assets Investment Co Ltd [32.7%]; Wing Wing Group Ltd [22.0%]; Fujian Pingtan Yonghong Investment Co Ltd [15.3%]; China Development Bank Corp [11.1%]; Fujian Local Industry Equity Investment Fund Partnership LP [10.0%]; unknown [6.5%]; Xiamen Fuyuanda Chemical Co Ltd [2.5%]
Phase II Unit 4 Fujian EVERSUN Technology Co Ltd [100%][1] Putian City state-owned Assets Investment Co Ltd [32.7%]; Wing Wing Group Ltd [22.0%]; Fujian Pingtan Yonghong Investment Co Ltd [15.3%]; China Development Bank Corp [11.1%]; Fujian Local Industry Equity Investment Fund Partnership LP [10.0%]; unknown [6.5%]; Xiamen Fuyuanda Chemical Co Ltd [2.5%]

Project-level coal details

  • Coal source(s): domestic/imported

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

The "Putian Shimen'ao Industrial Park Cogeneration Phase II Project" was proposed in Shimenao Industrial Park, Xiuyu District, Putian City, Fujian Province. The project was projected to include a new 3×910t/ h High temperature and high pressure circulating fluidized bed boiler (dual use and one backup) and 2 x 80 MW "back pressure steam turbine generator set."[4]

By October 2022, the construction was ongoing[5] and appeared nearly complete based on Planet satellite imagery. It appeared there were three existing boiler buildings, so Phase I may have three power generating units. Details were unknown.

In June 2023, it was reported that the units of the second phase of the power project were connected to the power grid.[6] At the time of report, one 80 MW unit had begun commercial operation.[6]

Phase II Unit 3 completed their 96-hour trial run in July 2023[7]. The main transformer for Unit 4 was successfully energized in January 2024[8].

Articles and Resources

References

  1. 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 https://news.bjx.com.cn/html/20220315/1210440.shtml. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 https://pt.fjsen.com/xw/2024-01/11/content_31498589.htm. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  4. 福建莆田市石门澳产业园热电联产二期项目环境影响报告书的批复, BJX, 2022-03-15
  5. "秀屿:节日鏖战不休 热电联产二期项目全力推进中," PTBTV, 2022-10-07
  6. 6.0 6.1 莆田市石门澳产业园热电联产二期项目并网发电 BJX, 2023-06-08
  7. "莆田市石门澳产业园热电联产二期项目机组并网发电". BJX. 2023-06-08. Retrieved 2026-07-20.{{cite web}}: CS1 maint: url-status (link)
  8. "石门澳热电厂4号主变启动送电工作圆满完成". 福建日报. 2024-01-11. Retrieved 2026-07-20.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.