Fushun Zhongji power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Fushun Zhongji power station (抚顺矿业中机热电) is an operating power station of at least 600-megawatts (MW) in Yanwu Street, Wanghua, Fushun, Liaoning, China. It is also known as 抚顺热电新建项目(New Fushun Cogen Power Station).
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Fushun Zhongji power station | Yanwu Street, Wanghua, Fushun, Liaoning, China | 41.819307, 123.8300555 (exact) |
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 41.819307, 123.8300555
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Unit 1 | Operating | coal: waste coal[1] | 300 | subcritical | yes | 2017 | False |
| Unit 2 | Operating | coal: waste coal[1] | 300 | subcritical | yes | 2017 | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Fushun Mining Zhongji Thermal Power Co Ltd [100%] | Liaoning Energy Industry Holding Group Co Ltd [40.8%]; China National Machinery Industry Corp [11.9%]; J-Yuan Trust Co Ltd [8.1%]; ZHEJIN Guoneng (Tianjin) New Energy Technology Partnership LP [7.1%]; Shanghai Electric Group Co Ltd [6.6%]; Jiangsu Chen YI Xuan Trading Co Ltd [5.8%]; Fushun MINING Group Co Ltd [5.1%]; Liaoning Huida Enterprise Management Co Ltd [5.1%]; unknown [4.2%]; Shanghai Changtai Electrical Co Ltd [3.9%]; Jiangsu Haichen Energy Co Ltd [0.9%]; Bank of Communications Co Ltd [0.5%] |
| Unit 2 | Fushun Mining Zhongji Thermal Power Co Ltd [100%] | Liaoning Energy Industry Holding Group Co Ltd [40.8%]; China National Machinery Industry Corp [11.9%]; J-Yuan Trust Co Ltd [8.1%]; ZHEJIN Guoneng (Tianjin) New Energy Technology Partnership LP [7.1%]; Shanghai Electric Group Co Ltd [6.6%]; Jiangsu Chen YI Xuan Trading Co Ltd [5.8%]; Fushun MINING Group Co Ltd [5.1%]; Liaoning Huida Enterprise Management Co Ltd [5.1%]; unknown [4.2%]; Shanghai Changtai Electrical Co Ltd [3.9%]; Jiangsu Haichen Energy Co Ltd [0.9%]; Bank of Communications Co Ltd [0.5%] |
Project-level coal details
- Coal source(s): domestic
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background on Project
Fushun Mining Group and Sinomach are sponsors of a two-unit waste coal-fired power plant with a total planned capacity of 600 MW in Liaoning Province. The plant is scheduled to be completed in 2015.[2]
The plant received environmental clearance at the end of 2014.[3] As of 2015 the project is still seeking a NDRC permit for construction.[4]
Unit 1 was commissioned in March 2017.[5][6] Unit 2 was commissioned in July 2017.[7]
Although the plant is operating, there is no record that the plant received the necessary permits for construction.
Articles and Resources
References
- ↑ 1.0 1.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "抚顺矿业中机热电有限责任公司", 抚顺矿业中机热电有限责任公司网站
- ↑ "抚辽宁抚顺热电厂“上大压小”新建项目环境影响报告书已获得国家环保部批复," 2014-12-31
- ↑ "抚顺市重大项目情况汇总," Fushun Development and Reform Commission, 2015-7-17
- ↑ "辽宁抚顺热电厂2台30万千瓦“上大压小”新建工程1号机组投产," 2017-3-16
- ↑ "抚热电2×300兆瓦工程2号机组一次并网成功," 2017-4-12
- ↑ "公司承建的抚顺热电厂2号机组顺利通过168小时试运行," CEEC, 2017-07-28