GasPort FSRU, also known as Port Qasim GasPort, PGPC terminal, and Pakistan FSRU 2, is an operating LNG import terminal in Pakistan.

Location

Table 1: Location details

Name Location Coordinates (WGS 84)
GasPort FSRU Port Qasim, Karachi, Sindh, Pakistan 24.7749916, 67.288333 (exact)

The map below shows the exact location of the terminal:

Loading map...

Project Details

Table 2: Infrastructure details

mtpa = million tonnes per year
Name Facility type Status Capacity Total terminal capacity Offshore Associated infrastructure
GasPort FSRU import operating 5 mtpa[1] 5.0 mtpa True –

Table 3: Cost

Name Facility type Cost Total known terminal costs
GasPort FSRU import US$500,000,000[2] US$500,000,000

Financing

No financing data available.

Table 4: Project timeline

FID = Final Investment Decision, used by some developers to indicate a project will move forward
Name Facility type Status Proposal year FID year Construction year Operating year Inactive year
GasPort FSRU import operating – – 2016[3] 2017 –

Ownership

Table 5: Ownership

Name Facility type Status Owners Parent companies Operator
GasPort FSRU import operating Pakistan GasPort Consortium Ltd [100%][4] Pakistan Gasport Ltd [100.0%] Pakistan GasPort Consortium[4]

Table 6: Vessel ownership

Name Facility type Status Vessel Vessel owners Vessel operator
GasPort FSRU import operating BW Integrity[4] Mitsui &; BW Group[5][5] BW Group[4]

Background

GasPort FSRU is an LNG import terminal in Sindh, Pakistan, originally planned to become operational in 2017.[6]

A consortium comprising Xinjiang Petroleum Engineering Company Limited (XPE), CCCC Third Harbor Consultants Company Limited and CCCC Third Harbor Engineering Company Limited is providing Engineering, Procurement, Supply, Dredging and Construction services to the project.[7]

The terminal began commercial operations in November 2017.[8]

Since August 2020 private players are permitted to import LNG to the country, and private sector companies in Pakistan are allowed to use the underutilized PGPC Port Qasim GasPort regasification terminal. [9]

In May 2024, a senior representative from the Special Investment Facilitation Council (SIFC) visited the terminal. The tour also included a visit to the site selected for the proposed GasPort FSRU 2 terminal.[10]

Articles and Resources

Additional data

To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.

References

  1. ↑ (PDF) https://giignl.org/wp-content/uploads/2024/06/GIIGNL-2024-Annual-Report-1.pdf. {{cite web}}: Missing or empty |title= (help)
  2. ↑ https://www.thenews.com.pk/print/1190728-sifc-representative-visits-pgpl-lng-terminal-at-port-qasim. {{cite web}}: Missing or empty |title= (help)
  3. ↑ https://splash247.com/bw-secures-fsru-contract-pakistan-gasport/. {{cite web}}: Missing or empty |title= (help)
  4. ↑ 4.0 4.1 4.2 4.3 (PDF) https://giignl.org/wp-content/uploads/2022/05/GIIGNL2022_Annual_Report_May5.pdf. {{cite web}}: Missing or empty |title= (help)
  5. ↑ 5.0 5.1 https://bw-group.com/our-businesses/bw-lng/projects/bw-integrity-in-pakistan/. {{cite web}}: Missing or empty |title= (help)
  6. ↑ "Procurement process," PGP Consortium Limited, 2016
  7. ↑ "About Us," Pakistan Gas Port, accessed August 2017
  8. ↑ Pakistan's second LNG import terminal to restart on Dec. 8 - company, Reuters, Dec. 7, 2017