Gasification of Eastern Republika Srpska
From Global Energy Monitor
Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Related categories: |
The Gasification of Eastern Republika Srpska is gas pipeline under construction in Bosnia and Herzegovina.[1]
Location
The pipeline runs from Šekovići to Milići.[2]
Project details
Main Line
- Operator: Sarajevo Gas[3]
- Owner:
- Parent company:
- Capacity:
- Length: 48.0 km[4]
- Diameter:
- Status: Construction[1]
- StartYear1: 2026[2]
- Cost: KM 74 million[1]
- Financing: Government of Republika Srpska[4]
- Associated infrastructure: TurkStream Gas Pipeline
Background
The pipeline will be operated by Sarajevo Gas and is being built with the backing the the Srpska government. Gas in Srpska is currently sourced from Russia via Serbia and the TurkStream pipeline.[2]
Articles and resources
References
{reflist}
- ↑ 1.0 1.1 1.2 "The works on construction of the main gas pipeline officially commence – the goal is to have full gasification of the Republic of Srpska". Government of Republic of Srpska. Retrieved 2025-09-03.
- ↑ 2.0 2.1 2.2 "Bosnia and Herzegovina: Gasification of eastern Republic of Srpska advances with pipeline construction on track". Serbia Energy. Retrieved 2025-09-03.
- ↑ "Gasification of Eastern Srpska Proceeding As Planned". Srpska National. 2025-08-25. Retrieved 2025-09-03.
- ↑ 4.0 4.1 "The works on construction of the main gas pipeline officially commence – the goal is to have full gasification of the Republic of Srpska". Government of Republic of Srpska. Retrieved 2025-09-03.