Gheraesti-Siret Gas Pipeline is a proposed natural gas pipeline.[1]

Location

The pipeline would run from Gheraesti to Siret in Romania.[1][2]

Loading map...

Project Details

  • Operator: SNTGN Transgaz SA[1]
  • Parent Company:
  • Proposed capacity:
  • Length: 146 km / 90.72 mi[1]
  • Diameter: 700 mm / 28 inches[3]
  • Status: Proposed
  • Start Year: 2025

Background

The pipeline is listed as a part of the European Network of Transmission System Operators for Gas (ENTSOG) 2020 Ten Year Network Development Plan as a part of the "interconnection between the RO and the UA gas transmission systems" (TRA-N-596) which is expected to commissioned in 2025 [1]

Articles and resources

References

  1. 1.0 1.1 1.2 1.3 1.4 European Network of Transmission System Operators for Gas (November 25, 2020). "TYNDP 2020 Annex A.2 – Project Tables". ENTSOG. Retrieved December 2, 2020.
  2. European Network of Transmission System Operators for Gas (October 2020). "TYNDP Transmission Map" (PDF). ENTSOG. Retrieved December 3, 2020.
  3. European Network of Transmission System Operators for Gas (November 25, 2020). "TYNDP 2020 Annex A.2 – Project Tables". ENTSOG. Retrieved December 2, 2020.

Related GEM.wiki articles

External resources

External articles