Baltic Pipe Project

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Baltic Pipe Project is a gas pipeline running from Denmark to Poland. It transports gas from Norway to Poland, crossing via Danish, Swedish, and Polish economic zones.[1]

Location

The project consists of five components:[2]

  • A new offshore gas pipeline, 105-110 kilometers long, from Norway’s pipeline Europipe II Gas Pipeline in the North Sea to a receiving terminal located North of Varde in Denmark
  • Expansion of the Danish transmission system with a new gas pipeline, approximately 210-230 kilometers long, which will run between Egtved in Jutland and the South-eastern part of Zealand, with a compressor station in the South-eastern part of Zealand
  • A new offshore gas pipeline, 260-310 kilometers long, in the Baltic Sea between Denmark and Poland.[3][4] The pipeline will pass through Danish and Polish maritime areas, as well as the Swedish exclusive economic zone.[1]
  • An expansion of the Polish gas transmission system onshore tying into the Goleniów–Lwówek Gas Pipeline.[5]


Loading map...

Project details

Main Segment

  • Operators: Energinet and GAZ-SYSTEM S.A.[6]
  • Owners: Energinet (50%) and GAZ-SYSTEM S.A. (50%)[6]
  • Owners: Energinet (50%) and GAZ-SYSTEM S.A. (50%)[6]
  • Proposed capacity: 10 billion cubic meters per year[7]
  • Length: 575-650 kilometers (average of estimates 612.5)[8]
  • Cost: €1.6 billion – €2.1 billion (US$1.79 billion – US$2.35 billion)[9]
  • Financing: Corporate financing from a consortium of commercial banks[10] and up to €267 million in European Union grants via the Connecting Europe Facility[11]
  • Status: Operating[12][13]
  • Start year: 2022[14][15][16][17]
  • Identifiers:
    • ENTSOG 2022 TYNDP: TRA-F-780 (Baltic Pipe project – onshore section in Denmark), TRA-A-1173 (Poland - Denmark interconnection (Baltic Pipe) - onshore section in Poland), TRA-A-271 (Poland - Denmark interconnection (Baltic Pipe) - offshore section) and TRA-F-394 (Norwegian tie-in to Danish upstream system)[18]
    • EU PCI: 8.3.2[18]
    • SciGrid_gas IGG: INET_PL_9180, INET_PL_9181, INET_PL_9182, INET_PL_9183, INET_PL_9184, INET_PL_9185, INET_PL_9186, INET_PL_9187[4]

Goleniów–Lwówek Gas Pipeline (Stage 1)

Goleniów–Lwówek Gas Pipeline (Stage 2)

Background

Main Segment

The Baltic Pipe is a proposed 650 kilometer (maximum) pipeline being developed by Energinet and Gaz-System with a 120km-long offshore natural gas pipeline portion that will be built between Rødvig, Denmark, and Niechorze, Poland. The final investment decision is scheduled to be reached in 2018, while the project's commission date is October 2022.[25] The Baltic Pipe Project will allow transport of gas from Norway to the Danish and Polish markets, as well as to end-users in neighboring countries. At the same time, the Baltic Pipe Project will enable the supply of gas from Poland to Danish and Swedish markets.[26]

In August of 2019, Poland's gas grid operator Gaz-System agreed to buy a set of compressor units for 550 million zlotys ($141 million) from U.S. company Solar Turbines for its planned link to Norway’s gas fields. Poland sees the Baltic Pipe as a way to diversify its gas supply, most of which is currently imported from Russia under a long-term contract with Gazprom that expires in 2022. The Baltic Pipe, as well as increased supplies of liquefied natural gas (LNG) via a Baltic Sea terminal at Świnoujście Polskie LNG Terminal, is designed to help Poland replace Russian gas deliveries.[27] The project also provides Poland with an opportunity to become a central European gas hub.[11]

Part of the project was approved as a Project of Common Interest (PCI) by the European Commission, meaning it will be eligible to receive public funding. The PCI portion of the project will be a total of 204 kilometers (200 onshore, 4 offshore), and 10 billion cubic meters/year.[28]

In May 2020, the project achieved a complete set of construction permits following Sweden's approval for the pipeline to pass through 85 kilometres of the Swedish exclusive economic zone of the Baltic Sea. However, the planned October 2022 construction completion date may be delayed as the Baltic Pipe crosses both the Nord Stream 1 and 2 pipelines in Danish waters and requires the approval of the operators of both Nord Stream pipelines to do so. Approval from the Nord Stream 1 consortium is expected because it is owned by a consortium of Gazprom and EU-based companies, but approval from the Nord Stream 2 project may be more complicated as it is wholly-Gazprom operated.[29]

In autumn 2020, construction work started to prepare the pipe landfalls in both Poland and Denmark. By the end of November it was reported that short sections of the pipeline had been laid on the east and west coasts of the Jutland peninsula.[30]

In June 2021, a temporary halt was called on pipeline construction work in Denmark following the rescinding of an environmental permit by a Danish public appeals committee due to concerns over the pipeline's impact on protected mice and bat species. Several weeks later, Energinet said that construction work would resume on parts of the project but that construction at two locations in Denmark would be suspended until 2022, pending the issuance of a new environmental permit. As a result, Energinet said that it expected the overall project completion to be delayed by three months.[31] Energinet estimated this delay will cost €80 million.[32]

As of August 2021, the Three Seas Initiative expected the project to be commissioned in October 2022.[17]

In November 2021, the final sea bed section of the pipeline offshore of Poland was completed.[33]

In March 2022, Energinet announced that construction work on the Danish section of the pipeline was restarting after it had received a new environmental permit for the works. The company said that it still expected the pipeline to be partially operational from 1 October 1, 2022, and operating at full capacity from January 1, 2023.[34]

Goleniów-Lwówek Gas Pipeline

The Goleniów–Lwówek segment of the pipeline will enable the off-take of an increased amount of gas from the Baltic Pipe offshore gas pipeline and the LNG Terminal in Świnoujście. According to Gaz-System as of January 2021, a complete set of construction permits for the project was obtained in February 2020, and work is underway related to the removal of trees and shrubs in private forests, dehumidification of the construction and assembly belt, the transport of cold-formed pipes and arches and the supply of basic building materials. [35]

Construction was to be undertaken in two stages: Stage 1 would be from Goleniów to Ciecierzyce, and Stage 2 would be from Ciecierzyce to Lwówek.[36]

In July 2021, Gaz System announced that "intensive works on the construction of Goleniów–Lwówek gas pipeline" had begun. It stated that "all pipes" included in Stage 1 "have already been strung and the entire route has been prepared for installation works. Already 75 km of pipes have been welded and 43 km of the pipeline has been laid in the trench." For Stage 2, the site had been prepared and "over 59% of pipes (total length of approx. 40 km) have been strung."[37]

Commissioning

On 27 September 2022, the pipeline was opened, though not at full capacity.[12][13] On 30 November 2022, Energinet, the Danish partner in the project, announced that the target transmission capacity of up to 10 bcm/y had been achieved following the completion of construction work in Denmark.[38]

Financing

In June 2020, the Financial Times reported that the project promoters were confident of securing financing for the project, with Gaz-System in talks with about 15 banks over the financing of its investment programme, which includes its share of the Baltic Pipe costs. Overall funding from European Union grants could rise to up to €267 million.[39] In April 2019 Poland received a €214.9 million grant from the EU's Connecting Europe Facility (CEF) to help build its portion of the pipeline.[40] The project was earlier awarded three CEF grants for a feasibility study and preparatory works: €387,374 in 2015[41]; €33,149,601 in 2017[42]; €18,300,000 in 2018.[43]

The international law firm Norton Rose Fulbright disclosed in July 2020 that it had advised a consortium of ten banks on the US$ 1.4 billion financing for Gaz-System which will be used as a stable source of funding for projects by the company to implement its 2020-2025 investment strategy, including the Baltic Pipe and the expansion of the Świnoujście Polskie LNG Terminal. The banks involved in the financing are: Alior Bank S.A., Bank Gospodarstwa Krajowego, Bank Millennium S.A., Bank of China (Luxembourg) S.A. Oddział w Polsce, BNP Paribas Bank Polska S.A., CaixaBank, S.A. (Spółka Akcyjna) Oddzial w Polsce, China Construction Bank (Europe) S.A. (Spółka Akcyjna) Oddział w Polsce, Credit Agricole Bank Polska S.A., mBank S.A. and Powszechna Kasa Oszczędności Bank Polski S.A.[10]

Technical Details

The Baltic Pipeline will include the following:[16]

  • A 105-110 kilometer long, new offshore gas pipeline from Norway’s Europipe II Gas Pipeline in the North Sea to a receiving terminal located North of Varde in Denmark.[8]
  • Expansion of the Danish transmission system with a new gas pipeline, approximately 210-230 kilometers long, which will run between Egtved in Jutland and the South-eastern part of Zealand.[8]
  • A compressor station in the South-eastern part of Zealand.[8]
  • A 260-310 kilometer long offshore gas pipeline in the Baltic Sea between Denmark and Poland.[8]
  • An onshore section in Poland[2]
    • including an approximately 82 km gas pipeline connecting the Baltic Pipe with the Goleniów-Lwówek Gas Pipeline[44]

Contractors

In July of 2019, DNV GL won a major contract to provide independent verification services for the Danish transmission system operator Energinet’s section of the Baltic Pipe project, offshore Denmark. DNV GL’s contract includes independent verification and submarine pipeline certification to the DNV GL certification regime DNVGL-SE-0475. The acceptance criteria are the Danish Continental Shelf Law, DNVGL-ST-F101 and the suite of underlying DNV GL standards and recommended practices. The work will take place during the engineering, procurement, construction, installation, hook-up and commissioning phases of pipeline development over the next three years.[45]

In August of 2019, Energinet contracted Corinth Pipeworks to supply offshore linepipe for the project. Corinth Pipeworks will manufacture 114 km (71 mi) of 32-inch and 36-inch SAWL steel pipes (43,000 tons in total) with a three-layer polyethylene anti-corrosion coating, epoxy lining for flow assurance, and concrete weight coating with sacrificial anodes and bends. Deliveries are due to start in late-2019 and continue through 2021, when the pipes will be laid through Danish waters.[46]

In April 2020, Gaz-System signed a contract with Italian construction company Saipem to lay the offshore pipeline, with work expected to start in the second half of 2020.[29]

Opposition

In July 2020, activists from the Baltic Pipe Nej Tak campaign occupied one of the project's pre-construction sites. Baltic Pipe Nej Tak (‘Baltic Pipe No Thanks!’) is a campaign platform for the wide movement against new fossil infrastructure, and is specifically focused on opposing construction of the Baltic Pipe gas pipeline.[47] The campaign post updates on their actions to their Facebook page.[48]

Protesters in Copenhagen march against the proposed Baltic Pipe in Jan. 2020[49]
Danish activists' protest against the proposed Baltic Pipe project, July 2020

Articles and resources

References

  1. 1.0 1.1 Baltic Pipe, Wikipedia, accessed March, 2018
  2. 2.0 2.1 "The Baltic Pipe Project consists of 5 components". Baltic Pipe Project. Retrieved August 24, 2021.{{cite web}}: CS1 maint: url-status (link)
  3. Baltic Pipe: Gas Pipeline, Connecting Denmark and Poland With Norway's Gas Fields, Energinet, accessed March 2018
  4. 4.0 4.1 Diettrich, Pluta, Medrjoubi (July 23, 2020). "The combined IGG gas transmission network data set". DLR Institute for Networked Energy Systems. {{cite journal}}: Cite journal requires |journal= (help)CS1 maint: multiple names: authors list (link)
  5. "Onshore Poland". www.baltic-pipe.eu. Retrieved 2021-08-24.{{cite web}}: CS1 maint: url-status (link)
  6. 6.0 6.1 6.2 "Baltic Pipe Gas Pipeline | Project | IJGlobal". ijglobal.com. Retrieved 2020-09-18.
  7. "BALTIC PIPE PROJECT" (PDF). baltic-pipe.eu. 2019. Retrieved March 23, 2021.{{cite web}}: CS1 maint: url-status (link)
  8. 8.0 8.1 8.2 8.3 8.4 Baltic Pipe: Gas Pipeline, Connecting Denmark and Poland With Norway's Gas Fields, Energinet, accessed March 2018
  9. Marek Grzegorczyk, As Baltic Pipe nears completion, Poland takes huge step towards energy diversification, Emerging Europe, Nov. 19, 2021
  10. 10.0 10.1 Norton Rose Fulbright advises a consortium of banks on financing for GAZ-SYSTEM, Poland’s designated natural gas transmission system operator, Norton Rose Fulbright press release, July 2020
  11. 11.0 11.1 James Shotter, Polish gas network close to fully financing Baltic Pipe to Norway, Financial Times, Jun. 9, 2020
  12. 12.0 12.1 Alisdair Sandford, Baltic Pipe: Norway-Poland gas pipeline opens in key move to cut dependency on Russia, Euronews, Sep. 27, 2022
  13. 13.0 13.1 13.2 13.3 "Launch of the Baltic Pipe". European Commission. Retrieved 2023-01-26.
  14. Shailaja A. Lakshmi, DNV GL Wins Baltic Pipe Project Marine Link, June 20, 2019
  15. Baltic Pipe Project (August 2020). "Baltic Pipe Project: Offshore gas pipeline – implementation stage" (PDF). Retrieved December 10, 2020.
  16. 16.0 16.1 Gaz-System (May 18, 2021). "Projekt Baltic Pipe: Nowe zrodlo dostaw gazu do Polski" (PDF). Gaz-System. Retrieved August 23, 2021.{{cite web}}: CS1 maint: url-status (link)
  17. 17.0 17.1 "Diversification of gas supply sources and integration of gas infrastructure in the Three Seas Region - Three Seas". projects.3seas.eu. Retrieved 2021-08-24.
  18. 18.0 18.1 European Network of Transmission System Operators for Gas (2020). "TYNDP - Annex A - Projects Tables RPJ007_NS_2020 - entsog". ENTSOG. Retrieved September 16, 2020.{{cite web}}: CS1 maint: url-status (link)
  19. "Goleniów-Lwówek gas pipeline". www.baltic-pipe.eu. Retrieved 2021-08-24.{{cite web}}: CS1 maint: url-status (link)
  20. "Goleniów-Lwówek gas pipeline". www.baltic-pipe.eu. Retrieved 2021-08-24.{{cite web}}: CS1 maint: url-status (link)
  21. 21.0 21.1 21.2 21.3 "Goleniów-Lwówek gas pipeline". www.baltic-pipe.eu. Retrieved 2021-08-24.{{cite web}}: CS1 maint: url-status (link)
  22. 22.0 22.1 Gaz-System (May 18, 2021). "Projekt Baltic Pipe: Nowe zrodlo dostaw gazu do Polski" (PDF). Gaz-System. Retrieved August 23, 2021.{{cite web}}: CS1 maint: url-status (link)
  23. "Goleniów-Lwówek gas pipeline". www.baltic-pipe.eu. Retrieved 2021-08-24.{{cite web}}: CS1 maint: url-status (link)
  24. "Goleniów-Lwówek gas pipeline". www.baltic-pipe.eu. Retrieved 2021-08-24.{{cite web}}: CS1 maint: url-status (link)
  25. Baltic Pipe Project, Hydrocarbons-Technology, accessed March, 2018
  26. Baltic Pipe Project, Baltic Pipe, accessed March 2018
  27. Poland's gas grid operator buys first equipment for Baltic Pipe Reuters, Aug. 14, 2019
  28. Reinforcement of Nybro — Poland/Denmark Interconnection European Commission, accessed Dec. 10, 2019
  29. 29.0 29.1 All Baltic Pipe gas link permits in place after Swedish approval, S&P Global, May 11, 2020
  30. Leszek Kadej, Baltic Pipe laid under the beach on the west coast of Denmark, wysokienapiecie.pl, Nov. 23, 2020
  31. Nikolaj Skydsgaard, Baltic Pipe gas link work resumes but faces 3-month delay, Reuters, Jun. 19, 2021
  32. "ENERGINET: Energinet estimates cost of Baltic Pipe delay at 80 million euro". www.baltic-pipe.eu. July 2, 2021. Retrieved 2021-08-23.{{cite web}}: CS1 maint: url-status (link)
  33. Marek Grzegorczyk, As Baltic Pipe nears completion, Poland takes huge step towards energy diversification, Emerging Europe, Nov. 19, 2021
  34. Denmark resumes construction of Norway-Poland gas link, EURACTIV, Mar. 11, 2022
  35. GOLENIÓW-LWÓWEK, Gaz-System, accessed August 2020
  36. "Goleniów-Lwówek gas pipeline". www.baltic-pipe.eu. Retrieved 2021-08-24.{{cite web}}: CS1 maint: url-status (link)
  37. GAZ-SYSTEM (June 14, 2021). "Intensive works on the construction of Goleniów-Lwówek gas pipeline". Baltic Pipe Project. Retrieved August 24, 2021.{{cite web}}: CS1 maint: url-status (link)
  38. Melisa Cavcic, ‘Huge day’ for Europe as Baltic Pipe goes full throttle, Offshore Energy, Dec. 1, 2022
  39. James Shotter, Polish gas network close to fully financing Baltic Pipe to Norway, Financial Times, Jun. 9, 2020
  40. Poland wins €215m EU grant for gas link to Norway, Euractiv, Apr. 15, 2019
  41. Feasibility Study regarding the PCI Poland - Denmark interconnection "Baltic Pipe" TRA-N-271..., European Commission, accessed Dec. 7, 2020
  42. Preparatory works for the Baltic Pipe Project up to obtainment of all necessary permission(s) in Poland and in Denmark, European Commission, accessed Dec. 7, 2020
  43. Reinforcement of the national gas transmission systems in Poland and Denmark for the Baltic Pipe Project, European Commission, accessed Dec. 7, 2020
  44. "Onshore Poland". www.baltic-pipe.eu. Retrieved 2021-08-24.{{cite web}}: CS1 maint: url-status (link)
  45. Shailaja A. Lakshmi, DNV GL Wins Baltic Pipe Project Marine Link, June 20, 2019
  46. Offshore Staff, Corinth to manufacture Danish section of Baltic Pipe Offshore, August 28, 2019
  47. [1] Baltic Pipe Nej Tak campaign website, accessed July 2020
  48. "Baltic Pipe NEJ TAK". www.facebook.com. Retrieved 2020-09-29.
  49. Arentsen, Ida Guldbæk (January 8, 2020). "Modstanden mod Baltic Pipe er nødvendig og retfærdig". Altinget. Retrieved August 11, 2020.

Related GEM.wiki articles

External resources

External articles