Growler to Lycium Oil Pipeline is an operating oil pipeline in Australia.[1]

Location

The pipeline runs from the Growler field in Queensland to the Lycium field in Queensland.[2]

Project Details

  • Owner: Senex Energy Limited (60%), Beach Energy Limited (40%)[3]
  • Capacity: 8000 barrels per day[4]
  • Length: 70 km[4]
  • Status: Operating[1]
  • Start year: 2012[1]
  • Cost: AUD$40 million[5]

Background

The pipeline is jointly owned by Senex (60%) and Beach Energy (40%).[1]

Articles and Resources

References

  1. ↑ 1.0 1.1 1.2 1.3 Cooper basin western flank pipelines on stream, archived from the original, PennEnergy, Dec. 28, 2012, archive accessed Aug. 15, 2021.
  2. ↑ "Growler to Lycium Pipeline to begin construction - The Australian Pipeliner". www.pipeliner.com.au. Retrieved 2026-03-06.
  3. ↑ Growler to Lycium Pipeline to Begin Construction, The Australian Pipeliner, Jan. 31, 2012, accessed Aug. 15, 2021.
  4. ↑ 4.0 4.1 Senex and Beach to construct an oil export flowline, Senex, Aug. 19, 2011, accessed Aug. 15, 2021.
  5. ↑ "Beach, Senex to build $40m oil pipeline". Australian Financial Review. 2011-08-19. Retrieved 2022-05-27.