Guangdong Xinhui Daze Gas Thermal power station (新会大泽2×50MW级燃气热电项目, 新会大泽工业园区热电联产项目) is a power station in Daze Town, Xinhui District, Jiangmen, Guangdong, China with multiple units of varying statuses, none of which are currently operating.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Guangdong Xinhui Daze Gas Thermal power station | Daze Town, Xinhui District, Jiangmen, Guangdong, China | 22.538499256116268, 112.93418090854225 (exact)[1][2] |
Unit-level coordinates (WGS 84):
- 1-1, 1-2, 2: 22.538499256116268, 112.93418090854225
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP |
---|---|---|---|---|---|
1-1 | Construction[2][3] | fossil gas: natural gas[4][2][3][5] | 50[2] | combined cycle[3] | yes[3] |
1-2 | Construction[2][3] | fossil gas: natural gas[4][2][3][5] | 50[2] | combined cycle[3] | yes[3] |
2 | Announced[2] | fossil gas: natural gas[2] | 50[2] | combined cycle[2] | yes[2] |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
1-1 | Guodian Investment (Jiangmen Xinhui) Smart Energy Co Ltd [100%][4][6] | China Power International Ltd [100.0%] |
1-2 | Guodian Investment (Jiangmen Xinhui) Smart Energy Co Ltd [100%][4][6] | China Power International Ltd [100.0%] |
2 | Guodian Investment (Jiangmen Xinhui) Smart Energy Co Ltd [100%][4][6] | China Power International Ltd [100.0%] |
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
This project is planned in two phases. Phase 1 (Unit 1 and Unit 2) officially entered the construction phase on September 30, 2022.[7] The Phase 1 is scheduled for operation in 2024.[8]
Articles and Resources
References
- ↑ http://www.jiangmen.gov.cn/hdjlpt/yjzj/answer/42739.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 "国家电投新会大泽2×50兆瓦级燃气热电项目首根钢架吊装". 2024-04-01. Archived from the original on 2024-05-07. Retrieved 2024-04-30.
- ↑ 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 https://www.xinhui.gov.cn/jmxhqdzz/gkmlpt/content/2/2707/post_2707745.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 4.0 4.1 4.2 4.3 4.4 https://web.archive.org/web/20220415213800/https://news.bjx.com.cn/html/20211213/1193316.shtml. Archived from the original on 2022-04-15.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.0 5.1 (PDF) https://web.archive.org/web/20220708194912/http://www.jiangmen.gov.cn/attachment/0/212/212142/2502172.pdf. Archived from the original (PDF) on 2022-07-08.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.0 6.1 6.2 http://www.xinhui.gov.cn/gzjg/qzfgzbm/jmsxhqfzhggj/tzgg/content/post_2584817.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "以"新会服务"创造"新会效益"!大泽项目建设开启加速度". 2022-10-01. Retrieved 2023-10-26.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "江门市能源发展十四五规划" (PDF). Retrieved 2023-10-26.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.