Guizhou Youshan cogen power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Guizhou Youshan cogen power station (贵州友山一期2×350MW超超临界燃煤发电项目) is a permitted power station in Chadian Town, Zhijin County, Bijie, Guizhou, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Guizhou Youshan cogen power station Chadian Town, Zhijin County, Bijie, Guizhou, China 26.885125, 105.735352 (approximate)
Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP
Unit 1 Permitted coal: unknown 350 ultra-supercritical yes
Unit 2 Permitted coal: unknown 350 ultra-supercritical yes

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Youshan New Materials Technology (Guizhou) Co Ltd Youshan New Materials Technology (Guizhou) Co Ltd
Unit 2 Youshan New Materials Technology (Guizhou) Co Ltd Youshan New Materials Technology (Guizhou) Co Ltd

Project-level coal details

  • Permit(s): 黔能源审〔2024〕366号

Background

The Guizhou Youshan project, which involves the construction of two 350MW ultra-supercritical coal-fired power units, is progressing through various regulatory stages. Key milestones include the environmental impact assessment (EIA) report's second public notice on December 5, 2024[1], and the Guizhou Provincial Ecological Environment Department is set to review the EIA approval opinions on January 7, 2025[2].

The project received approval from the provincial energy bureau on December 4, 2024 (黔能源审[2024]366 号), and the water and soil conservation plan was licensed by the Guizhou Provincial Water Resources Department on December 31, 2024[3]. The project land use was approved by the Zhijin local government in October 2024[4].

Articles and Resources

References

  1. "贵州友山一期2×350MW超超临界燃煤发电项目环境影响报告书环境影响评价第二次公示". 贵州省织金县人民政府网站. 2024-12-05. Retrieved 2025-09-18.{{cite web}}: CS1 maint: url-status (link)
  2. "贵州省生态环境厅2025年1月7日拟作出的建设项目环境影响评价文件(报告书)审批意见的公示(贵州友山一期2×350MW超超临界燃煤发电项目)". 贵州省生态环境厅网站. 2025-01-07. Retrieved 2025-09-18.{{cite web}}: CS1 maint: url-status (link)
  3. "贵州省水利厅关于贵州友山一期2×350MW超超临界燃煤发电项目水土保持方案的行政许可决定" (PDF). 2024-12-31. Retrieved 2025-09-18.{{cite web}}: CS1 maint: url-status (link)
  4. "织金县人民政府关于贵州友山一期2×350MW超超临界燃煤发电项目用地征地补偿安置公告". 贵州省织金县人民政府网站. 2024-10-29. Retrieved 2025-09-18.{{cite web}}: CS1 maint: url-status (link)