Gulei Petrochemical Base South Cogen power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Gulei Petrochemical Base South Cogen power station (古雷石化基地热电联产南部) is an operating power station of at least 130-megawatts (MW) in Gulei Town, Zhangpu, Zhangzhou, Fujian, China with multiple units, some of which are not currently operating. It is also known as 古雷石化基地热电联产南部一期 (Phase I Unit 1 & 2), 古雷石化基地热电联产南部二期 (Phase II Unit 3 & 4).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Gulei Petrochemical Base South Cogen power station Gulei Town, Zhangpu, Zhangzhou, Fujian, China 23.821626, 117.602719 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 23.821626, 117.602719

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Emergency/Backup
Phase I Unit 1 Operating[2] coal: unknown[1][3] 65[1] unknown yes[1] 2025[2] False
Phase I Unit 2 Operating[4] coal: unknown[1][3] 65[1] unknown yes 2025[4] False
Phase II Unit 3 Construction[5] coal: unknown[3][6] 75[6] unknown yes[6] 2026 (planned)[7] False
Phase II Unit 4 Construction[5] coal: unknown[3][6] 75[6] unknown yes[6] – False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase I Unit 1 Fujian Fuhaichuang Petrochemical Co Ltd [100%] Zhangzhou Jiulongjiang Group Co Ltd [37.8%]; Fujian Energy Petrochemical Group Co Ltd [26.8%]; unknown [16.6%]; Funeng Fuhua (Pingtan) Equity Investment Partnership LP [8.1%]; Bank of China Ltd [6.2%]; Fujian Gulei Petrochemical Equity Investment Partnership LP [4.4%]
Phase I Unit 2 Fujian Fuhaichuang Petrochemical Co Ltd [100%] Zhangzhou Jiulongjiang Group Co Ltd [37.8%]; Fujian Energy Petrochemical Group Co Ltd [26.8%]; unknown [16.6%]; Funeng Fuhua (Pingtan) Equity Investment Partnership LP [8.1%]; Bank of China Ltd [6.2%]; Fujian Gulei Petrochemical Equity Investment Partnership LP [4.4%]
Phase II Unit 3 Fujian Fuhaichuang Petrochemical Co Ltd [100%] Zhangzhou Jiulongjiang Group Co Ltd [37.8%]; Fujian Energy Petrochemical Group Co Ltd [26.8%]; unknown [16.6%]; Funeng Fuhua (Pingtan) Equity Investment Partnership LP [8.1%]; Bank of China Ltd [6.2%]; Fujian Gulei Petrochemical Equity Investment Partnership LP [4.4%]
Phase II Unit 4 Fujian Fuhaichuang Petrochemical Co Ltd [100%] Zhangzhou Jiulongjiang Group Co Ltd [37.8%]; Fujian Energy Petrochemical Group Co Ltd [26.8%]; unknown [16.6%]; Funeng Fuhua (Pingtan) Equity Investment Partnership LP [8.1%]; Bank of China Ltd [6.2%]; Fujian Gulei Petrochemical Equity Investment Partnership LP [4.4%]

Project-level coal details

  • Coal source(s): domestic/imported
  • Permit(s): 闽发改网审能源〔2022〕68号[6], 闽发改网审能源〔2022〕57号; 闽发改网审能源函〔2024〕41号[1]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

In 2024, Phase I Unit 1issued multiple procurement tenders for the EPC general contracting of the 2×65MW back-pressure turbine generator units[8][9].

In May 2025, Unit 1 successfully passed the 72+24 hour trial operation[10]. The project is part of the broader Zhangzhou Gulei Petrochemical Base cogeneration plan approved in November 2024[11].

Both Phase I units fully completed the 72+24 hour full-load trial operation and were formally commissioned by September 2025[12].

In January 2024, the Phase II project held its commencement ceremony[13].

By July 2024, comprehensive construction mobilization began, with concrete pouring documented[14].

In 2025, the project received approval for its general layout plan change in September[15].

In March 2026, the boiler ignition and blow-pipe work was completed[16].

Phase II Unit 4 achieved its first successful grid connection in April 2026[17].

Articles and Resources

References

  1. ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 https://news.bjx.com.cn/html/20220512/1224618.shtml. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.0 2.1 https://mp.weixin.qq.com/s/nmbauw0wzvgdo8aZLN6FQw. {{cite web}}: Missing or empty |title= (help)
  3. ↑ 3.0 3.1 3.2 3.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  4. ↑ 4.0 4.1 http://fjnyb.com/fjnyb/20251010/html/content_20251010002001.htm. {{cite web}}: Missing or empty |title= (help)
  5. ↑ 5.0 5.1 https://mp.weixin.qq.com/s/KX3lkisc2KAwbDrkX_zCKg. {{cite web}}: Missing or empty |title= (help)
  6. ↑ 6.0 6.1 6.2 6.3 6.4 6.5 6.6 https://news.bjx.com.cn/html/20220512/1224619.shtml. {{cite web}}: Missing or empty |title= (help)
  7. ↑ https://mp.weixin.qq.com/s/0n7yMQxLIjhSGq3EqVRNyw. {{cite web}}: Missing or empty |title= (help)
  8. ↑ "古雷石化基地热电联产南部一期项目2×65MW背压式汽轮发电机组及其配套设施EPC总承包烟道防腐材料采购招标公告". GWDT. 2024-08-02. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  9. ↑ "古雷石化基地热电联产南部一期项目2×65MW背压式汽轮发电机组及其配套设施EPC总承包项目管道管件及支吊架材料-三标段采购招标公告". GWDT. 2024-12-12. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  10. ↑ "古雷石化基地热电联产南部一期项目1号机组顺利通过72+24小时试运行". WeChat. 2025-05-03. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  11. ↑ "漳州古雷石化基地热电联产专项规划(2024-2030)". 福建省发展和改革委员会. 2024-11-05. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  12. ↑ "古雷石化基地热电联产南部一期项目两台65MW抽背式汽轮发电机组全部顺利完成72+24小时满负荷试运行". 福建能源报. 2025-10-10. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  13. ↑ "古雷石化基地热电联产南部二期项目开工仪式". WeChat. 2024-01-02. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  14. ↑ "能化古雷热电公司举行古雷石化基地热电联产南部二期项目全面动工动员大会". WeChat. 2024-07-31. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  15. ↑ "关于古雷石化基地热电联产南部二期项目(变更)总平面图的批前公示". 漳州古雷港经济开发区. 2025-09-30. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  16. ↑ "古雷石化基地热电联产南部二期项目5号锅炉点火吹管圆满完成". Baidu. 2026-03-27. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)
  17. ↑ "古雷石化基地热电联产南部二期项目4号机组首次并网一次成功". 电力网. 2026-04-26. Retrieved 2026-07-28.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.